Residential New Project

SRI DURGA BUILDERS

SRI DURGA BUILDERS & DEVELOPERS
GANGASTHAN 1, GANGASTHAN 1, KANTESHWAR, NIZAMABAD EAST (NEW), Nizamabad, PIN: 503002

Project Information

Project Name
SRI DURGA BUILDERS
Project Type
Residential
Project Status
New Project
Authority Name
DTCP
Plan Approval No.
3072/W1/2019/3814
Proposed Completion
01 Apr 2026
Last Modified
01 Oct 2020

Promoter Information

Promoter Name
SRI DURGA BUILDERS & DEVELOPERS
Promoter Type
Individual
Address
19,20,25,26,27, SR LILLY, Maruthi Nagar, GANGASTHAN-1 PARK

Land Details

Survey No.
261/EE,261/E,266/A,266/AA,266/E
Plot No.
19,20,25,26,27
Total Area
997.83
sq.m (10,741 sq.ft)
Net Area
997.83
sq.m (10,741 sq.ft)
Approved Built-up
2,876.26
sq.m (30,960 sq.ft)
Mortgage Area
261.46 sq.m
Total Building Units
1
Proposed Units
1

Property Boundaries

North
ROAD
South
NEIGHBOUR PLOTS
East
HOUSE
West
ROAD

Uploaded Documents 27

Encumbrance Details of encumbrances
Building Permit Commencement Certificates for each building in each phase
Resolution Copy of Board Resolution for appointment of Authorized Signatory in case of o...
Resolution Copy of Board Resolution for appointment of Authorized Signatory in case of o...
Document Incase these documents are under preparation at time of registration, please ...
Document Incase these documents are under preparation at time of registration, please ...
Declaration Declaration in FORM B
Declaration Declaration in FORM B
Legal Title Land Title Search Report from an advocate having experience of at least 10 years
Legal Title Land Title Search Report from an advocate having experience of at least 10 years
Legal Title Copy of the legal title report
Legal Title Copy of the legal title report
Document Incase these documents are under preparation at time of registration, please ...
Document Incase these documents are under preparation at time of registration, please ...
Document Incase these documents are under preparation at time of registration, please ...
Document Incase these documents are under preparation at time of registration, please ...
Document Incase these documents are under preparation at time of registration, please ...
Document Incase these documents are under preparation at time of registration, please ...
Legal Title Copy of the legal title report
Legal Title Copy of the legal title report
Legal Title Copy of the legal title report
Legal Title Copy of the legal title report
Layout Plan Letter of layout approval or Layout plan with a stamp of authority will also ...
Layout Plan Letter of layout approval or Layout plan with a stamp of authority will also ...
Building Plan Floorwise building plan approval need not be uploaded. Only 1 page IOD Note/A...
Building Plan Floorwise building plan approval need not be uploaded. Only 1 page IOD Note/A...
Completion Form–1A Architects certificate Overall completion of registered project
These documents were uploaded by the promoter to TG-RERA. Click any document to view or download the PDF.

Project Details

Item Proposed Booked Work Done (%)
Open Parking (In sqmts) 00 00 00%
Covered Parking ( In Numbers) 20 00 -

Construction Progress

# Activity Progress
1 Excavation
100%
2 X number of Basement(s) and Plinth
100%
3 X number of Podiums -
4 Stilt Floor -
5 X number of Slabs of Super Structure -
6 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises -
7 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises -
8 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. -
9 The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing -
10 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate -
11 Overall Percentage of Completion of the work done For the entire Building /Wing
20%

Bank Details

Bank Name
STATE BANK OF INDIA
Account Number
*******9330
Branch
GANGASTHAN
Ifsc
SBIN0020996

Common Areas & Facilities

Facility / Amenity Available Details
Copy of the legal title report View -
Copy of the legal title report View -
Copy of the legal title report View -
Copy of Approval Layout Plan View -
Proforma of the allotment letter and agreement for sale View -
Proforma of the allotment letter and agreement for sale View -
Proforma of the allotment letter and agreement for sale View -
Proforma of the allotment letter and agreement for sale View -
Declaration in FORM B View -
Copy of Sanctioned Building Plan View -
Land Title Search Report from an advocate having experience of at least 10 years View -
Copy of Board Resolution for appointment of Authorized Signatory in case of other than individual View -

Location

District
Mandal
NIZAMABAD EAST (NEW)
Village
KANTESHWAR
Locality
GANGASTHAN 1
Street
GANGASTHAN 1
PIN Code
503002

Registration Status

27 Documents Uploaded
Full Details Available

Need Complete Property Verification?

Get ownership details, EC records, survey sketch, zone checks, geo-insights & AI analysis - all in one place

Ownership Details
EC Records
Survey Sketch
Zone Checks
Geo-Insights
AI Analysis
Try VerifyMyLand Now ✨ Get comprehensive property verification in minutes

Verify Your Property Before You Buy

AI-powered legal due diligence — title verification, encumbrance checks, zoning compliance, and risk assessment in minutes. Catch issues before they cost you crores.