Residential

RAGHAVENDRAS MIRRA PANCHAJANYA

Raghavendra Neelima Constructions
JPN Nagar, JPN Nagar, Serilingampally, Ranga Reddy, PIN: 500049

Project Information

Project Name
RAGHAVENDRAS MIRRA PANCHAJANYA
Project Type
Residential
Authority Name
GHMC
Plan Approval No.
1/C12/07829/2018
Proposed Completion
26 May 2024
Last Modified
13 Sep 2023

Promoter Information

Promoter Name
Raghavendra Neelima Constructions
Promoter Type
Individual
Address
3-6-475/3/1, Kalpavruksha Estates, Himayatnagar, Himayatnagar

Land Details

Survey No.
120,121 & 122 of miyapur &sy no.12,13 ramannaguda village.
Total Area
15,855.31
sq.m (170,667 sq.ft)
Net Area
15,855.31
sq.m (170,667 sq.ft)
Approved Built-up
76,750.28
sq.m (826,140 sq.ft)
Mortgage Area
5,638.03 sq.m
Total Building Units
5
Proposed Units
5

Property Boundaries

North
60 Wide Road Left Side Mirra Hospital B K Enclave
South
Neelima Greens
East
Neelima Greens and B K Enclave
West
Sy No 166 P of HUDFA of Hafeezpet v 189 P Madinagu

Uploaded Documents 21

Legal Title Copy of the legal title report
Encumbrance Details of encumbrances
Document Incase these documents are under preparation at time of registration, please ...
Document Incase these documents are under preparation at time of registration, please ...
Declaration Declaration in FORM B
Building Plan Floorwise building plan approval need not be uploaded. Only 1 page IOD Note/A...
Building Plan Floorwise building plan approval need not be uploaded. Only 1 page IOD Note/A...
Building Plan Floorwise building plan approval need not be uploaded. Only 1 page IOD Note/A...
Building Plan Floorwise building plan approval need not be uploaded. Only 1 page IOD Note/A...
Building Plan Floorwise building plan approval need not be uploaded. Only 1 page IOD Note/A...
Building Plan Floorwise building plan approval need not be uploaded. Only 1 page IOD Note/A...
Building Plan Floorwise building plan approval need not be uploaded. Only 1 page IOD Note/A...
Building Plan Floorwise building plan approval need not be uploaded. Only 1 page IOD Note/A...
Layout Plan Letter of layout approval or Layout plan with a stamp of authority will also ...
Layout Plan Letter of layout approval or Layout plan with a stamp of authority will also ...
Building Plan Floorwise building plan approval need not be uploaded. Only 1 page IOD Note/A...
Building Plan Floorwise building plan approval need not be uploaded. Only 1 page IOD Note/A...
Building Plan Floorwise building plan approval need not be uploaded. Only 1 page IOD Note/A...
Building Plan Floorwise building plan approval need not be uploaded. Only 1 page IOD Note/A...
Building Permit Commencement Certificates for each building in each phase
Building Permit Commencement Certificates for each building in each phase
These documents were uploaded by the promoter to TG-RERA. Click any document to view or download the PDF.

Project Details

Item Proposed Booked Work Done (%)
Open Parking (In sqmts) - - -
Covered Parking ( In Numbers) 620 - -

Promoter / Land Owner / Investor Details 2

Name Type Agreement
Sri. Sardar Bimal Singh Individual AreaShare
Smt. Reshma Kaur Individual AreaShare

Construction Progress

# Activity Progress
1 Excavation
100%
2 X number of Basement(s) and Plinth
100%
3 X number of Podiums
100%
4 Stilt Floor
100%
5 X number of Slabs of Super Structure
100%
6 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises
100%
7 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises
100%
8 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.
100%
9 The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing
100%
10 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate
100%
11 Overall Percentage of Completion of the work done For the entire Building /Wing
100%

Bank Details

Bank Name
RAGHAVENDRA NEELIMA CONSTRUCTIONS MASTER-HDFC BANK
Account Number
**********7649
Branch
HIMAYATH NAGAR
Ifsc
HDFC0000081

Professional Information

Professional Name
ZAKI AHMED
Telanganarera Certificate No
NA
Professional Type
Structural Engineer
Professional Name
N SUNIL KUMAR
Telanganarera Certificate No
NA
Professional Type
Architect

Common Areas & Facilities

Facility / Amenity Available Details
Copy of Approval Layout Plan View -
Commencement Certificate/ Building permit View -
Copy of Sanctioned Building Plan View -
Copy of Sanctioned Building Plan View -
Copy of Sanctioned Building Plan View -
Copy of Sanctioned Building Plan View -
Copy of Sanctioned Building Plan View -
Copy of Sanctioned Building Plan View -

Location

District
Mandal
Serilingampally
Locality
JPN Nagar
Street
JPN Nagar
PIN Code
500049

Registration Status

21 Documents Uploaded
Full Details Available

Need Complete Property Verification?

Get ownership details, EC records, survey sketch, zone checks, geo-insights & AI analysis - all in one place

Ownership Details
EC Records
Survey Sketch
Zone Checks
Geo-Insights
AI Analysis
Try VerifyMyLand Now ✨ Get comprehensive property verification in minutes

Verify Your Property Before You Buy

AI-powered legal due diligence — title verification, encumbrance checks, zoning compliance, and risk assessment in minutes. Catch issues before they cost you crores.