Order Details
| Order Type | TG-RERA Authority |
|---|---|
| Complaint/Case Number | Complaint No.237 of 2024 |
| Year | 2024 |
| Order Category | Regular Order |
| Order Date | 27 Mar 2025 |
| Complainant | (H.no.5-96/154, Road no.7, Harivillutownship, Patelguda, Ameenpur, Sangareddy- 502319) |
| Respondent | (rep KakarlaSrinivas-plot no. 140,141, Eminent plaza, KPHB Colony, KukatpallyHyderabad) |
| PDF Document | Download PDF BU_050425122343417.pdf |
Full Order Text
BEFORE TELANGANA REAL ESTATE REGULATORY AUTHORITY
[Under the Real Estate (Regulation and Development) Act, 2016]
Complaint No. 237 of 2024
Dated: 27th March 2025
Corum:
Dr. N. Satyanarayana, IAS (Retd.), Hon’ble Chairperson
Sri K. Srinivasa Rao, Hon’ble Member
Sri Laxmi Narayana Jannu, Hon’ble Member
Gatta Soumya
(H.no.5-96/154, Road no.7, Harivillutownship, Patelguda, Ameenpur, Sangareddy- 502319)
…Complainant
Versus
M/s Jayathri Infrastructure India Pvt Ltd
(rep KakarlaSrinivas-plot no. 140,141, Eminent plaza, KPHB Colony, KukatpallyHyderabad)
…Respondent
The present matter filed by the Complainant herein came up for hearing on
11.12.2024 before this Authority wherein the Complainant appeared in person. Despite
service of notice, the Respondent failed to appear, and as such, was set ex parte vide order
dated 11.12.2024, and after hearing the Complainant, this Authority passes the following
ORDER:
2.
The present Complaint has been filed by the Complainant under Section 31 of the
Real Estate (Regulation & Development) Act, 2016 (hereinafter referred to as the “Act”) read
with Rule 34(1) of the Telangana Real Estate (Regulation and Development) Rules, 2017
(hereinafter referred to as the “Rules”) seeking appropriate relief(s) against the Respondent.
A.
The Brief facts of the case as per allegations/averments contained in the complaint are
as follows:
3.
The Complainant states that he has paid an amount of Rs. 9,00,000/- (Rupees Nine
Lakhs only) as a booking amount towards the purchase of a commercial unit in the project
titled "Western Galaxy", comprising a total area of 200 square feet, identified as Office No.
10/B, located on the 2nd floor, having a total built-up area of 1,00,000 square feet, along with
an undivided share of land admeasuring 3.2 square yards (out of Ac. 4 Acres), situated in
1 of 5
Survey No. 36/20, Gopanpally village, Serilingampally Mandal, GHMC, Serilingampally
Circle, Ranga Reddy District.
4.
As per the Memorandum of Understanding (MOU) dated 28.04.2021, the Respondent
undertook to register a plot as collateral security in favor of the Complainant until the time
possession of the office space is handed over. Upon the handover of the scheduled property,
the Complainant was required to return the collateral plot to the Respondent.
5.
As per the MOU, the Respondent assured that a fully constructed commercial
property would be handed over to the Complainant by December 2024.
6.
However, the Respondent has failed to deliver possession of the scheduled property
within the stipulated time, thereby violating the contractual terms and causing financial loss
and hardship to the Complainant.
B. Relief(s) Sought
7.
Aggrieved by the acts of the Respondent, the Complainant prays for the following
reliefs:
a. An order directing the Respondent to refund the amount of Rs. 9,00,000/- (Rupees
Nine Lakhs only) to the Complainant along with interest.
C. Observations of the Authority:
Points for Consideration:
1. Whether the Respondent has violated section 3 of the Real Estate (Regulation and
Development) Act, 2016?
2. Whether the Complainant is entitled to the relief sought?
Point 1
8.
This Authority notes that over 20 similar complaints have been filed against the same
Respondent concerning the same project. In prior proceedings, the Respondent’s counsel
submitted that due to non-compliance with the Agreement of Sale entered into with Sri M.
Laxmi Kanthai and Sri V. Gowrith on 25.03.2021, a portion of the project land is under
litigation before the Hon’ble Supreme Court, thereby preventing the commencement of the
2 of 5
project. Consequently, the said project has not been registered under RERA.In Complaint No.
1037 of 2023 & batch matters, this Authority directed an inspection of the concerned project
site through the Engineering Staff College of India (ESCI) vide Letter No.
1458/2023/TSRERA dated 10.10.2023. As per the ESCI report (ESCI/PD/TSRERA/07/202324) dated 01.12.2023, the project site remains vacant with no progress. There is no evidence
to establish the Respondent’s ownership or legal authority to undertake the project.
9.
Further, this Authority has previously imposed a penalty of Rs. 36,70,000/- for
contravening section 3 of the RE(R&D) Act, 2016 on the Respondent in Complaint No. 1037
of 2023 & batch matters, dated 12.08.2024.. Since the penalty has already been imposed in
the aforementioned order, this Authority does not find it necessary to impose an additional
penalty under Section 3 of the RE(R&D)Act.Thus, Point 1 is answered accordingly.
Point 2:
10.
The Complainant has sought either the registration of the allotted unit or a refund of
the amount paid. However, as the project does not exist anymore, the relief of registration of
the unit cannot be granted. Consequently, the request for a refund of the amount along with
interest merits consideration.The Respondent has failed to fulfil its contractual obligations.
Section 18(1) of the Act provides that if a promoter fails to complete or is unable to give
possession of an apartment or commercial space as per the terms of the agreement, the
allottee has an unqualified right to seek a refund of the paid amount along with interest.
11.
The provision for refund with interest applies when the promoter fails to complete the
project and the allottee wishes to withdraw. The allottee is entitled to interest to safeguard
their interests if the promoter fails to perform their obligations and is unable to hand over
possession.
12.
Attention is drawn to the decision of the Hon'ble Supreme Court of India in Civil
Appeal Nos. 3581-359 of 2022, Civil Appeal Diary No. 9796/2019, M/s Imperia Structures
Limited vs. Anil Patni & Others, wherein it was held:
"In terms of Section 18 of the RERA Act, if a promoter fails to complete or
is unable to give possession of an apartment by the date specified in the
agreement, the promoter would be liable, on demand, to return the
amount received in respect of that apartment if the allottee wishes to
3 of 5
withdraw from the project. Such a right of the allottee is 'without
prejudice to any other remedy available to him'. This right is unqualified,
and if availed, the deposited money must be refunded with interest as
prescribed. The proviso to Section 18(1) contemplates that if the allottee
does not intend to withdraw from the project, they are entitled to interest
for every month of delay until possession is handed over. The allottee may
proceed under Section 18(1) or the proviso thereto."
13.
Similarly, in Civil Appeal Nos. 6745-6749 of 2021, M/s Newtech Promoters and
Developers Private Limited vs. State of UP & Others, the Hon’ble Supreme Court observed:
"Section 18(1) of the Act spells out the consequences if the promoter
fails to complete or is unable to give possession of an 9 of 10
apartment, plot, or building in terms of the agreement for sale. The
allottee/home buyer holds an unqualified right to seek a refund of the
amount with interest as prescribed."
14.
Based on the records available, the averments made by the Complainant, and the
history of the Respondent’s violations, it is evident that the Respondent has kept several
complainants on hold for years by making false assurances regarding the registration of
commercial spaces in their names. It is pertinent to note that M/s Jayathri Infrastructures has
consistently violated the Act by misleading the public in multiple projects, thereby
demonstrating mala fide intent.
15.
Therefore, considering the aforementioned case laws and the provision of Section 18
of the RE(R&D) Act, this Authority is of the opinion that the Complainant, having invested a
substantial sum in anticipation of acquiring the allotted commercial space, has been
wrongfully deprived of their rights due to the Respondent’s absolute failure to execute the
project. Consequently, the Complainant is entitled to the relief sought, which includes a full
refund of the amount paid along with applicable interest.
16.
The Respondent is directed to refund the entire amount paid by the Complainant,
along with interesti.e Current Highest marginal cost of State Bank of India (9%) plus 2% that
is 11% per annum, calculated from the date of the Memorandum of Understanding (MOU)
entered into with the Complainant until the date of actual realization. This repayment shall be
completed within 90 days from the date of this order.
4 of 5
17.
The Complainant shall return any collateral land, if applicable, to the Respondent
immediately upon receipt of the refunded amount, inclusive of interest.
E. Directions of the Authority:
18.
In light of the findings of the Authority as recorded above, the following directions
are issued under Section 37 of the RE(R&D) Act to ensure compliance with the obligations
imposed upon the promoter as per the functions entrusted to the Authority under Section
34(f) of the RE(R&D) Act:
a. The Respondent is directed to refund the entire amount paid by the complainant for
the commercial spaces/units in the project "Western Galaxy" as mentioned above,
along with interest of 11% per annum from the date of the Memorandum of
Understanding (MOU) entered into with complainant, until the date of actual
realization.
b. The refund of the entire amount shall be paid by the Respondent to the complainant
within a period of 90 days from the date of this Order.
c. The complainantsshall return the collateral land, if applicable, to the Respondent
immediately upon receipt of the refunded amount, inclusive of interest.
19.
In light of the above findings and directions, the present complaint stands disposed of.
The parties shall bear their own costs. The parties are hereby informed that failure to comply
with this Order shall attract Section 63 of the RE(R&D) Act.
SdSri. K. Srinivas Rao,
Hon’ble Member
TG RERA
SdSri. Laxmi NaryanaJannu,
Hon’ble Member
TG RERA
SdDr. N. Satyanarayana, IAS (Retd.),
Hon’ble Chairperson
TG RERA
5 of 5
Related Orders
Interim Order Complaint No.228 of 2025
Rangareddy, Telangana, 500077)Order Complaint No. 386 of 2025
Koti, Hyderabad-500027.Order Complaint No. 153 of 2024
Telangana – 500011.Order Complaint No. 152 of 2024
Telangana – 500011.Order Complaint No. 151 of 2024
Telangana – 500011.Need Complete Property Verification?
Get ownership details, EC records, survey sketch, zone checks, geo-insights & AI analysis - all in one place