TG-RERA Authority

Order Complaint No. 821 Of 2021

30 Dec 2023
TG-RERA Authority
1 Pages

Order Details

Order Type TG-RERA Authority
Complaint/Case Number Complaint No. 821 Of 2021
Order Category Regular Order
Order Date 30 Dec 2023
Complainant Maintenance Co-Operative Society
Respondent rep. through Sri Ravinder Reddy
PDF Document Download PDF BU_090124181707671.pdf

Full Order Text

BEFORE TELANGANA STATE REAL ESTATE REGULATORY AUTHORITY
[Under the Real Estate (Regulation and Development) Act, 2016]
COMPLAINT NO.821 OF 2021
30th Day of December, 2023
Corum:

Dr. N. Satyanarayana, IAS (Retd.), Hon’ble Chairperson
Sri K. Srinivasa Rao, Hon’ble Member
Sri Laxmi Narayana Jannu, Hon’ble Member

Rock Gardens Flat Owners Welfare &
Maintenance Co-Operative Society

…Complainant
Versus

M/s Rainbow Builders
rep. through Sri Ravinder Reddy

…Respondent

The present matter filed by the Complainant herein came up for hearing on
09.08.2023, 29.08.2023, 21.09.2023, 19.10.2023 and 16.11.2023 before this
Authority in the presence of the Advocate, Mr. Deepak Chowdhary along with Office
bearers of the Complainant Association, and Sri Maram Ravinder Reddy on behalf
of the Respondent Builder/Developer, and upon hearing the arguments of both the
parties, this Authority passes the following ORDER:

2.

The present Complaint has been filed under Section 31 of the Real Estate

(Regulation and Development) Act, 2016 (hereinafter referred to as the “Act”) read
with Rule 34(1) of the Telangana Real Estate (Regulation and Development) Rules,
2017 (hereinafter referred to as the “Rules”) seeking the following reliefs against the
Respondent Builder:

“(i) direct the respondent to register the Residential Project under the name “Rock
Gardens” situated on Plot bearing Nos.155/P, 156, 157, 158, 159, 160, 161, 162,

1 of 10

163, 164, 165, 166, 167, 168 amd 169, forming part of Sy.Nos. 300 to 303, 306 to
311

and

313

to

315

in

“MARWA

TOWNSHIP-B”,

Narsingi

Village

and

Grampanchayat, Gandipet Mandal (erstwhile Rajendranagar), Ranga Reddy District,
Telangana with this Hon’ble Authority,
(ii) to appoint a registered Architect to evaluate the pending works of the Residential
Project,
(iii) direct the Respondent to deposit the entire expenditure/cost to be incurred for
completion of the pending works (amenities) into the account of the Complainant
Association so as to enable the Complainant Association to complete the works by
appointing a civil contractor,
(iv) direct the Respondent to deposit the amount of Rs.80,00,000/- as agreed under
Clause 26 of the MoU, dated 22.01.2021 along with the interest rate of 12% per
annum till the date of realisation,
(v) direct the Respondent to deposit the amount collected as corpus fund from each of
the allottees at the time of execution of the Sale Deed collectively into the account of
the Complainant association,
(vi) to restraint the Respondent from unauthorized conversion of the space allocated
for entrance access to cellar and its adjacent parking space on the ground floor for
any other purpose, which is in contravention of the sanction plan,
(vii) punish the Respondent for contravention of Section 3 r/w Section 4(1) of the Act,
2016 and the Rules 2017 envisaged therein,
(viii) and pass such other order or orders as this Hon’ble Authority may deem fit and
proper in the circumstances of the case.

A. Brief facts of the case:
3.

That the Complainant is a society formed by the Individual Flat Owners of

the Apartment Complex namely, “Rock Gardens” under the provisions of Telangana

2 of 10

Societies Registration Act, 2019 vide Reg. No.3600236/238 under the name and
style of “Rock Gardens Flat Owners Welfare & Maintenance Co-Operative Society”.
The Complainant Association submits that the Respondent is primarily engaged in
the business of construction of buildings, apartments, individual houses, land
development, civil contracts, etc., running under the name and style of “Rainbow
Builders”, a registered partnership firm registered under Section 63 of the Indian
Partnership Act, 1932, bearing Registration No.4250/2015, having its registered
office at H.No.3-12/23, Kalpana Kennel Road, Bhaskar Rao Nagar, Puppalaguda,
Gandipet Mandal (erstwhile Rajendra nagar mandal), Ranga Reddy District,
Telangana. The Respondent is represented by its Partners, Sri Maram Reddy,
Ravinder Reddy, S/o Sri Thirupathaiah (Managing Partner) and Smt. Maram Reddy
Vani Reddy W/o Maram Reddy Ravinder Reddy (Partner), both residents of Flat
No.101 & 102, Gold Stone Prime, Road No.13, Alkapoor Township, Puppalguda
Village, Gandipet Mandal, (erstwhile Rajendra nagar mandal), Ranga Reddy
District, Telangana.

4.

They further submitted that the Respondent Firm is the absolute owner and

possessor of the land admeasuring and extent of 4,632 Sq Yds bearing Plot
Nos.155/P, 156, 157, 158, 159, 160, 161, 162, 163, 164, 165, 166, 167, 168 amd
169, forming part of Sy. Nos. 300 to 303, 306 to 311 and 313 to 315 in “MARWA
TOWNSHIP-B”, Narsingi Village and Grampanchayat, Gandipet Mandal (erstwhile
Rajendranagar), Ranga Reddy District, Telangana. That in the year 2017, the
Respondent sought and was granted HMDA Permissions for the said plot for the
construction of Residential Apartment Complex comprising of Sub-cellar + Cellar +
Ground + 5 Floors, vide HMDA Permit No.00181/SKP/R1/U6/HMDA/02082016
dated 29.07.2017. That the Apartment Complex consists of two individual blocks

3 of 10

and each block consists of two separate access stairs and two individual lift facility
as per design plan of the project.

5.

The Complainant submits that provisions of the Act of 2016 and the Rules

thereunder are applicable to all Real Estate Projects across the State, whose
building permissions are approved on or after 01.01.2017 by the Competent
Authorities, viz., UDA/DTCP/Municipal Corporations, etc., and that the Project is
“on-going” as per the Rules, 2017.

6.

The Complainant Association submits that the Respondent has violated Rule

3 and 4 of the Rules, 2017 and also failed to adhere to the orders issued by this
Authority by extending the time for registration of ongoing projects. He submits
that Respondent has deliberately entered into Agreement of Sale with various
allottees in the project without adhering to the specific common timeline for
completion of the project. Further, he submits that, it appears from the agreement
of sale entered with the various allottees/purchasers of the project, the Respondent
has intentionally indicated different timelines only to mislead and falsely
warrant/lure the allottees for entering into agreement of sale for the purpose of
individual flats constructed in the building complex.

7.

The Association also submits that the Respondent has sold close to 90% of

the flats to various individual allottees and executed conveyance/sale deeds in
favour of the Allottees and around 50% of the allottees have taken possession of
their respective flats and have been utilising the same for living purposes. Till date
despite the repeated reminders, personal meetings with the Respondent, the status
of the activities in the project has come to a standstill. That only after repeated
reminders, the Respondent has installed lift provision with a delay of almost one

4 of 10

year from the date of possession and several other issues with respect to the
activities promised to be undertaken by the Respondent.

8.

The Complainant Association further submits that the Respondent has

already collected Rs.4,50,000/- and additional amount of Rs.50,000/- on account
of Corpus Fund in the form of cash from each of the Allottees at the time of
execution of conveyance/sale deed in favour of each of the allottee for the purpose
of providing amenities. Whereas, till date the Respondent has not taken any steps
to provide the same. Further, the Respondent entered into an MoU dated
22.02.2021 and thereby agreed to complete all the pending amenities within a
period of two months from the date of execution of the MoU. It was also agreed by
the Respondent that in case of default on his part, Rs.80,00,000/- shall be paid by
him to the Complainant Association as compensation with interest @ 12%.

9.

Further, they submit that the Respondent is planning to cover the space

allocated for entrance access to cellar and its adjacent parking space on the ground
floor for the purpose of sale to third parties in order for them to convert it into a
commercial space in contravention of the Sanction Plan and violative of the
provisions of the Act, 2016. Aggrieved by the same, the Complainant filed the
present complaint on 13.12.2021.

B. Notices issued:
10.

Accordingly, vide Notice dated 24.01.2022, this Authority directed the

Respondent to submit a reply along with such other information with regard to the
Project. Further, on the same day, i.e., on 24.01.2022, this Authority also issued
Show Cause Notice as to why penalty ought not to be issued upon the Respondent
for violation of Section 3 & 4 of the Act, 2016.

5 of 10

11.

Subsequently, another Show Cause Notice dated 12.05.2023, was issued to

the Respondent seeking explanation as to why this Authority shall not levy penalty
under Section 63 of the Act, 2016 for failing to comply with and contravening the
orders or directions of the Authority. The same was returned, notice was
incomplete.

C. Interim and Penalty Order:
12.

Again, Summons dated 01.08.2023 was issued to the parties to appear

before the Hon’ble Authority for hearing in the matter on 09.08.2023. Accordingly,
the Complainant Association represented by its Advocate, Mr. Deepak Chowdhary
along with office bearers of the Complainant Association appeared on 09.08.2023,
but there was no representation on behalf of the Respondent on the said day as
notice was incomplete.

13.

On the said day, the Complainant Association reiterated the contentions

raised in the complaint and sought for time to file additional documents such as
pending works, ECs, etc. It was prayed that interim orders may be passed
restraining the Respondent to register any further flats as the Respondent failed to
register before RERA, failed to provide amenities as promised under the Agreement
of Sale and also obtained Occupancy Certificate without completing the pending
works. They added that 63 out of 68 flats have already been sold causing grave
injustice to the said allottees. Accordingly, matter was adjourned to 29.08.2023
seeking the Respondent’s reply. A Notice dated 10.08.2023 was again issued to the
Respondent, however the same was returned on 27.08.2023 with a note “left
address”.

6 of 10

14.

On 29.08.2023, the Respondent did to appear as notice was incomplete

before this Authority and the Complainants submitted that only 2 out of 68 flats
are left and the rest of them have been sold by the Respondent Builder without
registering before this Authority.

15.

Therefore, upon consideration of the facts and circumstances of the present

case, this Authority issued an Interim Order dated 29.08.2023 restraining the
Respondent Builder, not to register/alienate any further flats without submitting
an Application of registration before this Authority and until the present matter is
disposed of. This Authority also issued Penalty Order dated 29.08.2023 imposing a
penalty of Rs.9,90,000/- (Rupees Nine Lakhs and Ninety Thousand Only) under
Section 59 for violation of Section 3 & 4 of the of the Act, 2016.

D. Reply by the Respondent:
16.

Subsequently, the matter came up for hearing on 21.09.2023, 19.10.2023

and 16.11.2023 and Sri Maram Ravinder Reddy on behalf of the Respondent
Builder appeared and filed a Reply dated 10.10.2023 and 20.10.2023 stating that
M/s Rainbow Builders, initiated a residential project approved by HMDA. The
project consists of 2 Cellar + 1 Ground + 5 Upper Floors, located on plot Nos: 155
to 169, as per approval vide: 000181/SKP/R1/U6/HMDA/02082016 dated 2/8
/2016.

17.

Thereafter,

Respondent

promptly

applied

for

RERA

Registration

in

accordance with Section 3(1) & 4(1) with application No: REA02400001060. He
submitted all the required documents, however, due to a lack of communication
from one of the Respondents’ employees regarding document shortfalls, they did
not receive RERA approval. He submitted that he agrees to pay the penalty amount

7 of 10

of Rs.9,90,000/-(Rupees Nine Lakhs and Ninety Thousand Only) in due time and
submit all the required shortfall documents and request your esteemed office to
consider these documents and proceed with the registration of the project under
TSRERA.

18.

He submitted that in the course of this project, the Respondent Builder

initiated construction activities and successfully sold units to family members and
a close-knit group of friends. The construction was completed in compliance with
HMDA norms, and that Occupancy Certificate was obtained on 08.04.2022 vide
000596/OC/HMDA/SKP/2022.

19.

After

hearing

was

conducted

on

19.10.2023

and

16.11.2023,

the

Respondent categorically submitted that following activities shall be completed by
him:

a. Solar fencing to the entire compound wall of the subject matter building, as
per physical condition.
b. Children play equipment will be provided and installed on designated place
in the building.
c. Complete building external painting of one coat will be completed.
d. Car parking slots will be allotted on the basis of serial allotting, starting from
northeast of the cellar 2 to cellar 1. Carparking serial number will be
starting from ground floor to Fifth floor. As per the sale deed respective flat
owner will be entitled to respective slots.

20.

Therefore, he prayed to approve the registration of the Project “Rock

Gardens” and further to cancel the Interim Order dated 29.08.2023 issued

8 of 10

restraining the Respondent Builder to alienate/sell any flats in the Project and
accordingly permit him to proceed with the sale and registration of the remaining
units without causing any inconvenience to the customers. He also requested this
Authority to allow him and his workers to visit the building and complete the above
committed works.

21.

He added that after the said allocation of car parking to the respective

owners, the said remaining parking slots will belong to the Respondent Builder and
the same can be sold to the requested members of the Project on agreed sale
consideration. In this regard, he sought direction from this Authority to all the
allottees of the Project to cooperate in completing this process is hassle free, and to
complete all this, the Respondent Builder sought 6 (six) months’ time i.e., on or
before 30.04.2024 on account of his current financial situation.

22.

The Complainants, vide Memo dated 28.11.2023 filed their written

submissions reiterating the contents of their Complaint and Rejoinder and seeking
prayers as mentioned therein.

E. Observations Directions of the Authority:
23.

This Authority has heard the matter at length and considered the

contentions of both the parties. In accordance thereof, the following directions are
issued to the Respondent Builder as well as the Complainant Association:
a. As there is ample parking space more than the constructed flats, the
Respondent Builder, as promised, is directed to conduct lottery for allotment
of car parking spaces to the individual flat owners in the presence of Flat
Owners Association as promised in the Agreement of Sale for which amount
was also collected.

9 of 10

b. As the Complainant Association/Flat Owners have already occupied flats
and living there they are bound to pay the maintenance for the smooth
functioning of community.
c. If any amounts are due to the Respondent (Builder) by the Complainant/Flat
Owners as per the statement of the Respondent during hearing in the
presence of the Complainant Association, the Complainant Association is
directed to pay the said amounts to the Respondent Builder within 60 days
of the receipt of this Order.
d. The Complainants are also directed to allow the Respondent Builder and his
workmen to enter into the Project premises to complete the pending works.
e. The tot-lot equipment to be installed and landscape to be maintained.
f. Solar fencing as promised by the Respondent Builder to be completed.
Regarding this a fresh Memorandum of Understanding may be made
between the Developer and the Association with time bound period.
g. The Respondent Builder shall complete all these pending works on or before
30.04.2024 as promised by him in the Letter submitted on 20.10.2023.
24.

In lieu of the above-mentioned directions, the present complaint stands

disposed of. The parties are hereby informed that failure to comply with this Order
shall attract Section 63 of the Act, 2016.
25.

If aggrieved by this Order, the parties may approach the TS Real Estate

Appellate Tribunal (vide G.O.Ms.No.8, Dt.11-01-2018, the Telangana State Value
Added Tax Appellate Tribunal has been designated as TS Real Estate Appellate
Tribunal to manage the affairs under the Act till the regular Tribunal is established)
within 60 days from the date of receipt of this Order.

Sd/Sri K. Srinivasa Rao,
Hon'ble Member,
TS RERA

Sd/Sri Laxmi Narayana Jannu,
Hon'ble Member,
TS RERA

Sd/Dr. N. Satyanarayana, IAS (Retd.),
Hon'ble Chairperson,
TS RERA

10 of 10

Related Orders

Interim Order Complaint No.228 of 2025
Rangareddy, Telangana, 500077)
15 Apr 2026
Order Complaint No. 386 of 2025
Koti, Hyderabad-500027.
09 Apr 2026
Order Complaint No. 153 of 2024
Telangana – 500011.
08 Apr 2026
Order Complaint No. 152 of 2024
Telangana – 500011.
08 Apr 2026
Order Complaint No. 151 of 2024
Telangana – 500011.
08 Apr 2026

Need Complete Property Verification?

Get ownership details, EC records, survey sketch, zone checks, geo-insights & AI analysis - all in one place

Ownership Details
EC Records
Survey Sketch
Zone Checks
Geo-Insights
AI Analysis
Try VerifyMyLand Now ✨ Get comprehensive property verification in minutes

Verify Your Property Before You Buy

AI-powered legal due diligence — title verification, encumbrance checks, zoning compliance, and risk assessment in minutes. Catch issues before they cost you crores.