TG-RERA Authority

Order Complaint No. 49 of 2024

14 Nov 2024
TG-RERA Authority
1 Pages

Order Details

Order Type TG-RERA Authority
Complaint/Case Number Complaint No. 49 of 2024
Year 2024
Order Category Regular Order
Order Date 14 Nov 2024
Complainant Sri Ganapathi P. Gorekar
Respondent M/s Aliens Developers Pvt.Ltd
PDF Document Download PDF BU_211224133609052.pdf

Full Order Text

BEFORE TELANGANA REAL ESTATE REGULATORY AUTHORITY
[Under the Real Estate (Regulation and Development) Act, 2016]
COMPLAINT NO. 49 OF 2024
Corum:

14th November, 2024
Dr. N. Satyanarayana, IAS (Retd.),Hon’ble Chairperson
Sri Laxmi Narayana Jannu, Hon’ble Member
Sri K. Srinivasa Rao, Hon’ble Member

Sri Ganapathi P. Gorekar

…Complainant

Versus
M/s Aliens Developers Pvt.Ltd

…Respondent

The present matter filed by the Complainant herein came up for final
hearing on 07.08.2024 before this Authority in the presence of Complainant
present in person and Respondent counsel Jasmin Kaur and upon hearing
the arguments of the party, this Authority passes the following ORDER:
2.

The present Complaint has been filed under Section 31 of the Real

Estate (Regulation and Development) Act, 2016 (hereinafter referred to as the
“RE(R&D) Act” read with Rule 34(1) of the Telangana Real Estate (Regulation
and Development) Rules, 2017 (hereinafter referred to as the “Rules”) seeking
directions from this Authority to take action against the Respondent.
A. Brief Facts on Behalf of the Complainant:
3.

The complainant initially booked a flat in Aliens Space Station,

Tellapur, Hyderabad, in 2012.Due to a lack of progress in the construction of
the originally booked flat, the complainant, at the request of the Developers,
changed the booking to Station No. 11, Flat No. 1865.
4.

An Agreement of Sale for the newly booked flat was entered into on

17.02.2016, with a total consideration of Rs. 67,00,000/- (excluding
applicable taxes).The Sale Deed and Construction Agreement were executed
and registered on 01.07.2016 and 02.07.2016, respectively.The complainant
has paid Rs. 63,75,951/- towards the cost of the flat (more than 95% of the
total consideration) and Rs. 4,18,356/-

towards applicable taxes.The

remaining amount is to be paid based on the progress of the work or at the
1 of 11

time of possession.The construction has only reached the structural frame
level; the finishing work is yet to be started and completed.
5.

As per the Agreement of Sale, possession of the flat was to be delivered

within three years from the date of the Agreement, i.e., by December 2017.The
Developers have repeatedly assured the complainant that the finishing work
will be completed and possession will be handed over once funds/loans are
sanctioned. This assurance has been ongoing for the past five years.
B.
6.

Relief Sought:
The complainant requests the following:
a. Intervene in the matter.
b. Direct Aliens Developers (P) Ltd. to hand over possession of Flat No.
1865 at Aliens Space Station, Tellapur, Hyderabad, at the earliest.

C.

Interim Request:
a. Immediate direction to the Developers to complete the finishing work
and hand over the possession of the flat.
b. Consideration of the financial burden on the complainant due to
continued rental payments.

D.

Respondent's Reply:

7.

The complainant's application is not maintainable under the facts and

circumstances of the case, as the complainant has approached this authority
by suppressing material facts. The instant application lacks any cause of
action against the respondent and is liable to be dismissed. It is submitted
that the complaint is misconceived, based on suppression and incorrect facts.
8.

The averments made in the application are false, baseless, and

concocted for the purpose of this application. The complainant is put to strict
proof of the same. The respondent denies each and every allegation made by
the complainant, except for those that are specifically and expressly admitted
herein.
9.

The respondent is a reputable construction company with its registered

office at Aliens Space Station, Tellapur, RC Puram Mandal, Gachibowli,
2 of 11

Sangareddy District - 502032. The complainant expressed interest in
purchasing residential flat No. 1865, a 3BHK of 1673 sq. ft. in super built-up
area, located in Station 11 on the 18th floor of the residential project "Aliens
Space Station," located at Survey Nos. 384 & 385, Tellapur, RC Puram
Mandal,

Sangareddy

District

-

502032,

Telangana,

for

a

total

sale

consideration of Rs. 67,00,000/- with a token amount of Rs. 32,00,000/-.
10.

The project, "Aliens Space Station," located at Survey Nos. 384 & 385,

Tellapur RC Puram Mandal, Sangareddy District, Telangana, commenced in
2008, long before the introduction of the RERA legislation. It is submitted that
although the project was launched in 2008, it did not take off as planned due
to several reasons, such as:
a. The 2008 housing crisis and global economic slowdown, which
adversely impacted the real estate market in India.
b. Political turmoil during 2011-12 due to the Telangana-Andhra Pradesh
bifurcation, which brought unrest in the real estate sector.
c. Numerous

external,

technical,

and

financial

challenges,

which

hampered the progress of the project. d) The COVID-19 pandemic,
which severely affected the project. Several employees, including key
managerial personnel of the respondent company, faced health
challenges during this period, leading the company to divert its focus
towards employees’ welfare, including medical expenses and setting up
quarantine centers, which caused a financial strain on the company.
Consequently, it took considerable time for the respondent to recover
from the pandemic’s aftermath.
11.

It is pertinent to mention that in order to revive the project, the

respondent

approached

SWAMIH

Investment

Fund

I

(SWAMIH),

a

government-backed investment fund under SBI Cap Ventures Ltd., formed for
completing stressed and stalled residential projects. The respondent received
a total sum of Rs. 280 crore and an additional Rs. 52 crore, solely for the
completion of the project, as per the SWAMIH Investment Committee's
approval.

3 of 11

12.

It is submitted that to proceed with the transactional documents and

commence the funding process, the respondent was required to obtain
requisite approvals from various authorities, including the Telangana Real
Estate Regulatory Authority (TGRERA). To meet SWAMIH's stipulations, the
project was registered with TGRERA, and a certificate bearing registration
number P01000007265 was issued on 16/11/2023.
13.

As per the RERA registration certificate granted on 16/11/2023, the

respondent has been adhering to RERA guidelines in both letter and spirit.
Furthermore, an expert committee has been formed to ensure the smooth
completion of the project. It is submitted that, as per the affidavit dated
01/03/2023 submitted before the TGRERA, the timeline for the project’s
completion is March 2027.
14.

The respondent sold the flat to the complainant for Rs. 67,00,000/- in

2016. Currently, similar flats in the same project are being sold for Rs. 1.45
crore. Despite the substantial increase in market value, the respondent is
committed to handing over the flat at the agreed price of Rs. 67,00,000/-.
15.

The respondent is fully committed to completing the final pending work

on the flat and handing it over to the complainant. The project has progressed
up to the 4th floor, and the structure of the 18th floor, where the
complainant's flat is located, has been completed. The respondent is
dedicated to fulfilling all remaining obligations to deliver the flat in
satisfactory condition and to ensure compliance with quality standards.
16.

As per the affidavit submitted, the deadline for project completion is

March 2027. The respondent hereby undertakes to hand over the flat to the
complainant well within the project’s completion deadline.
17.

Therefore, it is prayed before this Hon’ble Authority to stay all further

proceedings, based on the undertaking to hand over the flat within the
stipulated timelines, and to pass an order in favor of the respondent and
against the complaint.

4 of 11

E. Rejoinder:
18.

The reasons for the delay in handing over possession of the flat, as

enumerated in paragraph 2 of the developer’s letter dated 18/04/2024, are
not true. The fact is that, before booking the flat with Aliens Developers Pvt.
Ltd., the complainant visited the site of another housing project located in the
vicinity of the respondent’s project. The situation and reasons mentioned by
the respondent were the same and equally applicable to the other housing
project as well. However, the other developers have completed their projects
and handed over possession of the flats long ago.
19.

When the complainant booked the flat in December 2012 with the

respondent's project, the bifurcation of Telangana and Andhra Pradesh was
already over. The other developers faced the same situation but completed
their projects on time. None of the builders delayed the issue, unlike the
respondent.
20.

The COVID-19 pandemic, cited by the developer as a reason for the

delay, surfaced eight years after the complainant booked the flat. Therefore,
this reason is irrelevant and misleading.
21.

According to the registration of the project with TGRERA, the housing

project must be completed by the end of 2026. However, this deadline should
not apply to flats that were booked 11 years before RERA registration.
22.

Initially, the complainant booked flat No. 1406 in Station 1 with an area

of 1874 sq. ft. and one car parking space for a total cost of Rs. 64,54,284/- in
December 2012. Due to a lack of progress in construction, the complainant
changed to flat No. 1865 in Station 11, measuring 1673 sq. ft., on
31/01/2016, for a total cost of Rs. 67,00,000/- (at the prevailing rate), with
possession promised by 31/12/2017. To date, the complainant has paid Rs.
62,98,000/-, which is 94% of the flat's total cost, excluding taxes.
Additionally, the complainant paid Rs. 2,45,716/- extra due to the change to
a smaller flat by 201 sq. ft.

5 of 11

23.

The complainant is the only customer who booked a flat in 2012 and

has not yet received possession. Other customers who booked during that
time either received refunds or switched to other locations. The complainant
is the only exception and should be considered for early possession on a
priority basis.
24.

The developer sold the flat for Rs. 67,00,000/- in 2016, yet they are

comparing today's prices to those of over nine years ago. The complainant has
taken a housing loan, for which the bank charges 10% interest compounded
monthly. If the amounts paid by the complainant are calculated at the same
10% interest, compounded quarterly, the total would amount to Rs.
1,56,95,067/- by 10/07/2024, and more if compounded monthly.
25.

In light of this, the complainant requests the Hon'ble Authority to

determine who has actually incurred losses in this case. The respondent's
statement that the flat will be handed over by the end of 2026 is
unacceptable. If calculated from the date of booking, this would result in a
14-year delay, which is abnormal. This delay has caused significant mental
distress to the complainant.
26.

The Hon'ble TGRERA is requested to direct the developer to pay

compensation by way of monthly interest at 10% per annum on the amount
paid by the complainant (excluding taxes) from the agreed handover date until
the actual handover of possession. Additionally, it is requested that the
respondent be directed to complete the final finishing/touch-up work on the
flat as a priority.
F. Observation of the Authority:
27.

We have carefully considered the arguments advanced by both parties

and have thoroughly examined the record along with the documents
submitted by the Complainant and the Respondent. It is an undisputed fact,
as per the Agreement of Sale dated 17.02.2017, that the Respondent was
obligated to deliver possession of the unit by December 2017. The Respondent
has admitted that the project remains incomplete as of today and has stated
6 of 11

that they have received funding under the SWAMIH Fund for the purpose of
completing the construction. The stipulated date for completion was
December 2017, seven years ago. The Respondent attributes the delay to
political turmoil during 2011–12, various external, technical, and financial
challenges, and the impact of the COVID-19 pandemic.
28.

While the SWAMIH Fund, sanctioned by the Government of India, was

indeed established to support real estate projects affected by certain economic
conditions, the Authority notes that the reasons cited by the Respondent,
such as the 2008 housing crisis and political instability, are events that
occurred prior to the execution of the Agreement of Sale with the Complainant
in February 2017. At the time of entering into the Agreement, the Respondent
committed to delivering possession by December 2017. If the Respondent was
aware of these pre-existing challenges, it is inexplicable why such a timeline
was promised. The invocation of the COVID-19 pandemic as a reason for
delay is also untenable, as this event occurred only after the agreed
possession date and cannot be retroactively justified as a cause for the delay.
29.

The Respondent has further submitted that they have approached the

SWAMIH Investment Fund, a government-backed initiative managed by SBI
Cap Ventures Ltd., formed to complete stalled residential projects. To facilitate
funding, the Respondent had to obtain requisite approvals, leading to the
issuance of a TGRERA certificate (No. P01000007265) on 16.11.2023. The
Respondent claims to have complied with the RERA guidelines and has
revised the project’s completion timeline to the end of 2026, which has been
communicated to RERA at the time of registration.
30.The Authority emphasizes that the RERA registration granted to the
Respondent was issued with due consideration to protect the interests of all
project allottees, demonstrating the Respondent's commitment to complete
the project and deliver units to both existing and prospective allottees in good
faith. While obtaining RERA registration, the Respondent affirmed and
documented that all current allottees had consented to the projected
completion date. Notably, a condition of the RERA Registration certificate
required the formation of a Resident Association comprising all existing
7 of 11

allottees of the project, along with a formal resolution affirming their
agreement on the completion of development. However, when the Authority
requested the Respondent to furnish specific consent from the Complainant
regarding the project completion timeline, the Respondent acknowledged that
the Complainant is not among the consenting allottees. The Respondent,
therefore, cannot solely rely on the registration’s validity period, which
extends until 14.12.2026, as grounds to defer possession for allottees who
have not provided consent. Non-compliance in this regard shall invoke
consequential actions.
31.

The Complainant has waited for over a decade for the promised unit,

which was assured to him in 2017. The Complainant cannot be deprived of
his rightful possession due to the Respondent’s inability to complete the
project. The Complainant is fully within his rights to seek redress from this
Authority for the delay in possession. The Respondent's reliance on the
revised completion date of 2026 does not absolve them of their obligation to
deliver possession as per the original Agreement.
32.

In this context, the Authority would like to reference the decision of the

Hon’ble Supreme Court in Newtech Promoter & Developers Pvt. Ltd. v. State of
Uttar Pradesh (11.11.2021), where it was held:

“The unqualified right of the allottee to seek refund referred
under section 18(1)(a) and section 19(4) of the Act is not dependent
on any contingencies or stipulations thereof. It appears that the
Legislation has consciously provided this right of refund on
demand as an unconditional absolute right to the allottee. If the
promoter fails to give possession of the apartment plot or building
within the time stipulated under the terms of the agreement
regardless

of

unforeseen

events

or

stay

orders

of

the

Court/Tribunal, which is in either way attributable to the
allottee/homebuyer, the promoter is under an obligation to refund
the amount on demand with interest at the rate prescribed by the
State Government including compensation in the manner provided
under the Act with the proviso that if the allottee does not wish to
withdraw from the project, he shall be entitled for interest for the
period

of

prescribed.”

delay

till

handing

over

possession

at

the

rate

8 of 11

33.

In the present case, the Complainant has chosen not to withdraw from

the project and prays that the Respondent be directed to hand over
possession immediately. The Authority acknowledges that the Respondent's
project is distressed and has received financial backing from the Government
of India through SBI Cap Ventures Ltd- SWAMIH Fund. In light of the
Respondent's good faith efforts to complete the project, the Authority deems it
reasonable to allow them the opportunity to deliver the unit within the RERAregistered completion date, i.e., 14.12.2026. However, the Respondent cannot
indefinitely delay possession, and the unit must be handed over as soon as
possible.
34.

The Authority finds that the Respondent has not delivered possession of

the subject unit to the Complainant, thereby breaching its obligations under
the Agreement of Sale. This constitutes non-compliance with Section 11(4)(a),
read in conjunction with the proviso to Section 18(1) of the Real Estate
(Regulation and Development) Act, 2016. Consequently, the Respondent is
liable to pay the Complainant interest for the delay in possession.
In calculating this interest, the Respondent shall be entitled to benefit from
waivers applicable for the COVID-19 pandemic period, as per the Orders of
this issued as follows:

From 15.03.2020 to 14.09.2020, pursuant to Circular Order No. 14,
dated 13.05.2020, From 15.09.2020 to 15.03.2021, pursuant to Order
No. 15, dated 29.09.2020, and From 15.03.2021 to 14.09.2021,
pursuant to Order No. 16, dated 01.06.2021, as issued by TGRERA.

35.

After deducting these exempted periods, the Respondent is directed to

pay interest to the Complainant for each three-month delay period, calculated
from the due date of possession (December 2017) until the actual possession
is delivered or occupancy certificate is issued, whichever is earlier, at the rate
prescribed under Section 18 of the Act, read with Rule 15 of the TG RE(R&D)
Rules.
36.

Additionally,

acknowledging

the

Respondent’s

commitment

to

completing the project in good faith, the Authority deems it equitable to
permit the Respondent to pay the accrued interest for the balance period in
9 of 11

three equal monthly instalments from the date of issuance of occupancy
certificate (OC) obtained. This arrangement is intended to ensure project
completion within the stipulated RERA-registered timeframe, which is
December 2026, thereby serving the interests of other flat buyers in the
project, at large.
37.

As per the website of the State Bank of India (https://sbi.co.in), the

marginal cost of lending rate (MCLR) as of 01.10.2024 is 8.95% p.a.
accordingly; the prescribed interest rate shall be MCLR + 2%, amounting to
10.95% p.a.

Directions of the Authority:

38.

In light of the findings of the Authority as recorded above, the following

directions under section 37 of the RE(R&D) Act to ensure compliance with
obligations imposed upon the under the RE(R&D) Act are issued
i.

The Respondent is directed to pay interest at the prescribed rate of
10.95% per annum from the due date of possession, i.e., December
2017 to till date within 45 days, calculated, excluding the COVID-19
waiver period as per orders issued by TG RERA and for the balance
period in three monthly equal instalments from the date of issue of
Occupancy Certificate. This interest shall continue to accrue until the
issuance of the occupancy certificate (OC) or partial OC for the relevant
tower.

ii.

The arrears of interest accrued from December 2017 until the date of
this Order shall be paid by the Respondent to the Complainant within
45 days from the date of this Order. Thereafter, interest for each
subsequent three-month delay period shall be paid by the Respondent
to the Complainant on or before the 10th day following each threemonth period until possession is actually delivered.

iii.

The Respondent is hereby directed to expedite the completion of the
project and hand over possession of the subject unit to the Complainant
at the earliest possible date, without any further undue delay.
10 of 11

iv.

Complaint stands disposed of.

v.

Parties to bear their own costs.

vi.

The parties are hereby informed that failure to comply with this Order
shall attract Section 63 of the Act.

SdSri. K. Srinivas Rao,
Hon’ble Member
TG RERA

SdSri. Laxmi NaryanaJannu,
Hon’ble Member
TG RERA

Sd-

Dr. N. Satyanarayana, IAS (Retd.),
Hon’ble Chairperson
TG RERA

11 of 11

Related Orders

Interim Order Complaint No.228 of 2025
Rangareddy, Telangana, 500077)
15 Apr 2026
Order Complaint No. 386 of 2025
Koti, Hyderabad-500027.
09 Apr 2026
Order Complaint No. 153 of 2024
Telangana – 500011.
08 Apr 2026
Order Complaint No. 152 of 2024
Telangana – 500011.
08 Apr 2026
Order Complaint No. 151 of 2024
Telangana – 500011.
08 Apr 2026

Need Complete Property Verification?

Get ownership details, EC records, survey sketch, zone checks, geo-insights & AI analysis - all in one place

Ownership Details
EC Records
Survey Sketch
Zone Checks
Geo-Insights
AI Analysis
Try VerifyMyLand Now ✨ Get comprehensive property verification in minutes

Verify Your Property Before You Buy

AI-powered legal due diligence — title verification, encumbrance checks, zoning compliance, and risk assessment in minutes. Catch issues before they cost you crores.