TG-RERA Authority

Order Complaint No. 338 of 2025

06 Nov 2025
TG-RERA Authority
6 Pages

Order Details

Order Type TG-RERA Authority
Complaint/Case Number Complaint No. 338 of 2025
Year 2025
Order Category Regular Order
Order Date 06 Nov 2025
Complainant (R/o H. No. 1-29, Near Post Office, Telukunta, Mandal: Julapally, Peddapally Dist. 505 525)
Respondent Banjara Hills, Hyderabad, Telangana - 500082)
Project Name HAPPY
PDF Document Download PDF BU_131125142347029.pdf

Full Order Text

BEFORE TELANGANA REAL ESTATE REGULATORY AUTHORITY
[Under the Real Estate (Regulation and Development) Act, 2016]
Date: 6th November, 2025
Quorum:

Dr. N. Satyanarayana, IAS (Retd.), Hon’ble Chairperson
Sri K. Srinivasa Rao, Hon’ble Member
Sri Laxmi Narayana Jannu, Hon’ble Member
Complaint No. 338/2025/TG RERA

Allenki Nagaraju
(R/o H. No. 1-29, Near Post Office, Telukunta, Mandal: Julapally, Peddapally Dist. 505 525)
…Complainant
Versus
M/s. Bhuvanteja Infraprojects Pvt Ltd. represented by its Managing Director Sri. Chekka
Venkata Subrahmanyam
(Office at H. no: 201, 2nd Floor, Lumbini Amrutha Chambers, Nagarjuna Circle, Road No:3,
Banjara Hills, Hyderabad, Telangana - 500082)
…Respondents
The present matter filed by the Complainant came up for hearing on 07.08.2025 before
this Authority, in the presence of the Complainant in person, and no one appeared for the
Respondents despite due service of notice. After hearing the submissions of the Complainant,
the matter was set ex parte on 07.08.2025. This Authority now proceeds to pass the following
ORDER:
2.

The present Complaint have been filed by the Complainant under Section 31 of the Real

Estate (Regulation & Development) Act, 2016 (hereinafter referred to as the “Act”) read with
Rule 34(1) of the Telangana Real Estate (Regulation and Development) Rules, 2017
(hereinafter referred to as the “Rules”) seeking appropriate reliefs against the Respondents.
A. Brief Facts of the Case as per Form M submitted by the Complainant:
3.

It was submitted that the Complainant entered into an Agreement of Sale with the

Respondent on 29th January 2022 for the purchase of a residential apartment. The Complainant
stated that in pursuance of the said agreement, they paid a total sum of ₹22,42,000/- (Rupees
Twenty-Two Lakhs Forty-Two Thousand Only) to the Respondent as sale consideration.


It was further submitted that the agreement pertained to a property identified as Flat

No. 705, located in 'A Block' on the 7th Floor of the Respondent's project known as "HAPPY
HOMES (SHAMEERPET)".
5.

The Complainant contended that as per the terms of the Agreement of Sale, the

Respondent was obligated to complete construction and hand over possession of the apartment
within a period of 36 months from the date of the agreement (i.e., by approximately January
2025).
6.

It was alleged that the Respondent failed to fulfill this primary condition of the

agreement. The Complainant submitted that, despite the lapse of the stipulated 36-month period
and having received the aforementioned payment, the Respondent had not handed over the
apartment as of the date of filing the complaint.
B. Reliefs Sought
7.

Accordingly, the Complainant sought the following reliefs:
i.

To direct the Respondent to forthwith hand over possession of the apartment situated
in 'Happy Homes', A-Block, at Shameerpet, complete in all respects as per the
specifications mentioned in the Agreement for Sale.
OR;

ii.

To direct the Respondent to refund the entire principal amount paid by the
Complainant, together with interest thereon at the rate of 36% per annum.

C. Points for Consideration
8.

Based on the facts and circumstances placed before this Authority, the following

questions arise for adjudication:
I.

Whether the Respondents have violated provisions of the RE(R&D) Act, 2016?

II.

Whether Complainant is entitled to relief(s) as prayed for? If yes, to what extent?

D. Observations of the Authority
9.

Before further adjudicating on the matter, this Authority takes due note of the repeated

non-compliance by the Respondents, who have failed to appear before this Authority despite
service of multiple notices and affording sufficient opportunities. In view of their continued


Upon careful perusal of the records and the submissions placed before this Authority, it

is observed that the subject project titled “Happy Homes (Shamirpet)”, being developed by the
Respondent, M/s. Bhuvanteja Infraprojects Private Limited, remains unregistered with this
Authority. As per the Agreement of Sale dated 29.01.2022 executed between the Complainant
and the Respondent, the proposed project is situated in multiple survey numbers at Shamirpet
Village & Mandal, admeasuring approximately Ac. 10.37 guntas (around 42,000 square
metres). Therefore, the project clearly exceeds the minimum threshold of 500 square metres
prescribed under Section 3(2)(a) of the Real Estate (Regulation and Development) Act, 2016.
Consequently, the project mandatorily requires registration under Section 3 of the Act. The
Respondent-promoter’s failure to obtain such registration prior to marketing, sale, and
execution of agreements constitutes a violation of Section 3, thereby attracting liability under
Section 59 of the RE(R&D) Act, 2016.
11.

It is further noted that, in a prior matter vide Complaint No. 286 of 2024, involving a

different complainant but pertaining to the same project and the same Respondent-promoter,
this Authority had already adjudicated upon similar facts and had imposed a penalty for
violation of Section 3 of the Act. Accordingly, the issue of unregistered development by the
Respondent-promoter in the present matter stands on the same footing, and the violation has
already been adjudicated by this Authority.
12.

In addition, this Authority observes that the conduct of the Respondent-promoter

reflects a recurrent and continued pattern of non-compliance with statutory mandates under the
RE(R&D) Act, 2016. It is relevant to refer to Complaint No. 264 of 2024, wherein this
Authority had taken cognisance of similar violations and had declared the Respondent as a
“defaulter.” The relevant extract from the said order is reproduced below for reference:
“35… Accordingly, Respondent No.1 is hereby declared to be a “defaulter” both in its
capacity as a “promoter” and as an “agent” within the meaning of Sections 2(zk) and
2(zm) of the RE(R&D) Act, 2016. As a consequence, the Respondent shall be prohibited
from undertaking, advertising, marketing, booking, selling, or registering any new real
estate project or acting as a real estate agent within the jurisdiction of this Authority until
such time as all existing dues, refunds, interest, penalties, and regulatory compliances are
fully discharged to the satisfaction of this Authority”

13.

Point I is answered accordingly.


Upon perusal of the material available on record, it is noted that the Complainant

entered into an Agreement of Sale dated 29.01.2022 with the Respondent for the purchase of
Flat No. 705, located in A-Block, 7th Floor of the project titled “Happy Homes (Shamirpet)”.
As per the terms of the said Agreement of Sale, the Complainant has paid the entire sale
consideration amounting to ₹22,42,000/- (Rupees Twenty-Two Lakhs Forty-Two Thousand
Only) to the Respondent.
15.

The Agreement of Sale further stipulates that the possession of the subject flat was to

be handed over within 36 months from the date of obtaining building permissions from HMDA
and RERA approvals. However, the Respondent has neither obtained the requisite statutory
approvals nor commenced lawful construction activity on the site. Consequently, no progress
has been made towards completion of the project, and possession has not been delivered to the
Complainant.
16.

As already noted under Point No. I, the Respondent has not registered the project with

this Authority, nor secured necessary development permissions. In the absence of such
mandatory approvals, the Respondent is incapable of proceeding with lawful construction,
rendering the completion of the project within agreed timelines impracticable.
17.

In light of the above, the relief sought by the Complainant for possession cannot be

granted, as the pre-conditions for commencement and completion of the project have not been
fulfilled by the Respondent. Therefore, the Complainant is entitled to seek a refund of the
amount paid along with applicable interest.
18.

In this regard, Section 18(1)(a) of the Real Estate (Regulation and Development) Act,

2016 is applicable, which reads as follows:
(1) If the promoter fails to complete or is unable to give possession of an apartment, plot
or building, —
(a) in accordance with the terms of the agreement for sale or, as the case may be, duly
completed by the date specified therein; or
(b) due to discontinuance of his business as a developer on account of suspension or
revocation of the registration under this Act or for any other reason,
he shall be liable on demand to the allottees, in case the allottee wishes to withdraw from
the project, without prejudice to any other remedy available, to return the amount
received by him in respect of that apartment, plot, building, as the case may be, with
interest at such rate as may be prescribed in this behalf including compensation in the
manner as provided under this Act.


Accordingly, this Authority holds that the Complainant is entitled to the refund of the

entire sale consideration paid, i.e., Rs. 22,42,000/-, along with interest at the rate prescribed
under Rule 15 of the Telangana Real Estate (Regulation and Development) Rules, 2017, i.e.,
State Bank of India’s MCLR plus 2% per annum (8.75% + 2% = 10.75%), calculated from the
respective dates of payments made until full and final realization of the amount.
20.

Accordingly, Point II is answered.

E. Directions of the Authority
21.

In accordance with the discussions made above, this Authority, vide its powers under

Sections 37 and 38, issues the following directions to the Respondent:
i.

The Respondent is directed to refund the entire amount of Rs. 22,42,000/- (Rupees
Twenty-Two Lakhs Forty-Two Thousand Only) along with interest at the rate of
10.75% per annum (SBI MCLR of 8.75% + 2%) calculated from the respective
dates of payment made by the Complainant until the date of actual refund by the
Respondent, within 30 (thirty) days from the date of this order.

ii.

Failing to comply with the above-said direction by the Respondent shall attract
penal action in accordance with Section 63 of the RE(R&D) Act, 2016.

22.

In view of the above, the present complaint is disposed of. No order as to costs.

Sd/Sri K. Srinivasa Rao,
Hon’ble Member,
TG RERA

Sd/Sri Laxmi Narayana Jannu,
Hon’ble Member,
TG RERA

Sd/Dr. N. Satyanarayana, IAS (Retd.),
Hon’ble Chairperson,
TG RERA


Related Orders

Interim Order Complaint No.228 of 2025
Rangareddy, Telangana, 500077)
15 Apr 2026
Order Complaint No. 386 of 2025
Koti, Hyderabad-500027.
09 Apr 2026
Order Complaint No. 153 of 2024
Telangana – 500011.
08 Apr 2026
Order Complaint No. 152 of 2024
Telangana – 500011.
08 Apr 2026
Order Complaint No. 151 of 2024
Telangana – 500011.
08 Apr 2026

Need Complete Property Verification?

Get ownership details, EC records, survey sketch, zone checks, geo-insights & AI analysis - all in one place

Ownership Details
EC Records
Survey Sketch
Zone Checks
Geo-Insights
AI Analysis
Try VerifyMyLand Now ✨ Get comprehensive property verification in minutes

Verify Your Property Before You Buy

AI-powered legal due diligence — title verification, encumbrance checks, zoning compliance, and risk assessment in minutes. Catch issues before they cost you crores.