BEFORE TELANGANA REAL ESTATE REGULATORY AUTHORITY
[Under the Real Estate (Regulation and Development) Act, 2016]
Date: 30th December, 2025
Quorum:

Dr. N. Satyanarayana, IAS (Retd.), Hon’ble Chairperson
Sri K. Srinivasa Rao, Hon’ble Member
Sri Laxmi Narayana Jannu, Hon’ble Member
Complaint No. 312/2024/TG RERA

Sri Methuku Srinivas Reddy
(R/o Flat Mo. 201, second floor, A-Block,
Balaji Avenue, Bandijangaianh Gardens,
Peerzadiguda Village, Medipally Mandal,
Medchal-Malkajigiri District)
…Complainant
Versus
M/s. Sunrise Builders and Developer,
(Office at: Plot No.4, Road No.12, Swaroop Nagar, Near VenkateshwaraSwamy Temple, Uppal
Village and Mandal, Medchal-Malkajgiri District.)
Represented by its Partners
1. Keesari Satyanarayana
(R/o Plot No.4, Ramabhadra Apartments,
2nd Lane, L.B.Nagar, Ranga Reddy District.)
2. Vundela Avula Reddy
(R/o H.No.9-268, Viswanadhapuram, Podili,
Prakasham District, Andhra Pradesh.)
…Respondents
1.

The present Complaint was listed for hearing before this Authority on 13.08.2025. On

the said date, the Complainant remained absent, while the learned Counsel appearing for the
Respondents was present.
2.

The learned Counsel for the Respondents submitted that the issues raised in the

Complaint had been amicably settled between the parties and further undertook that a memo
for withdrawal of the Complaint would be filed within one week. However, no such withdrawal

Page 1 of 2


It is evident from the record that the Complainant has failed to evince any interest in

prosecuting the Complaint, despite sufficient opportunity. In the absence of the Complainant
and in view of the continued non-appearance and non-compliance, this Authority is constrained
to conclude that the Complaint is not being pursued diligently.
5.

Accordingly, the Complaint is dismissed for non-prosecution. No order as to costs.

Sd/Sri K. Srinivasa Rao,
Hon’ble Member,
TG RERA

Sd/Sri Laxmi Narayana Jannu,
Hon’ble Member,
TG RERA

Sd/Dr. N. Satyanarayana, IAS (Retd.),
Hon’ble Chairperson,
TG RERA

Page 2 of 2


Related Orders

Interim Order Complaint No.228 of 2025
Rangareddy, Telangana, 500077)
15 Apr 2026
Order Complaint No. 386 of 2025
Koti, Hyderabad-500027.
09 Apr 2026
Order Complaint No. 153 of 2024
Telangana – 500011.
08 Apr 2026
Order Complaint No. 152 of 2024
Telangana – 500011.
08 Apr 2026
Order Complaint No. 151 of 2024
Telangana – 500011.
08 Apr 2026

Need Complete Property Verification?

Get ownership details, EC records, survey sketch, zone checks, geo-insights & AI analysis - all in one place

Ownership Details
EC Records
Survey Sketch
Zone Checks
Geo-Insights
AI Analysis
Try VerifyMyLand Now ✨ Get comprehensive property verification in minutes

Verify Your Property Before You Buy

AI-powered legal due diligence — title verification, encumbrance checks, zoning compliance, and risk assessment in minutes. Catch issues before they cost you crores.