Order Complaint No. 312 of 2024
Order Details
| Order Type | TG-RERA Authority |
|---|---|
| Complaint/Case Number | Complaint No. 312 of 2024 |
| Year | 2024 |
| Order Category | Regular Order |
| Order Date | 30 Dec 2025 |
| Complainant | Medchal-Malkajigiri District) |
| Respondent | Prakasham District, Andhra Pradesh.) |
| PDF Document | Download PDF BU_100226174339114.pdf |
Full Order Text
BEFORE TELANGANA REAL ESTATE REGULATORY AUTHORITY
[Under the Real Estate (Regulation and Development) Act, 2016]
Date: 30th December, 2025
Quorum:
Dr. N. Satyanarayana, IAS (Retd.), Hon’ble Chairperson
Sri K. Srinivasa Rao, Hon’ble Member
Sri Laxmi Narayana Jannu, Hon’ble Member
Complaint No. 312/2024/TG RERA
Sri Methuku Srinivas Reddy
(R/o Flat Mo. 201, second floor, A-Block,
Balaji Avenue, Bandijangaianh Gardens,
Peerzadiguda Village, Medipally Mandal,
Medchal-Malkajigiri District)
…Complainant
Versus
M/s. Sunrise Builders and Developer,
(Office at: Plot No.4, Road No.12, Swaroop Nagar, Near VenkateshwaraSwamy Temple, Uppal
Village and Mandal, Medchal-Malkajgiri District.)
Represented by its Partners
1. Keesari Satyanarayana
(R/o Plot No.4, Ramabhadra Apartments,
2nd Lane, L.B.Nagar, Ranga Reddy District.)
2. Vundela Avula Reddy
(R/o H.No.9-268, Viswanadhapuram, Podili,
Prakasham District, Andhra Pradesh.)
…Respondents
1.
The present Complaint was listed for hearing before this Authority on 13.08.2025. On
the said date, the Complainant remained absent, while the learned Counsel appearing for the
Respondents was present.
2.
The learned Counsel for the Respondents submitted that the issues raised in the
Complaint had been amicably settled between the parties and further undertook that a memo
for withdrawal of the Complaint would be filed within one week. However, no such withdrawal
Page 1 of 2
It is evident from the record that the Complainant has failed to evince any interest in
prosecuting the Complaint, despite sufficient opportunity. In the absence of the Complainant
and in view of the continued non-appearance and non-compliance, this Authority is constrained
to conclude that the Complaint is not being pursued diligently.
5.
Accordingly, the Complaint is dismissed for non-prosecution. No order as to costs.
Sd/Sri K. Srinivasa Rao,
Hon’ble Member,
TG RERA
Sd/Sri Laxmi Narayana Jannu,
Hon’ble Member,
TG RERA
Sd/Dr. N. Satyanarayana, IAS (Retd.),
Hon’ble Chairperson,
TG RERA
Page 2 of 2
Related Orders
Interim Order Complaint No.228 of 2025
Rangareddy, Telangana, 500077)Order Complaint No. 386 of 2025
Koti, Hyderabad-500027.Order Complaint No. 153 of 2024
Telangana – 500011.Order Complaint No. 152 of 2024
Telangana – 500011.Order Complaint No. 151 of 2024
Telangana – 500011.Need Complete Property Verification?
Get ownership details, EC records, survey sketch, zone checks, geo-insights & AI analysis - all in one place