Order Complaint No. 289 of 2024
Order Details
| Order Type | TG-RERA Authority |
|---|---|
| Complaint/Case Number | Complaint No. 289 of 2024 |
| Year | 2024 |
| Order Category | Regular Order |
| Order Date | 13 Oct 2025 |
| Complainant | (R/o. Janapriya Nilevally, 2817, Ameenapur, Sangareddy 500 049) |
| Respondent | 500 034) |
| PDF Document | Download PDF BU_131025214938103.pdf |
Full Order Text
BEFORE TELANGANA REAL ESTATE REGULATORY AUTHORITY
[Under the Real Estate (Regulation and Development) Act, 2016]
COMPLAINT NO.289 OF 2024
13th Day of October 2025
Quorum:
Dr. N. Satyanarayana, IAS (Retd.), Hon’ble Chairperson
Sri K. Srinivasa Rao, Hon’ble Member
Sri Laxmi Narayana Jannu, Hon’ble Member
Rajesh Rayi
(R/o. Janapriya Nilevally, 2817, Ameenapur, Sangareddy 500 049)
…Complainant
Versus
M/s. Janapriya Townships Private Limited
(Office Address: Keerthi Pride Towers. 3rd& 5th floor Rd. No. 2, Banjara Hills, Hyderabad
500 034)
…Respondent
The present matter filed by the Complainant herein came up for hearing before this
Authority in the presence of the Complainant in person, and the Counsel for Respondent and
upon hearing submissions made by both parties, and the matter reserved over for
consideration till this date, this Authority passes the present Complaint ORDER:
2.
The Complainant has filed complaint on hand under Section 31 of the Real Estate
(Regulation and Development) Act, 2016 (hereinafter referred to as the "RE(R&D) Act"),
read with Rule 34(1) of the Telangana Real Estate (Regulation and Development) Rules,
2017 (hereinafter referred to as the "Rules"), alleging commission of violation and
contravening of the provisions of the said Act and Rules and sought for the appropriate reliefs
against the Respondent.
A. Brief facts of the case:
3.
The Complainant submitted that he had booked a flat on 07.12.2011in the
Respondent's “Janapriya Nile Valley” project. The details of the flat are Flat No. 2817,
located in Block 2B. The flat had a super built-up area of 1,060 sq. ft., at an agreed price of
₹1,870 per sq. ft., after a discount of ₹40 per sq. ft., bringing the total sale consideration to
₹24,03,488. That out of the sale consideration amount, he(Complainant) paid an initial
Page 1 of 9
The Complainant further submitted that even after paying approximately 70% of the
total cost of the flat, the construction on Block 2B had not commenced, and the Respondent
was unresponsive to notices and any communication. Eventually, the Respondent offered a
shift to Block 2A, where the construction was ongoing. After a few months in 2015, the
Respondent insisted that the Complainant pay as per current market rates, excluding other
additional charges and making the flat unaffordable to the Complainant.
5.
The complainant submits that in the year 2023, the Respondent sent a cancellation
notice citing non-payment, even though the Complainant had paid 70%, and eventually, the
Complainant discovered that his flat had been sold to another person without his consent, and
the bank refused to provide an NOC. After several failed attempts to resolve the issue
amicably the Complainant had requested for a refund, and in April 2024, the Respondent
agreed to refund Rupees ₹ 33,35,600/-, allegedly pressurising him (Complainant) to accept
the amount without condition, or otherwise pursue legal recourse and having exhausted all
avenues, he(Complainant)has approached TS-RERA in August 2024 seeking justice.
B. Reliefs Sought for:
6. Aggrieved by the actions of the Respondent, the Complainant approached this Authority
for the following reliefs
i. The Complainant requests an immediate refund of ₹15,70,000 plus 12% annual interest for
a 13-year delay, totalling to approximately ₹68,50,684.
ii. The complainant seeks compensation for the financial burden caused by missed rent on his
home loan, amounting to 18,00,000 from 2012 to 2024.
iii. Complainant seeks compensation of ₹10,00,000 for the mental and emotional distress
caused by the builder's continued delays, false promises, and lack of communication.
iv. Action against the builder for failure to comply with RERA guidelines and penalty for
violating the project timeline, making false promises, and unauthorised selling of the flat.
Page 2 of 9
The Respondent filed a reply stating that the Complaint does not come under the
purview of RERA, as TG RERA was not in force when the Complainant booked the flat in
2011.
8.
The Respondent submits that the complainant being desirous of having a flat in its
project entered into an agreement of sale dated 06/12/2011 for purchase of an apartment
No.2817, admeasuring built up area 840 sq.ft along with common service area of 220 sq.ft in
8th floor of Block-2, including common areas and amenities together with undivided share of
land of 30.42 sq. yds, out of the land admeasuring Ac.24-25.5 gts., for a consideration of
Rs.20,24,600/- (excluding amenities cost of Rs.2,82,000/-) and paid an advance amount of
Rs.50,000/- towards advance payment vide Cheque No 00004 dated 27/11/2011, and
Rs.3,50,000/- by cheque No.000005, dated 11/12/2011. Subsequently, he arranged a loan
from HDFC Bank, which disbursed Rs 11,70,000. Rupees Eleven Lakh Seventy Thousand
Only) On 14/12/2011, totalling to Rs. 15,70,600/- (Rupees Fifteen Lakh Seventy Thousand
Six Hundred Only) and the deferred payments schedule of balance sale consideration as
agreed to be paid stage-wise by the complainant was set out in clause 2.2 of the agreement
9.
The Respondent also submitted that the project's delay occurred due to delay in
getting permissions from the concerned departments, and that further delay was occurred due
to COVID-19. Finally, it(Respondent) states that they have completed the construction of the
2B block by 2024 and registered the flats in favour of other booked customers who have
made a complete payment and handed over the flats to them.
10.
The Respondent submitted that the Complainant had approached them and requested
a refund, duly cancelling his booked flat, for which it(Respondent) had agreed, and after
considering the cancellation request, it(Respondent) has refunded the amount to the
Complainant that was paid by him, along with appropriate interest. Further it has submitted
that the present complaint filed by the Complainant under the RERA Act, 2016 is ex-facie not
maintainable, as the Complainant has already entered into a full and final settlement and
received a total sum of Rs. 33,35,598/-, comprising Rs. 15,70,600/- towards the consideration
paid and Rs. 17,64,998/- as compensation totaling to Rs. 33,35,598 and the same was
transferred from its (Respondent) Axis Bank account in three equal installments of Rs.
11,11,866/-
on
16.04.2024,
28.05.2024,
and
25.07.2024,
respectively,
to
the
complainant'sbank account.
Page 3 of 9
The Respondent further submitted that the Complainant remained informed and was a
witness to the project's developments throughout that period. Eventually, at the
Complainant’s request, it (Respondent) agreed to cancel the booking and refunded the entire
amount of Rs. 33,35,598/- as detailed herein above. Having voluntarily accepted the refund
without any protest, the Complainant is now estopped from re-agitating the same grievance
before this Authority, and the attempt to seek further relief under Section 18 of the Act is
legally unsustainable.
12.
The Respondent further submits that the Complainant withdrew from its project on his
own volition and received due compensation. This present complaint, seeking additional
refund, interest, and compensation, amounts to forum shopping and abuse of the legal
process, and that the allegation made in the rejoinder regarding coercion in arriving at the
settlement is a fabricated afterthought, solely intended to justify filing of this frivolous
complaint.
13.
The Respondent has also submitted a memo before this authority stating that basing
on it the Compensation amount of Rs. 17,65,600/- was paid to the complainant. That the said
settlement was arrived at pursuant to several deliberations that were had with the
Complainant and was also done as per the Complainant’s consent vide his email
communication dated 09.09.2023, wherein the Complainant has requested it (Respondent) to
proceed with payment at 9% per annum (from January, 2012 to December, 2023 i.e. 12 years
X Rs. 141300 16,95,600/- + 70,000/- for 6 months i.e. from Jan to June, 2024, totalling to Rs.
17,65,600/-), as a condition for cancellation of the flat and the amount was worked out to
33,35,600/-, which was the basis for making the payment of Rs.33,35,600/- (Rupees Thirty
Three Lakh Thirty Five Thousand Six Hundred Only) to the Complainant. The Respondent
has attached the email of the complainant addressed to it(Respondent) company dated
08.09.2023.
14. The Respondent further submitted that the Complainant, despite receiving of the final
payment from the it(Respondent), has approached the RERA authorities for compound
interest, which is against their earlier understanding, and the same is arbitrary and irrational
and hence in conclusion, it(Respondent) prayed this Hon’ble Authority to dismiss the
complaint.
Page 4 of 9
The Complainant in his rejoinder submitted that the Respondent has made deliberate
misrepresentations before this authority, which include false statements, unauthorised sale of
the flat, and failure to provide possession.
16.
The Complainant submits that if the approvals were pending then the Respondent
should not have collected 70% of amount, that the reasons for settlement was that the
Respondent refused to provide the flat, that the Respondent also had sold the flat unilaterally
and illegally without informing to him (Complainant) and obtaining of NOC from the bank
and that since 2011, he (Complainant) suffered from the actions of the Respondent.
17.
The Complainant further submitted that the Respondent has made a partial payment of
Rs. 33,35,598/- towards the total compensation amount; however, the total amount due,
including principal and compound interest at 10.75% per annum (HDFC bank loan) from Dec
2011 to Feb 2025 is Rs. 68,42,782/- and that after deducting the partial payment of Rs.
33,35,598/-, the remaining outstanding balance due to him is Rs. 27,07,184/-, and prayed to
grant reliefs as prayed for by him.
E. Points for consideration:
18.
Based on the facts and circumstances of this case, the following questions came up for
consideration before us:
I. Whether the present complaint is maintainable before this
Authority? If so, to what extent?
II. Whether the Complainant is entitled to the reliefs sought for?
F. Observation of the Authority:
19.
It is desirable to discuss the point I and II together to avoid repetition in discussing the
material available on record before this authority.
20.
Upon examining the material available on record before this authority and
consideration of the oral and written submissions made by both the parties, it is evident that
the facts which are not in disputed and admitted facts are that the Complainant booked flat
No. 2817 of block 2B of Janapriya Nile valley Hyderabad, with an area of 1060 sq. ft and
Page 5 of 9
21.
While so it is the claim of the Complainant that though he had paid 70% of the flat
cost to the Respondent, it had delayed the completion of the construction of Block 2B. It is
also the case of the Complainant that the Respondent was unresponsive to his emails and
phone calls. Eventually, he was offered a shift to Block 2A, where construction was ongoing,
but the said shift had not materialised. In the meanwhile, the Respondent sent a cancellation
notice citing non-payment of amounts due by him and thereafter came to know that the flat
no. 2817, booked by him, was sold to another buyer without his consent, and after several
failed attempts to resolve the issue amicably, he requested a refund for the amount paid by
him along with interest. However, the interesting aspect that has to be taken note of is that in
the rejoinder, he took a different stand, contending that his said booked flat was fraudulently,
unilaterally and illegally sold to another buyer without informing him or obtaining NoC from
his bank. He also contended that he was forced into the settlement. Now, the question is
whether such contentions taken in the rejoinder can be sustained or not. In this context, it is
very pertinent to take note of the Email dated 08.09.2023 sent by him to the Respondent,
which was brought on record before this authority by the Respondent. A careful perusal of
the same it will be evident that he had agreed for the cancellation of the said flat and also
agreed to receive Rs. 33,00,000/- towards full and final settlement. Thus this email will make
it clear that the Complainant himself had voluntarily agreed for the cancellation of the flat
booked by him and also agreed to receive Rs. 33,00,000/- towards refund amount. If really,
he was coerced or pressurised to agree to the cancellation of the said flat booked by him, then
in all probability, he would not have sent the said email agreeing to the cancellation of the flat
and for receiving of Rs. 33,00,000/- towards the refund amount. Therefore, in these
circumstances, the above-highlighted contention of the Complainant taken in the rejoinder
appears to have been taken as an afterthought and as such the same cannot be sustained.
22.
Further, as can be gathered from the material available before this authority, the
Respondent has refunded an amount of Rs. 33,35,598/-, in 3 equal instalments that is to say
Rs.11,18,666/- on 3 occasions, on 16.04.2024, on 28.05.2025, and on 25.07.2024 through
online transfers from its (Respondent's) Axis Bank account to the (Complainant's) ICIC Bank
Page 6 of 9
Rs. 33,35,598/- from the
Respondent towards the agreed refund as a full and final settlement. Which, in all probability,
should have included the sale consideration amount of Rs. 15,70,000/- paid by him to the
Respondent and the balance amount of Rs. 17,65,598/- towards compensation amount.
Admittedly receiving of the said amount of Rs.33,35,598/- was not denied by the
Complainant when that is so now it has to been seen whether the relief sought for by him in
the present complaint to order refund of all payments made by him to the Respondent
amounting to Rs. 17,70,000/- with an interest of 12% per annum for the delayed period of 13
years which totals to approximately Rs. 68,50,684/-, compensation amount of Rs. 18,00,000/for the financial burden due to loss of rent due to his home loan amount for the period 20122024, and further compensation of Rs. 10,00,000/- for mental and emotional distress caused
by the builder continued delay, false promises and lack of communication.
23.
In this context, it is very useful to look into Section 18 of the RE(R&D) Act, 2016,
which deals with the return(refund) of the amount and compensation. For clarity and
convenience sake, the relevant portion of section 18 of the Act is extracted hereunder: 18. Return of amount and compensation: (1) If the promoter fails to complete or is unable to give possession of an apartment, plot
or building: (a) in accordance with the terms of the agreement for sale or, as
the case may be, duly completed by the date specified therein; or
(b) due to discontinuance of his business as a developer on account of
suspension or revocation of the registration under this Act or for any other
reason, he shall be liable on demand to the allottees, in case the allottee
wishes to withdraw from the project, without prejudice to any other
remedy available, to return the amount received by him in respect of that
apartment, plot, building as the case may be, with interest at such rate as
may be prescribed in this behalf including compensation in the manner as
provided under this Act.
24.
A careful reading of the above extracted section 18(1) of the RE (R&D) Act, 2016,
makes it clear that if the promoter fails to complete or is unable to give possession of an
apartment, flat or building (a) in accordance with the terms of the agreement for sale or, as
Page 7 of 9
25.
In the present case, from the discussion made in foregoing para’s it will be evident
that the Complainant himself as per his email dated 08.09.2023, has voluntarily withdrew
from the project of the Respondent and so also received amount of Rs. 33,35,598/- towards
refund amount which was mutually arrived at and accepted by him (Complainant) without
any contemporaneous protest, which included the consideration amount paid by
him(Complainant) to the Respondent and so also agreed additional amount detailed herein
above. On such voluntary withdrawal and receiving of the refund amount in full and final
settlement, he(Complainant) ceased to be an allottee of the flat in the project of the
Respondent. Thus, when he lost the status of allottee in the said project of the Respondent by
voluntarily withdrawing from the project and so also receiving of the agreed refund amount
i.e., Rs. 33,35,598/- by 25.07.2025, he became a stranger to the project of the Respondent and
as such cannot be categorised as an “aggrieved person”. According to section 31(1) only an
aggrieved person can file a complaint with this authority. In these circumstances the present
complaint filed by the complainant invoking statutory reliefs under Section 18(1) before this
authority seeking for refund of Rs. 15,70,000/- with an interest of 12 % per annum for the
alleged delay period of 13 years amounting to Rs. 68,50,684/- and also other reliefs as prayed
for in present complaint cannot be maintained by him before this authority.
26. Even assuming, for the sake of argument, that the Complainant had accepted the amount
under coercion or was influenced by the Respondent to accept the refund, it is pertinent to
note that the Complainant, at that time, had an opportunity to avail statutory remedy under
Section 18 of the RE(R&D) Act, 2016, which he chose not to pursue. Instead, he himself
voluntarily cancelled his booking of the flat, withdrew from the project of the Respondent
and proceeded to accept the agreed refund amount. The fact that remains is that the
Complainant, after receiving of the entire agreed amount by 25.07.2024, approached this
Authority by filing complaint under Form-M, once again claiming the entire amount with
Page 8 of 9
In light of the foregoing discussion and the evidence available on record, this
authority is of the considered view that the present complaint filed by him u/s 31 of the Act is
not maintainable and so also does not warrant further adjudication under the provisions of the
RE (R&D) Act, 2016. Accordingly, the complaint is liable to be dismissed.
29.
In the result, the complaint accordingly dismissed.
Sd/Sri K. Srinivasa Rao,
Hon'ble Member,
TG RERA
Sd/Sri Laxmi Narayana Jannu,
Hon'ble Member,
TG RERA
Sd/Dr. N. Satyanarayana, IAS (Retd.),
Hon'ble Chairperson,
TG RERA
Page 9 of 9
Related Orders
Interim Order Complaint No.228 of 2025
Rangareddy, Telangana, 500077)Order Complaint No. 386 of 2025
Koti, Hyderabad-500027.Order Complaint No. 153 of 2024
Telangana – 500011.Order Complaint No. 152 of 2024
Telangana – 500011.Order Complaint No. 151 of 2024
Telangana – 500011.Need Complete Property Verification?
Get ownership details, EC records, survey sketch, zone checks, geo-insights & AI analysis - all in one place