Order Complaint No. 286 of 2025
Order Details
| Order Type | TG-RERA Authority |
|---|---|
| Complaint/Case Number | Complaint No. 286 of 2025 |
| Year | 2025 |
| Order Category | Regular Order |
| Order Date | 30 Dec 2025 |
| Complainant | Kukatpally, Hyd 500085. |
| Respondent | Road No. 12, Banjara Hills, Hyderabad, Telangana - 500034 |
| PDF Document | Download PDF BU_311225181307803.pdf |
Full Order Text
BEFORE TELANGANA REAL ESTATE REGULATORY AUTHORITY
[Under the Real Estate (Regulation and Development) Act, 2016]
Complaint No. 286 of 2025
Dated: 30th December 2025
Quorum:
Dr. N. Satyanarayana, IAS (Retd.), Hon’ble Chairperson
Sri K. Srinivasa Rao, Hon’ble Member
Sri Laxmi Narayana Jannu, Hon’ble Member
1. Nalluri Chandra Mouli
2. Nalluri Sujatha W/o Nalluri Chandra Mouli
16-31-IX-MIG-11-111, 9th Phase, KPHB Colony,
Kukatpally, Hyd 500085.
…Complainant
Versus
M/s. Vasavi Realtor LLP,
Rep by its Designated Partner, Vijay Kumar Yerram & Kandey Ramesh,
Vasavi Corporate,
H.No.8-2-703/7/1 and 8-2-703/7/1/A,
4th Floor, Vasavi Corporate Building, Amrutha Valley Apartments,
Road No. 12, Banjara Hills, Hyderabad, Telangana - 500034
…Respondent
The present matter filed by the Complainant herein came up for final hearing on
11.07.2025 before this Authority in presence of Complainant and the Respondent; upon
pursuing the material on record and on hearing arguments of both the parties and having stood
over for consideration till this day, the following order is passed:
ORDER
2.
The present Complaint has been filed by the Complainant under Section 31 of the Real
Estate (Regulation & Development) Act, 2016 (hereinafter referred to as the “Act”) read with
Rule 34(1) of the Telangana Real Estate (Regulation and Development) Rules, 2017
(hereinafter referred to as the “Rules”) seeking appropriate relief(s) against the Respondents.
A. The brief facts of the case, as stated by the Complainant, are as follows:
1.
It was submitted that the Complainant had booked a flat, identified as Unit 2-13-05 in
Tower 2 of the project “Vasavi Lake City-East,” on 01.12.2020. The booking was made based
on representations in advertisements, information on the Respondent's website, and interactions
with the marketing team. An Agreement for Sale was subsequently executed on 10.05.2021.
Page 1 of 20
It was stated that out of a total sale consideration of Rs. 1,03,54,980/-, the Complainant
had paid a sum of Rs. 87,00,000/- (Rupees Eighty-Seven Lakhs Only) between December 2020
and March 2021. As per the terms of the Agreement for Sale, the balance amount was to be
paid at the time of registration or possession.
3.
It was further submitted that pursuant to Clause 7.1 of the said Agreement for Sale, the
promoter had provided an assurance to hand over possession of the flat, complete with all
common areas, specifications, amenities, and facilities, on or before August 2023, with an
additional grace period of six months.
4.
It was contended that despite these assurances and the payment of more than eighty
percent of the total consideration by March 2021, the project had faced unjustified delays and
remained incomplete as of April 2025. It was alleged that the Respondent had continuously
postponed the handover date, providing vague reasons and false assurances without
communicating a clear timeline for completion. The Complainant submitted that their
investment of Rs. 87,00,000/- had become unfruitful after a lapse of four years, leaving them
in a state of uncertainty and financial distress.
5.
It was submitted that the continued delay in handing over possession constituted a
serious violation of the provisions of the Real Estate (Regulation and Development) Act, 2016.
It was contended that by collecting a substantial payment upfront and subsequently failing to
fulfill its contractual obligations to deliver the project within the stipulated timeline, the
Respondent had breached the governing guidelines.
6.
It was stated that the prolonged delay, lack of accountability, and failure to provide a
firm completion date had caused the Complainant significant financial strain, mental stress,
and emotional distress. The complaint was therefore filed to seek intervention, financial
compensation, and strict action against the Respondent under Clause 7.6 and other relevant
clauses of the Agreement of Sale and the applicable sections of the RERA Act, Telangana.
B. Reliefs Sought
7.
Accordingly, the Complainant sought the following reliefs:
i.
To direct the Respondent to forthwith complete all pending construction and hand
over possession of the subject flat to the Complainant at the earliest, within a fixed
and enforceable timeframe to be determined by this Honourable Authority, failing
which to impose strict penalties upon the Respondent.
ii.
To direct the Respondent to pay adequate compensation to the Complainant for
the severe mental distress, financial strain, and disruption to personal and
Page 2 of 20
It was submitted by the Respondent that the complaint was not maintainable either in
law or on facts and was liable to be dismissed. The Respondent contended that the Complainant
had failed to follow the remedies available under the Agreement for Sale for the resolution of
disputes before approaching this Hon’ble Authority. It was further submitted that no prior legal
notice was issued before the filing of the complaint, which rendered the application defective.
9.
It was submitted that the project, “Lake City-East,” was developed lawfully after the
Respondent obtained rights from the landowners under registered documents, covering a total
land area of 34,704.37 sq. yds. The requisite permissions for land conversion and for the
construction of multi-storied residential apartments were obtained on 07.02.2020. The project,
consisting of multiple towers and a clubhouse, was duly registered with this Authority vide
Registration No. P02500001821 dated 20.03.2020.
10.
It was further submitted that the Complainant was allotted apartment No. E. 21305 on
the 13th Floor of Tower 2, admeasuring 1990 sq. ft., and an undivided share of 56 sq. of land
under the Agreement of Sale. The agreement detailed the carpet area, balcony area, common
area, and the undivided share of land. The total sale consideration was Rs. 1,03,54,980/-.
11.
It was submitted that as per Clause 7 of the Agreement, the Respondent was obligated
to hand over possession of the apartment on or before 31.08.2024, with a grace period of six
months. The said clause explicitly stated that the period of completion would stand extended
in the event of force majeure conditions, during which the allottee was not entitled to claim any
compensation for the delay.
12.
It was contended that the Complainant had not approached this Hon’ble Authority with
clean hands but with an ulterior motive for unlawful gain, and that there had been a material
suppression of facts. While the existence of the Agreement of Sale was not in dispute, the
Respondent averred that the Complainant made false claims despite being aware of the
contractual terms and circumstances.
13.
The Respondent stated that the project timelines were severely impacted by the
COVID-19 pandemic, which was a force majeure event recognized under law. It was submitted
that following the declaration of a public health emergency in January 2020, a nationwide
Page 3 of 20
The Respondent further relied on the orders of the Hon’ble Supreme Court in Suo Motu
Writ Petition (C) No. 3 of 2020, whereby the period from 15.03.2020 to 28.02.2022 was
excluded for the purposes of computing limitation across all statutes. It was contended that this
legally recognized the extraordinary circumstances and justified the extension of timelines for
project completion.
15.
In addition to the pandemic, the Respondent submitted that the project was delayed by
other unforeseen factors. It was stated that the project site contained rocky terrain which, due
to its location in a residential vicinity, could not be excavated using explosives. The consequent
need for manual rock-breaking compounded the construction delays. Furthermore, the project
was adversely impacted by third-party disputes, including several legal proceedings filed
against the project, such as RERA Case No. 190/2020, W.P. No. 2694/2021, and W.P. No.
26301/2024, which hindered its smooth progress. These challenges were communicated to the
customers in periodic meetings.
16.
It was contended that any clerical or typographical errors in the Agreement of Sale,
such as an incorrect possession date mentioned in one instance, could not be exploited to create
liability, especially when the magnitude of the project made such a timeline practically
impossible. The Respondent asserted that the project was over 90% complete and in the final
finishing stages. An extension for the project registration had been granted by this Authority
up to 07.02.2026, and the Respondent gave an undertaking to deliver the apartments within this
extended period.
17.
With regard to the claims for interest and compensation, the Respondent submitted that
such reliefs were not maintainable in view of the force majeure conditions. It was argued that
the circumstances clearly fell within the definition provided under Section 6 of the Act. The
Respondent maintained that the delay was not due to any deliberate act or default on its part,
and therefore, the Complainant had not established any legal basis for claiming compensation
for mental agony or financial loss.
Page 4 of 20
The Respondent concluded that the complaint was preposterous and without
foundation. It was prayed that the complaint be dismissed and the Respondent be allowed to
complete the project and deliver possession to all allottees as per the extended timeline.
D. Rejoinder filed by the Complainants.
19.
It was submitted in response to the preliminary objection on maintainability, that the
said objection was not only vague but legally unfounded. The complaint had been filed under
Section 31 of the Real Estate (Regulation and Development) Act, 2016, which provided an
explicit statutory right to any aggrieved allottee to seek relief. It was stated that the Agreement
of Sale dated 10th May 2021 clearly stipulated the committed possession date as 31st August
2023, and as the flat remained undelivered, the complaint was well within legal bounds.
20.
The contention that the Complainant had not availed methods as provided in the
agreement was described as wholly misconceived and devoid of any merit. It was submitted
that the Respondent's reliance on internal dispute resolution mechanisms was irrelevant and
legally unsustainable. It was stated that the Complainant, along with other allottees, had
approached the Respondent's office in good faith, but the Respondent failed to provide any
definitive timeline and arbitrarily altered proposed delivery dates. It was further stated that the
Complainant had made repeated attempts to communicate with the Respondent, but these
efforts were met with consistent avoidance tactics and an endless loop of blame-shifting
between internal teams, which effectively stonewalled the Complainant.
21.
The objection regarding the non-issuance of a legal notice was submitted as being
without merit, as there was no such legal mandate under RERA to issue a prior notice.
22.
It was stated that the Respondent's development rights and the permissions obtained for
construction were not in dispute; the issue lay in the Respondent's failure to deliver possession
on time as per contractual obligations.
23.
It was submitted that while the project was registered with RERA, the Respondent had
grossly failed to abide by the obligations that accompanied such registration, particularly those
relating to timely possession and transparency. The Respondent's conduct post-registration
showed a blatant disregard for the regulations, and their reply demonstrated a shocking lack of
respect towards the Hon'ble Authority.
24.
It was submitted that as per the RERA framework, the Agreement of Sale dated 10th
May 2021 was the only binding document, which included the crucial possession commitment
of 31st August 2023. The Complainant had duly paid a sum of ₹87,00,000/- towards the
Page 5 of 20
The Respondent's reliance on a RERA extension was described as legally flawed and
misleading. It was submitted that the possession date as agreed between the parties, 31st August
2023, must prevail for assessing delay, irrespective of any regulatory extensions. The
Respondent's conduct, in now citing a delivery date of February 2026, rendered the contract
meaningless.
26.
The Complainant fully acknowledged the payment of ₹87,00,000/-. However, it was
submitted that the Respondent's attempt to divert the discussion toward specifications was
unrelated to the core issue of delay in possession. It was clarified that the balance consideration
was expressly linked to registration and possession milestones, and any insinuation that
payments were overdue was factually incorrect.
27.
It was submitted that the Respondent had selectively cited clauses from the Agreement
to justify their delay. The Respondent had far exceeded even the six-month grace period. The
repeated reference to force majeure was described as legally untenable and factually
inapplicable, as the Agreement of Sale was executed on 10th May 2021, well after the nation
had emerged from full lockdown. It was argued that force majeure clauses could not override
statutory protections afforded to allottees under Section 18(1) of the RERA Act.
28.
The Respondent's selective quoting of Clause 7.2 was stated to be entirely misplaced,
as the condition precedent of obtaining an occupancy certificate (OC) had not been met. It was
submitted that Clause 9, which dealt with promoter defaults, must now be actively enforced as
the Respondent had unambiguously breached the possession timeline.
29.
The Complainant categorically denied the baseless, vague, and defamatory allegations
of acting with an "ulterior motive." It was submitted that the Complainant had made full
disclosure of all material facts, including the Agreement for Sale and proof of payments
totalling ₹87,00,000/-, whereas the Respondent had repeatedly failed to meet their own
promised timelines.
30.
While the impact of the COVID-19 pandemic was acknowledged, it was submitted that
the Respondent's reliance on it was misleading, as the Agreement for Sale was executed on
Page 6 of 20
It was submitted that the legal provisions and extensions cited by the Respondent
related solely to statutory periods of limitation for filing legal proceedings and had no
applicability whatsoever to the contractual obligations of a real estate developer under the
RERA Act.
32.
The attempt to attribute the delay to labour migration was stated as not being applicable
to the facts, as the Complainant's unit in Tower Two had been structurally completed, and the
subsequent delay reflected a lack of intent and mismanagement on the part of the builder. It
was also stated that there was no documentary evidence to support the claim that allottees were
formally informed of such delays.
33.
The Respondent's statement regarding "various additional factors" was described as
vague, evasive, and devoid of any factual backing. It was submitted that the claim that
"customers were intimated from time to time" was simply untrue in the Complainant's case.
34.
The response by the Respondent, terming the committed possession date in a formally
executed Agreement of Sale as a product of "clerical and typographical mistakes," was
described as both self-incriminating and legally indefensible. It was pointed out that the
Respondent had, with wrong motive, distorted the facts by mentioning the AOS date as 21-102023 and possession date as 31-08-2024 in the rejoinder, whereas the Complainant's actual
agreement was dated 10th May 2021 with a possession date of 31st August 2023. This was
submitted as a dishonest afterthought reflecting a complete abdication of responsibility.
35.
It was submitted that while certain legal disputes may have arisen, the mere existence
of litigation involving third parties could not be used as a blanket justification for delay. It was
the legal responsibility of the promoter under Section 11(3)(a) of the RERA Act to ensure the
project was free of encumbrances.
36.
The Complainant challenged the Respondent to produce any formal written
communication that proactively disclosed delays. It was submitted that the pattern of repeatedly
outlining and then dishonouring revised timelines reflected a calculated approach to deflect
pressure, and to now question the reasonableness of pursuing a claim under RERA was deeply
unjust.
37.
The Complainant submitted that the claim for interest was a non-negotiable and
unconditional statutory right under Section 18(1) of the Act. The reliance on force majeure due
Page 7 of 20
The Respondent's statement regarding compensation was stated to reflect complete
insensitivity to the real and severe consequences faced by the Complainant, which had been
clearly laid out in Form M.
39.
The Complainant strongly objected to the Respondent's claim that delivery was now
scheduled for February 2026 and that the Complainant had defaulted on payments. It was
asserted that the Complainant had never agreed to any extension and was not in arrears, having
paid 82% of the consideration as of March 2021. The Respondent's "unconditional
undertaking" was stated as not waiving their legal liability for interest.
40.
The response regarding the Complainant agreeing to the delay was described as another
attempt to deflect responsibility using afterthought excuses. It was stated that the Complainant
never agreed to excuse the delay. The new claim about rocky terrain reflected a lack of due
diligence and was a foreseeable project risk, not force majeure.
41.
The Respondent's statement that the Complainant was not entitled to any relief was
described as a sweeping and baseless denial of liability. It was submitted that the Respondent's
generic claim that the delay was "beyond their control" had been repeatedly refuted.
42.
Finally, it was submitted that the Respondent's characterization of the complaint as
"preposterous" and "false" was unfounded. The Respondent's claimed reputation could not
override the specific facts of the case. The Complainants respectfully prayed that the Hon'ble
Authority take cognizance of the material facts and pass appropriate directions.
43.
It was most respectfully requested that the Hon'ble Authority take cognizance of the
procedural and substantive lapses on the part of the Respondent, namely: that the counter
statement was unsigned; that the Respondent had failed to furnish proper evidence; and that
the Respondent had not undertaken a proper rebuttal of the documents annexed by the
Complainant.
E. Points for Consideration
44.
Upon a careful perusal of the record and the submissions advanced by both parties, oral
as well as written, this Authority is of the view that the following issues arise for determination
in the present complaint:
Page 8 of 20
The Respondent has raised an objection as to the maintainability of the present
complaint on the ground that the Complainants failed to first resort to the contractual dispute
resolution mechanism envisaged in the Agreement of Sale, namely an amicable settlement by
mutual discussion, prior to approaching this Authority. The Authority finds this objection
untenable for the following reasons:
46.
The Authority finds this objection untenable for the following reasons: The relevant
Dispute Resolution clause in the Agreement of Sale is reproduced below for ready reference:
“33. Dispute Resolution clause in the Agreement of sale executed between the parties,
the said clause stated that all or any disputes arising out ot touching upon or in relation
to the terms and conditions of this Agreement, including the interpretation and validity
of the terms thereof and the respective rights and obligations of the Parties, shall be
settled amicably by mutual discussion, falling which the same shall be settled through
adjudication officer appointed under the Act.”
47.
It is clear from the above that the clause only requires the parties to attempt an amicable
settlement by mutual discussion. Such a clause is at best directory and cannot oust or restrict
the statutory jurisdiction of this Authority. Section 79 of the RE(R&D) Act expressly bars the
jurisdiction of Civil Courts in respect of any matter which this Authority, the Adjudicating
Officer, or the Appellate Tribunal is empowered to determine. Likewise, Section 88 clarifies
that the provisions of the RE(R&D) Act are in addition to, and not in derogation of, other laws.
Thus, the intention of the legislature is that remedies under this beneficial legislation must
remain open to allottees, irrespective of any private clause for amicable settlement.
48.
Even in cases where agreements contained arbitration clauses (which is not the case
here), the Hon’ble Supreme Court and the Hon’ble NCDRC have consistently held that such
clauses cannot circumscribe the jurisdiction of consumer fora or statutory authorities
constituted under special enactments.
49.
In National Seeds Corporation Ltd. v. M. Madhusudhan Reddy (2012) 2 SCC 506, the
Supreme Court held that remedies under special statutes are in addition to, and not in derogation
of, other remedies. For ready reference, the relevant extract is reproduced below:
Page 9 of 20
Similarly, in Aftab Singh &Ors. v. Emaar MGF Land Ltd. &Ors. (Consumer Case No.
701 of 2015, decided on 13.07.2017), it was held that arbitration clauses in builder-buyer
agreements cannot oust the jurisdiction of consumer fora. The said view was later upheld by
the Hon’ble Supreme Court in Civil Appeal Nos. 23512–23513 of 2017. The relevant para
reads:
“25. This Court in the series of judgments as noticed above considered the provisions
of Consumer Protection Act, L986 os well as Arbitration Act, 1996 and laid down that
complaint under Consumer Protection Act being a special remedy, despite there being
an arbitration agreement the proceedings before Consumer Forum have to go on and
no ercor committed by Consumer Forum on rejecting the application. There is reason
for not interjecting proceedings under Consumer Protection Act on the strength an
arbitration agreement by Act, 1996. The remedy under Consumer Protection Act is a
remedy provided to a consumer when there is a defect in any goods or services. The
Page 10 of 20
In the present matter, there is only a clause requiring amicable discussion before
invoking remedies. Such a clause is directory at best, and cannot override or defeat the statutory
right of the Complainant to approach this Authority under the RE(R&D) Act. Accordingly, this
Authority has no hesitation in holding that the Complainant is well within its rights to approach
this forum without being first compelled to pursue an amicable settlement under the
Agreement. The objection of the Respondent as to maintainability is therefore rejected.
Point No. 2:
52.
The Complainant has sought relief on the ground that there has been an inordinate
delay in handing over possession of the subject flat, despite timely payments of approximately
80% of the total sale consideration, causing significant financial and emotional distress. It is
the case of the Complainant that the Agreement of Sale dated 10.05.2021 clearly stipulated that
possession of the subject flat would be handed over by 31.08.2023, with a grace period of six
months, ending on 28.02.2024. The Respondent has failed to hand over possession even as of
February 2025. Further, although the project was registered with TG RERA up to February
2025 and later extended until 07.02.2026, the project remains incomplete, with construction
progress stalled at approximately 65-70% as per the Complainant’s submission, with key
aspects such as interior finishing, common amenities, and supporting infrastructure remaining
unfinished. The Complainant submits that the Respondent has issued multiple revised handover
schedules without providing valid justification or a clear roadmap for completion.
53.
The Complainant further submits that despite assurances made, including a promise to
pay compensation for delay as per RERA guidelines, no such compensation has been provided.
The Respondent, conversely, attributes the delay to the Covid-19 pandemic, claiming force
majeure, citing the nationwide lockdown beginning March 2020, the impact on migrant labour,
and consequential delays. The Respondent further cites rocky terrain at the site, third-party
disputes, and typographical errors in the possession date as additional justifications.
Page 11 of 20
This Authority finds no merit in such a contention. The Agreement of Sale was
executed on 10.05.2021, well after the onset and initial impact of the Covid-19 pandemic. The
Respondent, being fully aware of the prevailing circumstances, nevertheless executed the
Agreement by specifically assuring completion of the project by August 2023. Having
consciously undertaken such commitment, the Respondent cannot now, with retrospective
justification, rely on Covid-19 as a defense to escape its contractual and statutory obligations.
Such conduct clearly amounts to holding out false assurances with mala fide intent.
55.
It is a settled principle that once a promoter has chosen to register a project and enter
into binding contractual commitments with allottees, he does so with full knowledge of the
risks, constraints, and challenges of the market. At the time of entering into the Agreement of
Sale with the present Complainant, the Respondent was already aware of the Covid-related
disruptions, as well as the Government notifications granting moratoriums for project
completion timelines. Despite this knowledge, the Respondent chose to provide a specific
assurance of delivery by August 2023.
56.
This Authority aligns with the observations of the Hon’ble Bombay High Court in
Neelkamal Realtors Suburban Pvt. Ltd. &Anr. vs. Union of India &Ors. [2017 SCC OnLine
Bom 9302], wherein at para 119 it was categorically observed:
"While the proposal is submitted, the Promoter is supposed to be conscious of the
consequences of getting the project registered under RERA. Having sufficient
experience in the open market, the Promoter is expected to have a fair assessment of
the time required for completing the project…".
57.
The above dictum fortifies the principle that the promoter, being structurally at an
advantageous position with respect to project information and market realities, is under a
statutory duty to provide realistic timelines. The framework of the Real Estate (Regulation and
Development) Act, 2016 reinforces this obligation by mandating timely completion and
possession within the period stipulated in the Agreement of Sale.
58.
Therefore, the plea of Covid-19 as a force majeure defence in the present case is wholly
untenable. The Respondent, having executed the Agreement of Sale in May 2021 with specific
Page 12 of 20
The Respondent has further contended that, since extensions have been granted by this
Authority, the project timeline now stands extended up to February 2026, and therefore
possession shall be delivered by then. The Complainants, however, have questioned the validity
and effect of such extensions.
60.
At the outset, it must be clarified that under the scheme of the RE(R&D) Act:
“An Act to establish the Real Estate Regulatory Authority for regulation and promotion
of the real estate sector and to ensure sale of plot, apartment or building, as the case
may be, or sale of real estate project, in an efficient and transparent manner and to
protect the interest of consumers in the real estate sector and to establish an
adjudicating mechanism for speedy dispute redressal and also to establish the
Appellate Tribunal to hear appeals from the decisions, directions or orders of the Real
Estate Regulatory Authority and the adjudicating officer and for matters connected
therewith or incidental thereto.”
61.
The paramount objective is twofold: protection of consumer interest, and ensuring
completion of projects in an efficient manner. Denial of extension during the Covid-19
disruption would have resulted in projects being stalled, to the grave prejudice of allottees. It
was in this context that this Authority, balancing the equities, granted extensions in line with
the moratoriums issued by Telangana RERA:
1. 15.03.2020 to 14.09.2020 (Circular No.14 dated 13.05.2020),
2. 15.09.2020 to 15.03.2021 (Order No.15 dated 29.09.2020),
3. 15.03.2021 to 14.09.2021 (Order No.16 dated 01.06.2021).
62.
Accordingly, an aggregate 18 months’ extension was applied across projects to
safeguard larger consumer interest. However, it is equally well settled that such regulatory
extensions cannot dilute the contractual rights of individual allottees under their respective
Agreements of Sale, nor can they displace the statutory rights flowing from Section 18 of the
RE(R&D) Act.
Page 13 of 20
In the present matter, it is evident that the Respondent has unilaterally revised
possession timelines first to February 2024, and thereafter to February 2026 due to the
extension taken without consultation or consent of the Complainants. Such unilateral revisions
are impermissible. The Hon’ble Bombay High Court in Neelkamal Realtors Suburban Pvt. Ltd.
vs. Union of India &Ors. [2017 SCC OnLine Bom 9302], while upholding the constitutional
validity of RERA, categorically observed:
Para 119 “The RERA does not contemplate rewriting of contract between the flat
purchaser and the promoter.”
Para 256 of this Judgment further clarifies that “by giving opportunity to the promoter
to prescribe fresh timeline under Section 4(2)(l)(C), he is not absolved of the liability
under the agreement for sale”
64.
The above dicta makes it abundantly clear that any extension granted by the Authority,
or revised timelines uploaded on the TG RERA project registration portal, do not ipso facto
alter or bind the allottees’ contractual rights. The agreed date of possession remains as
stipulated in the Agreement for Sale, and unilateral extensions by the promoter cannot be
foisted upon allottees to their detriment.
65.
Accordingly, this Authority holds that the revised possession dates mentioned by the
Respondent, whether while seeking extensions before the Authority or as updated on the
registration portal, cannot be treated as binding on the Complainants.
(iii)Relief under Section 18 of the RE(R&D) Act:
66.
It has been observed by this Authority that the total sale consideration is for an amount
of Rs. 1,03,54,980/- (Rupees One Crore Three Lakh Fifty Four Thousand Nine Hundred And
Eighty Only). That, as per the Agreement of Sale as well as the submissions made by the
Complainant, the Complainant has paid an amount of Rs.87,00,000/- (Rupees Eighty Seven
Lakh Only) has been duly paid towards the sale consideration. Further, the Agreement of Sale
clearly stipulated possession by 31.08.2023, with a grace period of 6 months to 28.02.2024.
Admittedly, possession has not been delivered.
67.
The Respondent’s contention that 90% work is complete and that the Complainants
have paid only a portion of the consideration is wholly unsustainable. The Complainants have
already paid over 80% of the agreed consideration as per their averments. Despite receiving
Page 14 of 20
The Respondent further seeks to shift the burden on the complainant by contending that
the balance amount is unpaid. This plea is untenable. The law does not permit a defaulter to
take advantage of its own breach. As held by the Hon’ble Supreme Court in Kusheshwar
Prasad Singh v. State of Bihar [Civil Appeal No. 7357 of 2000]:
“It is settled principle of law that a man cannot be permitted to take undue and unfair
advantage of his own wrong to gain favourable interpretation of law. It is sound
principle that he, who prevents a thing from being done shall not avail himself of the
non-performance he has occasioned. To put it differently, "a wrongdoer ought not to
be permitted to make a profit out of his own wrong”
69.
In this context, it is pertinent to note that the Agreement of Sale linked the payment
schedule to the progress of construction. While the allottees are indeed bound to adhere to the
agreed payment plan, such obligation arises only when the promoter simultaneously fulfils its
reciprocal obligation of executing construction in line with the assured progress. In the absence
of such progress, the Respondent cannot insist upon further payments as a condition to claim
relief.
70.
Section 18 of the RE(R&D) Act is categorical and unconditional. It does not make the
grant of interest contingent upon the quantum of sale consideration paid, nor does it provide
any defence to a defaulting promoter. Once delay in handing over possession is established, an
allottee who elects to remain in the project is entitled to interest for every month of delay,
irrespective of whether part or whole of the consideration has been paid, provided that the
payments already made are in accordance with the Agreement of sale. The Respondent’s plea
that only partial sale consideration has been paid and hence interest cannot be granted is
therefore vague, misconceived, and contrary to the express mandate of the statute. Now,
Section 18 of the RE(R&D) Act is categorical:
“(1) If the promoter fails to complete or is unable to give possession of an apartment,
plot or building,—
Page 15 of 20
This statutory right of allottee is unqualified and absolute. Attention is drawn to the
decision of the Hon'ble Supreme Court of India in Civil Appeal Nos. 3581-359 of 2022, Civil
Appeal Diary No. 9796/2019, M/s Imperia Structures Limited vs. Anil Patni & Others,
wherein it was held:
"In terms of Section 18 of the RERA Act, if a promoter fails to complete or is unable to
give possession of an apartment by the date specified in the agreement, the promoter
would be liable, on demand, to return the amount received in respect of that apartment
if the allottee wishes to withdraw from the project. Such a right of the allottee is 'without
prejudice to any other remedy available to him'. This right is unqualified, and if availed,
the deposited money must be refunded with interest as prescribed. The proviso to
Section 18(1) contemplates that if the allottee does not intend to withdraw from the
Page 16 of 20
Similarly, in Civil Appeal Nos. 6745-6749 of 2021, M/s Newtech Promoters and
Developers Private Limited vs. State of UP & Others, the Hon’ble Supreme Court observed:
"Section 18(1) of the Act spells out the consequences if the promoter fails to complete
or is unable to give possession of an 9 of 10 apartment, plot, or building in terms of the
agreement for sale. The allottee/home buyer holds an unqualified right to seek a refund
of the amount with interest as prescribed."
73.
Further, as earlier observed, the Hon’ble Bombay High Court in Neelkamal Realtors
Suburban Pvt. Ltd. v. Union of India [(2017) SCC Online Bom 9302] clarified that RERA
registration or its extension cannot rewrite the contract between parties. The date assured under
the Agreement of Sale, executed with the allottee’s consent, shall prevail. Thus, the Respondent
is bound by Section 11(4)(a) of the RE(R&D) Act, which mandates adherence to the terms of
the Agreement of Sale.
74.
At the same time, if the Complainant has indeed defaulted in adhering to the payment
schedule, the Respondent is not without remedy. Sections 19(6) and 19(7) of the Act confer
upon the promoter a right to claim interest for delayed payments, as per Rule 15 of the
Telangana RE(R&D) Rules, 2017. Nevertheless, such entitlement shall be subject to the
Respondent producing cogent and substantive documents demonstrating both the stage-wise
progress of construction and the corresponding default, and not merely based on unilateral
assertions.
75.
In the present case, this Authority finds the Respondent in clear breach of both statutory
and contractual obligations. The Complainant is therefore entitled to interest at the prescribed
rate for the entire period of delay, i.e., from 01.03.2024 until the actual date of handing over
possession. As regards claims of compensation, this Authority notes that jurisdiction for
adjudicating compensation lies with the Adjudicating Officer under Section 71 of RE(R&D)
Act with Form ‘N’. The Complainant is at liberty to pursue such remedy separately.
76.
Accordingly, while the Complainant is entitled to relief under Section 18 of the
RE(R&D) Act, this entitlement is subject to the reciprocal statutory duty of the Complainant
Page 17 of 20
This Authority cannot remain oblivious to the larger pattern of violations. It is noted
with grave concern that more than fifty complaints have already been received against this very
Respondent in respect of the subject project. Such repeated defaults and false assurances strike
at the very root of the confidence that homebuyers are entitled to repose under the protective
framework of the RE(R&D) Act.
78.
The Statement of Objects and Reasons of the RE(R&D) Act explicitly emphasizes
“greater accountability towards consumers and to inject transparency, efficiency, and discipline
in the real estate sector”. The conduct of the Respondent herein is in gross derogation of that
legislative mandate. If such violations are permitted to persist, the very soul of the Act would
stand diluted and the protection promised to allottees rendered illusory. Accordingly, this
Authority hereby sternly warns the Respondent promoter that any further default, noncompliance, or failure to deliver possession within the assured statutory timelines or any fresh
grievances brought to notice by allottees shall invite invocation of Section 63 of the RE(R&D)
Act.
79.
This Authority shall not hesitate to take the strictest view in future, for the Act was
enacted not as a mere regulatory framework but as a beneficial legislation to protect innocent
homebuyers from the very malaise exemplified by the conduct of this Respondent.
80.
The Respondent is hereby directed to complete the project and hand over possession to
the Complainants within the stipulated period. It is further clarified that if the Complainants
have defaulted in making payments as per the agreed schedule, the Respondent shall be entitled
under Section 19(6) of the Act to claim interest on such delayed payments, provided that it
substantiates such claim with credible documentary evidence of both construction progress and
corresponding default.
81.
In the event the Complainants have defaulted in making payments as per the agreed
schedule, the Respondent shall be entitled, under Section 19(6) of the Real Estate (Regulation
and Development) Act, 2016, to claim interest on such delayed payments in accordance with
Rule 15 of the Telangana Real Estate (Regulation and Development) Rules, 2017.
Nevertheless, such entitlement shall be subject to the Respondent producing cogent and
Page 18 of 20
The Complainants are, in turn, directed to discharge any balance amounts due under
the agreed payment schedule, if not already paid. Mutual compliance is essential to ensure
timely completion and delivery of the project.
G. Directions of the Authority:
83.
In view of the findings and observations recorded hereinabove, this Authority proceeds
to issue the following directions:
a. The preliminary objection raised by the Respondent regarding the maintainability of
the complaint on account of the Dispute Resolution Clause in the Agreement of Sale
stands rejected. The complaint is maintainable before this Authority.
b. The Respondent’s reliance on the Covid-19 pandemic as a ground of force majeure is
held untenable, since the Agreement of Sale was executed after the subsiding of the
pandemic and with full knowledge of the prevailing circumstances.
c. The extension of registration taken by this Respondent cannot dilute the contractual
rights of the Complainant under the Agreement of Sale. The date of possession as
stipulated in the Agreement shall prevail.
d. The Respondent is held liable for failure to hand over possession of the subject flat by
the agreed date i.e., 28.02.2024 (inclusive of grace period).
e. The Complainants are entitled to interest at the rate of 10.70% per annum (being SBI
MCLR + 2% as per Rule 15 of the TG RE(R&D) Rules, 2017), computed on the
amounts actually paid by the Complainants, with effect from 01.03.2024 until actual
handing over of lawful possession. The exact computation shall be subject to
verification of such payments by the Respondent at the stage of effecting payment. The
Respondent shall pay the arrears accrued up to the date of this Order within sixty (60)
days, and shall thereafter continue to pay the accruing interest on a monthly basis, on
or before the 10th day of each succeeding month, until possession is delivered.
f. Insofar as compensation is concerned, the Complainant is at liberty to pursue
appropriate proceedings before the Learned Adjudicating Officer under “Form N”.
g. The Respondent is hereby directed to complete the project forthwith and hand over
possession to the Complainants within the statutory timelines.
Page 19 of 20
Having regard to the repeated defaults and the large number of complaints already
pending against this Respondent in the same project, this Authority sternly warns the
Respondent that any further delay, non-compliance, or grievance brought to notice by allottees
shall invite section 63 of the RE(R&D) Act.
85.
The Complaint is accordingly allowed in part, in terms of the above directions.
86.
Failure to comply with above said directions by the Respondent shall attract penalty in
accordance with Section 63 of the RE(R&D) Act, 2016
87.
As a result, the Complaint is disposed of accordingly. No order as to costs.
Sd/Sri K. Srinivasa Rao,
Hon’ble Member,
TG RERA
Sd/Sri Laxmi Narayana Jannu,
Hon’ble Member,
TG RERA
Sd/Dr. N. Satyanarayana, IAS (Retd.),
Hon’ble Chairperson,
TG RERA
Page 20 of 20
Related Orders
Interim Order Complaint No.228 of 2025
Rangareddy, Telangana, 500077)Order Complaint No. 386 of 2025
Koti, Hyderabad-500027.Order Complaint No. 153 of 2024
Telangana – 500011.Order Complaint No. 152 of 2024
Telangana – 500011.Order Complaint No. 151 of 2024
Telangana – 500011.Need Complete Property Verification?
Get ownership details, EC records, survey sketch, zone checks, geo-insights & AI analysis - all in one place