BEFORETELANGANAREALESTATEREGULATORY AUTHORITY
[Under the Real Estate (Regulation and Development) Act,2016]
Complaint No. 282 of 2024
Corum:
19th April,2025
Dr.N. Satyanarayana, IAS(Retd.), Hon’ble Chairperson
Sri K. Srinivasa Rao, Hon’ble Member
SriLaxmi Narayana Jannu, Hon’ble Member
Mr. Gudala Ganesh Sai Prasanna
Flat No 529, Ishta City, Bapughat Road
Attapur, Hyderabad,
Telangana- 500048
…Complainant
Versus
1.M/s Bricmor VR LLP
Plot No. 47, 3rd floor, Lumbini Avenue
Behind Hyderabad Bicycling Club
Gachibowli
Hyderabad, Telangana-500081
2.Nallamilli Srinivasa Reddy
R/o 6-127, Magadha Village
Kokapet, C.B.I.T, K.V Ranga Reddy District
Hyderabad, Telangana-500032
…Respondent(s)
This present Complaint came up for hearing on 27.03.2025 before this Authority, in the
presence of Complainant in person, Mr. B.S. Reddy, learned Counsel, appeared on behalf of the
Respondent. Upon taking into consideration the submissions made by the Complainant, this
Authority proceeds to pass the following ORDER:
2.
The Complainant has filed complaint under Section 31 of the Real Estate(Regulation and
Development) Act, 2016 (hereinafter referred to as the "RE (R&D) Act"), read with Rule 34(1) of
the Telangana Real Estate (Regulation and Development) Rules, 2017 (hereinafter referred to as
the "Rules"), alleging commission of violation of the said Act and Rules and sought for the
appropriate reliefs against the Respondent.
3.
On 20.02.2025, the Complainant filed a Memo enclosing a Memorandum of
Understanding (MoU), wherein it was submitted that the matter has been amicably resolved
between the parties and that the grievance raised in the complaint stands redressed by the
Respondent.
4.
It is pertinent to note that this Authority has previously issued a Show Cause Notice to the
Respondent for contravention of Sections 3 and 4 of the RE(R&D) Act in relation to the concerned
project. The Respondent’s reply to the said notice has been taken on record in Case No. 96 of 2024,
which is currently pending adjudication before this Authority. In light of the ongoing proceedings
concerning identical violations, this Authority is of the considered view that no further directions
are warranted against the Respondent in the present matter.
5.
In view of the aforementioned submission made by the Complainant on 20.02.2025, the
present complaint stands disposed off as settled.
Sd/-
sd/-
SriK.SrinivasaRao,
Hon’bleMember
Sri.LaxmiNarayanaJannu,
Hon’bleMember
TG RERA
TG RERA
sd/Dr. N.Satyanarayana,IAS(Retd.),
Hon’bleChaiperson
TG RERA
Related Orders
Interim Order Complaint No.228 of 2025
Rangareddy, Telangana, 500077)Order Complaint No. 386 of 2025
Koti, Hyderabad-500027.Order Complaint No. 153 of 2024
Telangana – 500011.Order Complaint No. 152 of 2024
Telangana – 500011.Order Complaint No. 151 of 2024
Telangana – 500011.Need Complete Property Verification?
Get ownership details, EC records, survey sketch, zone checks, geo-insights & AI analysis - all in one place