Order Complaint No. 241 of 2025
Order Details
| Order Type | TG-RERA Authority |
|---|---|
| Complaint/Case Number | Complaint No. 241 of 2025 |
| Year | 2025 |
| Order Category | Regular Order |
| Order Date | 30 Dec 2025 |
| Complainant | Miyapur, Hyderabad, Telangana - 500049 |
| Respondent | Road No. 12, Banjara Hills, Hyderabad, Telangana – 500034. |
| PDF Document | Download PDF BU_311225171427205.pdf |
Full Order Text
BEFORE TELANGANA REAL ESTATE REGULATORY AUTHORITY
[Under the Real Estate (Regulation and Development) Act, 2016]
Complaint No. 241 of 2025
Dated: 30th December 2025
Quorum:
Dr. N. Satyanarayana, IAS (Retd.), Hon’ble Chairperson
Sri K. Srinivasa Rao, Hon’ble Member
Sri Laxmi Narayana Jannu, Hon’ble Member
Shri. Paluru Chandra Dheeraj
R/o. Flat No. 401, Venkat Diamond, Matrusri Nagar,
Miyapur, Hyderabad, Telangana - 500049
…Complainant
Versus
M/s. Vasavi Realtor LLP,
Rep by its Designated Partner, Yerram Vijay Kumar,
Vasavi Corporate,
H.No.8-2-703/7/1 and 8-2-703/7/1/A,
4th Floor, Vasavi Corporate Building, Amrutha Valley Apartments,
Road No. 12, Banjara Hills, Hyderabad, Telangana – 500034.
…Respondent
The present matter filed by the Complainant herein came up for hearing before this
Authority in presence of Complainant and the Respondent; upon pursuing the material on
record and on hearing arguments of both the parties and having stood over for consideration
till this day, the following order is passed:
ORDER
2.
The present Complaint has been filed by the Complainant under Section 31 of the Real
Estate (Regulation & Development) Act, 2016 (hereinafter referred to as the “Act”) read with
Rule 34(1) of the Telangana Real Estate (Regulation and Development) Rules, 2017
(hereinafter referred to as the “Rules”) seeking appropriate relief(s) against the Respondents.
A. The brief facts of the case, as stated by the Complainant, are as follows:
3.
It is submitted that the Complainant purchased a flat in the project “Vasavi Lake City”
in 2021, based on the advertisements, personal interactions with the marketing team, and the
website information of the Respondent, which highlighted the project as a well-planned and
timely development. The purchase was made with the expectation that the Respondent would
deliver the flat within the promised timeframe.
Page 1 of 20
It is stated that as per the agreed terms, the Complainant made 90% of the payment
towards the flat, believing that the project was on track. The builder, Sri Vijay Kumar Yerram,
had personally assured that the handover would take place by August 2023, and that possession
could even be expected before the committed deadline. As per the Agreement, the handover
date is August, 2023 plus 6 months of grace period.
5.
It is contended that despite these assurances, the project faced repeated and unjustified
delays and, as of February 2025, remained incomplete. The Respondent allegedly postponed
the handover dates on multiple occasions, provided vague reasons, and failed to communicate
a clear and firm timeline. Having already paid 90% of the amount, the Complainant stated that
this delay caused uncertainty and financial distress, significantly impacting plans and
investments.
6.
It is further submitted that as of January 2025, the project was only 60% to 70%
completed, with no major work carried out thereafter. Key aspects such as interior finishing,
common amenities, and supporting infrastructure remained incomplete. Despite multiple
follow-ups, the Respondent allegedly failed to provide any roadmap or completion schedule,
leaving the Complainant and other homebuyers frustrated and anxious. It is further submitted
that the lack of visible progress and absence of proper communication have further raised
doubts whether the Respondent is genuinely committed to complete the project.
7.
The Complainant alleged that the continued delay in possession constitutes a violation
of the provisions of the RE(R&D) Act, 2016, as the Respondent failed to deliver the project
within the stipulated timeline without valid justification. By collecting 90% of the payment
upfront, and failing to fulfil contractual obligations, the Respondent has allegedly breached the
statutory requirements. The Complainant stated that the delay has caused financial strain,
mental stress, and emotional distress, and therefore sought intervention of this Authority for
urgent directions, financial compensation, and strict action against the Respondent.
B. Relief(s) Sought:
8.
Accordingly, the Complainant sought the following reliefs:
i.
To direct the Respondent to complete the construction and hand over possession of the
flat at the earliest. Seeking immediate action to ensure that the remaining work is
Page 2 of 20
To direct the Respondent to pay interest on the total amount paid by the Complainant
from the promised possession date of August 2023 until the actual date of handover
along with interest at the prescribed rate under RERA for the entire delay period.
iii.
To direct the Respondent to pay compensation for the inconvenience, and financial
losses incurred as a result of the prolonged delay, and if the Respondent further delays
and doesn’t show the intent of completing the project, then to direct the Respondent to
pay amount at the current market selling price while the Complainant dropout of the
Agreement.
C. Counter filed by the Respondent:
8.
It is submitted by the Respondent that the complaint is not maintainable either in law
or on facts and is liable to be dismissed. It is submitted that the complainant has not followed
the remedies available under the Agreement for Sale for resolution of disputes before
approaching this Hon’ble Authority. Further, no prior legal notice was issued before filing this
complaint, which itself renders the application defective and not maintainable.
9.
It is submitted that the project “Lake City-West” was developed lawfully after obtaining
rights from the landowners under registered documents, covering 43,298.17 sq. yds. While
requisite land conversion permissions and building permissions for construction of multistoried apartments were obtained on 07.02.2020. The project consists of seven towers (cellars
+ ground + 14 upper floors), and a clubhouse (stilt + five upper floors). The project was duly
registered with this Authority vide Registration No. P02500001819 dated 20.03.2020.
10.
It is further submitted that the Complainant was allotted an apartment in the project
vide booking dated 19.03.2021, and was allotted an apartment No. W.20501 on the 5th Floor
of Tower 2, admeasuring 1915 sq. ft., along with parking, for a total consideration of Rs.
84,36,800/-. The Agreement of Sale sets out the carpet area, balcony/veranda area, common
area, and undivided share of land. The Complainant has paid Rs. 21,00,000/- towards the sale
consideration, while the balance amount remains payable in accordance with the agreed
payment schedule.
Page 3 of 20
It is submitted that as per Clause 7 of the Agreement, the Respondent was obligated to
hand over possession of the flat and common areas by 31.08.2023, subject to extension in the
event of force majeure. The Agreement itself clearly records that timely delivery is the essence
of the contract but also recognises that the period of completion shall stand extended to the
extent of delay caused by force majeure conditions, during which period the allottee is not
entitled to claim compensation.
12.
It is submitted that the complainants have not come before this Hon’ble Authority with
clean facts but with an ulterior motive to make unlawful gain and that there has been material
suppression of facts of the case with regard to the claim and the relief sought therein.
13.
It is further stated that COVID-19 is a force majeure event duly recognized under law,
and hence the timelines stood extended. The Respondent contended that the COVID-19
pandemic, subsequent lockdowns, and migration of labourers had severely impacted
construction work. The Respondent further relies on the orders of the Hon’ble Supreme Court
in Suo Motu Writ Petition No. 3 of 2020, whereby the period from 15.03.2020 till 28.02.2022
was excluded for the purposes of computation of limitation across various statutes. It is
contended that the extension of time for completion of the project was not only factually
justified but also recognised in law.
14.
In addition to COVID-19, the Respondent submits that unforeseen site conditions such
as rocky terrain requiring manual excavation further delayed the project. Owing to restrictions
on blasting due to the residential nature of the surrounding locality, excavation could only be
done manually, which compounded the delay. These challenges were communicated to all
allottees through regular updates and meetings.
15.
The Respondent also submits that certain third-party disputes adversely impacted the
project timelines. These include cases such as RERA Case No. 190/2020, W.P. Nos.
2694/2021, 13898/2022, 33433/2023, W.A. No. 584/2023, SLP Nos. 9694–9695/2023, and
W.P. No. 26301/2024, some of which are still pending. While most have been resolved, their
pendency at various points of time hindered the smooth progress of the project.
16.
It is contended that the project has been executed strictly in accordance with approved
plans and specifications, and any clerical or typographical errors in the Agreement of Sale
Page 4 of 20
With regard to the claims for interest and compensation, the Respondent submits that
in view of the force majeure conditions, no such relief is available to the Complainant under
law. Section 6 of the Act specifically contemplates force majeure events such as natural
calamities and other circumstances beyond the control of the promoter. The Respondent
submits that the COVID-19 pandemic, together with the extraordinary circumstances outlined
above, clearly falls within the scope of force majeure.
D. Rejoinder filed by the Complainant:
18.
At the very outset, it is submitted that all statements and averments claimed in the
counter filed by the Respondent are denied in toto, except those which are matters of record or
specifically admitted. The averments made by the Respondent are devoid of merit and far from
truth. The complaint already filed may be read as part and parcel of this rejoinder, and the
Complainant reserves the right to file any additional pleadings if necessary.
19.
It is submitted that the decision to purchase Flat No. 02-501, Tower-2, West Wing,
Vasavi Lake City, was taken only because of the Respondent’s categorical assurances of timely
possession, with confidence further built by repeated promises that delivery would be well
within the committed time frame.
20.
It is further submitted that over time, this trust was broken as the Respondent displayed
irresponsible conduct, repeatedly postponing possession, offering unreasonable excuses, and
giving false promises. Despite the Complainant’s repeated follow-ups, meetings were rarely
scheduled, and when held, they only resulted in further false assurances. After exhausting all
efforts, the Complainant had no option but to seek justice before this Hon’ble Authority.
21.
It is submitted that the complaint has been filed under Section 31 of the RE(R&D) Act,
2016, and the Agreement of Sale dated 15.06.2021 clearly stipulates the possession date as
Page 5 of 20
It is further submitted that the Dispute Resolution clause in the Agreement only required
initial attempts at mutual discussion, which were duly made by the Complainant but
consistently evaded by the Respondent under excuses such as unavailability of management,
hospitalization, or shifting responsibility between teams. Even when meetings were reluctantly
scheduled, false promises were made. Thus, the Complainant has fully complied with the
Agreement before approaching this Authority.
23.
It is submitted that there is no requirement under RERA to issue a legal notice before
filing a complaint under Section 31, and therefore, the Respondent’s objection on this ground
is frivolous and intended only to delay the proceedings.
24.
It is further submitted that the Respondent’s rights to development and registration are
not disputed as a matter of record. However, having registered the project with RERA, the
Respondent is bound by statutory duties, including timely delivery as per the Agreement.
Instead of adhering to these obligations, the Respondent has indulged in excuses, displaying
complete disregard for commitments and process of law.
25.
It is submitted that the Agreement dated 15.06.2021 expressly records possession to be
delivered by 31.08.2023. The Complainant has duly performed obligations, having paid 90%
of the sale consideration by June 2023, and stands entitled to remedies under Sections 18(1)
and 19(4) of the Act.
26.
It is further submitted that extension of the project registration up to 2026 does not
authorize the Respondent to default on delivery. Section 19 of the Act entitles allottees to
information, progress reports, and timely delivery, none of which have been complied with.
The Respondent continued to make false assurances even beyond August 2023 and now
casually proposes delivery by 2026, which cannot be accepted unless accompanied by financial
accountability.
27.
It is submitted that possession is a condition precedent for the balance 10% payment.
Having already paid 90% of the sale value, the Complainant is entitled to withhold further
payments until lawful possession is given. It is further submitted that Clause 7.1 of the
Agreement stipulates possession by August 2023 with six months’ grace only in case of force
Page 6 of 20
It is submitted that reliance on Clause 7.2 is misplaced, as the precondition of obtaining
Occupancy Certificate has not been met. It is further submitted that defamatory allegations
made against the Complainant are baseless, unsubstantiated, and only intended to divert from
the core issue of failure to deliver possession. The Respondent’s shifting of timelines from
August 2023 to February 2024, then October 2024, and now February 2026, proves deliberate
procrastination.
29.
It is submitted that the Agreement was executed well after the pandemic disruptions,
and by 2021 economic activity had revived. The prolonged delay from 2023 to 2025 cannot be
attributed to COVID-19, but only to the Respondent’s mismanagement. Section 19(4) of the
Act entitles the Complainant to refund, interest, and compensation in case of failure to deliver
possession in terms of the Agreement. It is further submitted that judicial precedents cited by
the Respondent relating to limitation are wholly irrelevant to the present case, where the issue
is the builder’s contractual and statutory failure under RERA.
30.
It is submitted that repeated reliance on COVID-19 as force majeure is a mere excuse
to conceal mismanagement, since the Agreement itself was entered into in June 2021, after the
pandemic period. No evidence of timely notice or mitigation has been provided. It is further
stated that vague references to “various additional factors” are unsupported and cannot justify
the delay. If indeed 90% of construction is complete, possession should have been offered; the
continued delay is deliberate.
31.
It is submitted that the attempt to describe the binding Agreement as a “clerical or
typographical error” is dishonest and alarming. The date of 31.08.2023 was consistently
recorded and never corrected. Such conduct amounts to misrepresentation. It is further
submitted that derogatory allegations against the Complainant are diversionary. Documentary
evidence such as the Agreement, payment receipts, MOMs of meetings, and correspondence
have already been produced, establishing delay and false promises.
32.
It is submitted that pending litigations with third parties cannot be used as a blanket
excuse to penalize buyers. It was the duty of the Respondent to ensure clear title and proactively
disclose any disputes. Instead, they are now raised belatedly to justify the delay.
Page 7 of 20
It is submitted that the Complainant’s claim for interest is squarely within Section 18
of the Act. The extension obtained belatedly in January 2025, citing force majeure of 2020, is
irrelevant and unsustainable. It is also stated that the hardship faced by the Complainant, having
paid 90% of the sale price, yet continuing to live in a rented flat for over two years beyond the
promised date, has caused severe financial and emotional distress.
34.
It is submitted that extension of project till 2026 does not absolve liability. The
Complainant never consented to such extension. The Respondent’s reliance on manual
excavation or rocky terrain is untenable, as such risks were foreseeable and within their
responsibility.
35.
In view of the above, it is humbly prayed that the contentions of the Respondent be
rejected, the complaint be allowed, and to pass suitable orders with regard to compensation
considering the facts and circumstances of the case.
E. Points for Consideration
36.
Upon a careful perusal of the record and the submissions advanced by both parties, oral
as well as written, this Authority is of the view that the following issues arise for determination
in the present complaint:
1. Whether the present complaint is maintainable before this Authority?
2. Whether the Complainants are entitled to the reliefs as prayed for?
F. Observations of the Authority:
Point 1:
37.
The Respondent has raised an objection as to the maintainability of the present
complaint on the ground that the Complainants failed to first resort to the contractual dispute
resolution mechanism envisaged in the Agreement of Sale, namely an amicable settlement by
mutual discussion, prior to approaching this Authority. The Authority finds this objection
untenable for the following reasons:
The relevant Dispute Resolution clause in the Agreement of Sale is reproduced below for ready
reference:
Page 8 of 20
It is clear from the above that the clause only requires the parties to attempt an amicable
settlement by mutual discussion. Such a clause is at best directory and cannot oust or restrict
the statutory jurisdiction of this Authority.
39.
Section 79 of the RE(R&D) Act expressly bars the jurisdiction of Civil Courts in respect
of any matter which this Authority, the Adjudicating Officer, or the Appellate Tribunal is
empowered to determine. Likewise, Section 88 clarifies that the provisions of the RE(R&D)
Act are in addition to, and not in derogation of, other laws. Thus, the intention of the legislature
is that remedies under this beneficial legislation must remain open to allottees, irrespective of
any private clause for amicable settlement.
40.
Even in cases where agreements contained arbitration clauses (which is not the case
here), the Hon’ble Supreme Court and the Hon’ble NCDRC have consistently held that such
clauses cannot circumscribe the jurisdiction of consumer fora or statutory authorities
constituted under special enactments.
41.
In National Seeds Corporation Ltd. v. M. Madhusudhan Reddy (2012) 2 SCC 506, the
Supreme Court held that remedies under special statutes are in addition to, and not in derogation
of, other remedies. For ready reference, the relevant extract is reproduced below:
*“49. Support to the above view is also lent by Section 79 of the recently enacted Real
Estate (Regulation and Development) Act, 2016 (for short "the Real Estate Act").
Section 79 of the said Act reads as follows:‘79. Bar of jurisdiction - No civil court shall have jurisdiction to entertain any suit or
proceeding in respect of any matter which the Authority or the adjudicating officer or
the Appellate Tribunal is empowered by or under this Act to determine and no
injunction shall be granted by any court or other authority in respect of any action
Page 9 of 20
Similarly, in Aftab Singh &Ors. v. Emaar MGF Land Ltd. &Ors. (Consumer Case No.
701 of 2015, decided on 13.07.2017), it was held that arbitration clauses in builder-buyer
agreements cannot oust the jurisdiction of consumer fora. The said view was later upheld by
the Hon’ble Supreme Court in Civil Appeal Nos. 23512–23513 of 2017. The relevant para
reads:
“25. This Court in the series of judgments as noticed above considered the provisions
of Consumer Protection Act, L986 os well as Arbitration Act, 1996 and laid down that
complaint under Consumer Protection Act being a special remedy, despite there being
an arbitration agreement the proceedings before Consumer Forum have to go on and
no error committed by Consumer Forum on rejecting the application. There is reason
for not interjecting proceedings under Consumer Protection Act on the strength an
arbitration agreement by Act, 1996. The remedy under Consumer Protection Act is a
remedy provided to a consumer when there is a defect in any goods or services. The
complaint means any allegation in writing made by a complainant has also been
explained in Section 2(c) of the Act. The remedy under the Consumer Protection Act is
confined to complaint by consumer as defined under the Act for defect or deficiencies
Page 10 of 20
In the present matter, there is only a clause requiring amicable discussion before
invoking remedies. Such a clause is directory at best, and cannot override or defeat the statutory
right of the Complainant to approach this Authority under the RE(R&D) Act, 2016.
Accordingly, this Authority has no hesitation in holding that the Complainant is well within its
rights to approach this forum without being first compelled to pursue an amicable settlement
under the Agreement. The objection of the Respondent as to maintainability is therefore
rejected.
Point No. 2:
44.
The Complainants have sought relief on the ground that there has been an inordinate
delay in handing over possession of the subject flat.
45.
It is the case of the Complainants where Agreement of Sale was executed on 15.06.2021
between the parties, clearly stipulated that possession of the subject flat would be handed over
by 31.08.2023, with a grace period of six months, ending on 28.02.2024. The Respondent has
failed to hand over possession even as on date. Further, although the project was registered
with TG RERA up to February 2025 and later extended until 07.02.2026, the project remains
incomplete.
46.
The Complainants submit that the Respondent has repeatedly given false assurances of
completion, while allottees continue to suffer. The Respondent, conversely, attributes the delay
to the Covid-19 pandemic, claiming force majeure, citing the nationwide lockdown beginning
March 2020, the impact on migrant labour, and consequential delays. The Respondent further
cites rocky terrain at the site, third-party disputes, and typographical errors in the possession
date as additional justifications.
(i)
Whether the Covid-19 pandemic can be taken as a valid shield by the Respondent
in the present case?
47.
This Authority finds no merit in such a contention. The Agreement of Sale was executed
on 15.06.2021, well after the onset and subsiding of the Covid-19 pandemic. Having
consciously undertaken such commitment, the Respondent cannot now, with retrospective
Page 11 of 20
It is a settled principle that once a promoter has chosen to register a project and enter
into binding contractual commitments with allottees, he does so with full knowledge of the
risks, constraints, and challenges of the market. At the time of entering into the Agreement of
Sale with the present Complainant, the Respondent was already aware of the Covid-related
disruptions, as well as the Government notifications granting moratoriums for project
completion timelines. Despite this knowledge, the Respondent chose to provide a specific
assurance of delivery by 31.08.2023 and six months of grace period.
This Authority aligns with the observations of the Hon’ble Bombay High Court in
49.
Neelkamal Realtors Suburban Pvt. Ltd. &Anr. vs. Union of India &Ors. [2017 SCC OnLine
Bom 9302], wherein at para 119 it was categorically observed:
"While the proposal is submitted, the Promoter is supposed to be conscious of the
consequences of getting the project registered under RERA. Having sufficient
experience in the open market, the Promoter is expected to have a fair assessment of
the time required for completing the project…".
50.
The above dictum fortifies the principle that the promoter, being structurally at an
advantageous position with respect to project information and market realities, is under a
statutory duty to provide realistic timelines. The framework of the Real Estate (Regulation and
Development) Act, 2016 reinforces this obligation by mandating timely completion and
possession within the period stipulated in the Agreement of Sale.
51.
Therefore, the plea of Covid-19 as a force majeure defence in the present case is wholly
untenable. The Respondent, having executed the Agreement of Sale in the year 2021 with
specific possession timelines, cannot now seek to retrospectively attribute delays to the
pandemic. Accordingly, this Authority holds that the reliance on Covid-19 as a shield stands
rejected.
ii)
52.
Extension of Registration
The Respondent has further contended that, since extensions have been granted by this
Authority, the project timeline now stands extended up to February 2026, and therefore
Page 12 of 20
At the outset, it must be clarified that under the scheme of the RE(R&D) Act, 2016.
“An Act to establish the Real Estate Regulatory Authority for regulation and
promotion of the real estate sector and to ensure sale of plot, apartment or
building, as the case may be, or sale of real estate project, in an efficient and
transparent manner and to protect the interest of consumers in the real estate
sector and to establish an adjudicating mechanism for speedy dispute redressal
and also to establish the Appellate Tribunal to hear appeals from the decisions,
directions or orders of the Real Estate Regulatory Authority and the
adjudicating officer and for matters connected therewith or incidental thereto.”
54.
The paramount objective is twofold: protection of consumer interest, and ensuring
completion of projects in an efficient manner. Denial of extension during the Covid-19
disruption would have resulted in projects being stalled, to the grave prejudice of allottees. It
was in this context that this Authority, balancing the equities, granted extensions in line with
the moratoriums issued by Telangana RERA:
1. 15.03.2020 to 14.09.2020 (Circular No.14 dated 13.05.2020),
2. 15.09.2020 to 15.03.2021 (Order No.15 dated 29.09.2020),
3. 15.03.2021 to 14.09.2021 (Order No.16 dated 01.06.2021).
55.
Accordingly, an aggregate 18 months’ extension was applied across projects to
safeguard larger consumer interest. However, it is equally well settled that such regulatory
extensions cannot dilute the contractual rights of individual allottees under their respective
Agreements of Sale, nor can they displace the statutory rights flowing from Section 18 of the
RE(R&D) Act, 2016.
56.
In the present matter, it is evident that the Respondent has unilaterally revised
possession timelines first to to February 2026 due to the extension taken without consultation
or consent of the Complainants. Such unilateral revisions are impermissible. The Hon’ble
Bombay High Court in Neelkamal Realtors Suburban Pvt. Ltd. vs. Union of India &Ors.
Page 13 of 20
The above dicta makes it abundantly clear that any extension granted by the Authority,
or revised timelines uploaded on the TG RERA project registration portal, do not ipso facto
alter or bind the allottees’ contractual rights. The agreed date of possession remains as
stipulated in the Agreement for Sale, and unilateral extensions by the promoter cannot be
foisted upon allottees to their detriment.
58.
Accordingly, this Authority holds that the revised possession dates mentioned by the
Respondent, whether while seeking extensions before the Authority or as updated on the
registration portal, cannot be treated as binding on the Complainants.
(iii)Relief under Section 18 of the RE(R&D) Act:
59.
It is observed as per the records furnished before this Authority that the entire sale
consideration is for an amount of Rs. Rs.84,36,800/- (Rupees Eighty Four Lakh Thirty Six
Thousand And Eight Hundred Only.) It is observed as per the said Agreement of Sale only an
amount of Rs. 21,00,000/- (Rupees Twenty One Lakh Only) has been paid by the Complainant
towards the sale consideration. However, it is duly noted as per the payment receipts placed
before this Authority that the Complainant has paid a sum of Rs. Rs.79,72,776/- (Rupees
Seventy Nine Lakh Seventy Two Thousand Seven Hundred And Seventy Six Only) which is
over 90% of the total sale consideration amount. It is also observed that the Agreement of Sale
unequivocally stipulates that possession was to be delivered by 31.08.2023, with a grace period
of six months, i.e., up to 28.02.2024. Admittedly, possession has not been delivered within the
stipulated period.
60.
The Respondent’s contention that 90% work is complete and that the Complainants
have paid only a portion of the consideration is wholly unsustainable. The Complainants have
already paid over 90% of the agreed consideration as per their averments. Despite receiving
Page 14 of 20
The Respondent further seeks to shift the burden on the complainant by contending that
the balance amount is unpaid. This plea is untenable. The law does not permit a defaulter to
take advantage of its own breach. As held by the Hon’ble Supreme Court in Kusheshwar
Prasad Singh v. State of Bihar [Civil Appeal No. 7357 of 2000]:
“It is settled principle of law that a man cannot be permitted to take undue and unfair
advantage of his own wrong to gain favourable interpretation of law. It is sound
principle that he, who prevents a thing from being done shall not avail himself of the
non-performance he has occasioned. To put it differently, "a wrongdoer ought not to
be permitted to make a profit out of his own wrong.”
62.
In this context, it is pertinent to note that the Agreement of Sale linked the payment
schedule to the progress of construction. While the allottees are indeed bound to adhere to the
agreed payment plan, such obligation arises only when the promoter simultaneously fulfils its
reciprocal obligation of executing construction in line with the assured progress. In the absence
of such progress, the Respondent cannot insist upon further payments as a condition to claim
relief.
63.
Section 18 of the RE(R&D) Act is categorical and unconditional. It does not make the
grant of interest contingent upon the quantum of sale consideration paid, nor does it provide
any defence to a defaulting promoter. Once delay in handing over possession is established, an
allottee who elects to remain in the project is entitled to interest for every month of delay,
irrespective of whether part or whole of the consideration has been paid, provided that the
payments already made are in accordance with the Agreement of sale. The Respondent’s plea
that only “partial sale consideration” has been paid and hence interest cannot be granted is
therefore vague, misconceived, and contrary to the express mandate of the statute. Now,
Section 18 of the RE(R&D) Act is categorical:
“(1) If the promoter fails to complete or is unable to give possession of an apartment,
plot or building,—
Page 15 of 20
This statutory right of allottee is unqualified and absolute. Attention is drawn to the
decision of the Hon'ble Supreme Court of India in Civil Appeal Nos. 3581-359 of 2022, Civil
Appeal Diary No. 9796/2019, M/s Imperia Structures Limited vs. Anil Patni & Others,
wherein it was held:
"In terms of Section 18 of the RERA Act, if a promoter fails to complete or is unable to
give possession of an apartment by the date specified in the agreement, the promoter
would be liable, on demand, to return the amount received in respect of that apartment
if the allottee wishes to withdraw from the project. Such a right of the allottee is 'without
prejudice to any other remedy available to him'. This right is unqualified, and if availed,
the deposited money must be refunded with interest as prescribed. The proviso to
Section 18(1) contemplates that if the allottee does not intend to withdraw from the
project, they are entitled to interest for every month of delay until possession is handed
over. The allottee may proceed under Section 18(1) or the proviso thereto."
Page 16 of 20
Similarly, in Civil Appeal Nos. 6745-6749 of 2021, M/s Newtech Promoters and
Developers Private Limited vs. State of UP & Others, the Hon’ble Supreme Court
observed:
"Section 18(1) of the Act spells out the consequences if the promoter fails to
complete or is unable to give possession of an 9 of 10 apartment, plot, or
building in terms of the agreement for sale. The allottee/home buyer holds an
unqualified right to seek a refund of the amount with interest as prescribed."
66.
Further, as earlier observed, the Hon’ble Bombay High Court in Neelkamal Realtors
Suburban Pvt. Ltd. v. Union of India [(2017) SCC Online Bom 9302] clarified that RERA
registration or its extension cannot rewrite the contract between parties. The date assured under
the Agreement of Sale, executed with the allottee’s consent, shall prevail. Thus, the Respondent
is bound by Section 11(4)(a) of the RE(R&D) Act, which mandates adherence to the terms of
the Agreement of Sale.
67.
At the same time, if the Complainant has indeed defaulted in adhering to the payment
schedule, the Respondent is not without remedy. Sections 19(6) and 19(7) of the Act confer
upon the promoter a right to claim interest for delayed payments, as per Rule 15 of the
Telangana RE(R&D) Rules, 2017. Nevertheless, such entitlement shall be subject to the
Respondent producing cogent and substantive documents demonstrating both the stage-wise
progress of construction and the corresponding default, and not merely based on unilateral
assertions.
68.
In the present case, this Authority finds the Respondent in clear breach of both statutory
and contractual obligations. The Complainant is therefore entitled to interest at the prescribed
rate for the entire period of delay, i.e., from 01.03.2024 until the actual date of handing over
possession. As regards claims of compensation, this Authority notes that jurisdiction for
adjudicating compensation lies with the Adjudicating Officer under Section 71 of RE(R&D)
Act with Form ‘N’. The Complainant is at liberty to pursue such remedy separately.
69.
Accordingly, while the Complainant is entitled to relief under Section 18 of the
RE(R&D) Act, this entitlement is subject to the reciprocal statutory duty of the Complainant
to discharge any outstanding amounts under the payment plan, if not already paid. Compliance
on both sides is essential to ensure balance of obligations and timely delivery.
Page 17 of 20
This Authority cannot remain oblivious to the larger pattern of violations. It is noted
with grave concern that more than fifty complaints have already been received against this very
Respondent in respect of the subject project. Such repeated defaults and false assurances strike
at the very root of the confidence that homebuyers are entitled to repose under the protective
framework of the RE(R&D) Act, 2016.
71.
The Statement of Objects and Reasons of the RE(R&D) Act explicitly emphasizes
“greater accountability towards consumers and to inject transparency, efficiency, and
discipline in the real estate sector”. The conduct of the Respondent herein is in gross
derogation of that legislative mandate. If such violations are permitted to persist, the very soul
of the Act would stand diluted and the protection promised to allottees rendered illusory.
72.
Accordingly, this Authority hereby sternly warns the Respondent promoter that any
further default, non-compliance, or failure to deliver possession within the assured statutory
timelines or any fresh grievances brought to notice by allottees shall invite invocation of
Section 63 of the RE(R&D) Act, 2016.
73.
This Authority shall not hesitate to take the strictest view in future, for the RE(R&D)
Act, 2016 was enacted not as a mere regulatory framework but as a beneficial legislation to
protect innocent homebuyers from the very malaise exemplified by the conduct of this
Respondent.
74.
The Respondent is hereby directed to complete the project and hand over possession to
the Complainants within the stipulated period. It is further clarified that if the Complainants
have defaulted in making payments as per the agreed schedule, the Respondent shall be entitled
under Section 19(6) of the RE(R&D) Act, 2016 to claim interest on such delayed payments,
provided that it substantiates such claim with credible documentary evidence of both
construction progress and corresponding default.
75.
In the event the Complainants have defaulted in making payments as per the agreed
schedule, the Respondent shall be entitled, under Section 19(6) of the Real Estate (Regulation
and Development) Act, 2016, to claim interest on such delayed payments in accordance with
Rule 15 of the Telangana Real Estate (Regulation and Development) Rules, 2017.
Nevertheless, such entitlement shall be subject to the Respondent producing cogent and
substantive documents demonstrating both the stage-wise progress of construction and the
corresponding default, and not merely based on unilateral assertions.
Page 18 of 20
The Complainants are, in turn, directed to discharge any balance amounts due under
the agreed payment schedule, if not already paid. Mutual compliance is essential to ensure
timely completion and delivery of the project.
G. Directions of the Authority:
77.
In view of the findings and observations recorded hereinabove, this Authority proceeds
to issue the following directions:
a) The preliminary objection raised by the Respondent regarding the maintainability of
the complaint on account of the Dispute Resolution Clause in the Agreement of Sale
stands rejected. The complaint is maintainable before this Authority.
b) The Respondent’s reliance on the Covid-19 pandemic as a ground of force majeure is
held untenable, since the Agreement of Sale was executed after the subsiding of the
pandemic and with full knowledge of the prevailing circumstances.
c) The extension of registration taken by this Respondent cannot dilute the contractual
rights of the Complainant under the Agreement of Sale. The date of possession as
stipulated in the Agreement shall prevail.
d) The Respondent is held liable for failure to hand over possession of the subject flat by
the agreed date i.e., 28.02.2024 (inclusive of grace period).
e) The Complainants are entitled to interest at the rate of 10.7% per annum (being SBI
MCLR + 2% as per Rule 15 of the TG RE(R&D) Rules, 2017), computed on the
amounts actually paid by the Complainants, with effect from 01.03.2024 until actual
handing over of lawful possession. The exact computation shall be subject to
verification of such payments by the Respondent at the stage of effecting payment The
Respondent shall pay the arrears accrued up to the date of this Order within sixty (60)
days, and shall thereafter continue to pay the accruing interest on a monthly basis, on
or before the 10th day of each succeeding month, until possession is delivered.
f) Insofar as compensation is concerned, the Complainant is at liberty to pursue
appropriate proceedings before the Learned Adjudicating Officer under “Form N”.
g) The Respondent is hereby directed to complete the project forthwith and hand over
possession to the Complainants within the statutory timelines.
h) The Complainants are directed to pay the balance consideration strictly in accordance
with the agreed payment schedule. In the event of any default in adhering to such
schedule, the Respondent shall be at liberty to claim interest on the delayed amounts,
Page 19 of 20
78.
Having regard to the repeated defaults and the large number of complaints already
pending against this Respondent in the same project, this Authority sternly warns the
Respondent that any further delay, non-compliance, or grievance brought to notice by allottees
shall invite section 63 of the RE(R&D) Act.
79.
The Complaint is accordingly allowed in part, in terms of the above directions.
80.
Failure to comply with above said directions by the Respondent shall attract penalty in
accordance with Section 63 of the RE(R&D) Act, 2016.
81.
As a result, the complaint is disposed of accordingly. No order as to costs.
Sd/-
Sd/-
Sd/-
Sri K. Srinivasa Rao,
Sri Laxmi Narayana Jannu,
Dr. N. Satyanarayana, IAS (Retd.),
Hon’ble Member,
Hon’ble Member,
Hon’ble Chairperson,
TG RERA
TG RERA
TG RERA
Page 20 of 20
Related Orders
Interim Order Complaint No.228 of 2025
Rangareddy, Telangana, 500077)Order Complaint No. 386 of 2025
Koti, Hyderabad-500027.Order Complaint No. 153 of 2024
Telangana – 500011.Order Complaint No. 152 of 2024
Telangana – 500011.Order Complaint No. 151 of 2024
Telangana – 500011.Need Complete Property Verification?
Get ownership details, EC records, survey sketch, zone checks, geo-insights & AI analysis - all in one place