TG-RERA Authority

Order Complaint No. 201 of 2025

30 Dec 2025
TG-RERA Authority
21 Pages

Order Details

Order Type TG-RERA Authority
Complaint/Case Number Complaint No. 201 of 2025
Year 2025
Order Category Regular Order
Order Date 30 Dec 2025
Complainant Kamalapuri Colony, Hyderabad – 5000073)
Respondent Road No. 12, Banjara Hills, Hyderabad, Telangana – 500034)
PDF Document Download PDF BU_010126140504859.pdf

Full Order Text

BEFORE TELANGANA REAL ESTATE REGULATORY AUTHORITY
[Under the Real Estate (Regulation and Development) Act, 2016]
Complaint No. 201/2025/TG RERA
Dated: 30th December 2025
Quorum:

Dr. N. Satyanarayana, IAS (Retd.), Hon’ble Chairperson
Sri K. Srinivasa Rao, Hon’ble Member
Sri Laxmi Narayana Jannu, Hon’ble Member

1. Mr. Vundela Vinod Kumar Reddy
2. Mrs. Venkata Kalpana Polu
(D.No. 8-3-833/97, Phase 3,
Kamalapuri Colony, Hyderabad – 5000073)
…Complainant
Versus
M/s. Vasavi Realtor LLP,
(Rep by its Designated Partner, Vijay Kumar Yerram,
Vasavi Corporate,
H.No.8-2-703/7/1 and 8-2-703/7/1/A,
4th Floor, Vasavi Corporate Building, Amrutha Valley Apartments,
Road No. 12, Banjara Hills, Hyderabad, Telangana – 500034)

…Respondent
The present matter file by the Complainant herein came up for hearing on
11.07.2025 before this Authority in presence of Complainant in person and Respondents
Counsels Sri D Madhav Rao and M.K.Joy Raj; upon pursuing the material on record and on
hearing arguments of the both the parties and having stood over for consideration till this
day, the following order is passed:
ORDER
2.

The present Complaint has been filed by the Complainant under Section 31 of the

Real Estate (Regulation & Development) Act, 2016 (hereinafter referred to as the “RE(R&D)
Act”) read with Rule 34(1) of the Telangana Real Estate (Regulation and Development)
Rules, 2017 (hereinafter referred to as the “TG RE(R&D) Rules”) seeking appropriate
relief(s) against the Respondents.
A. The brief facts of the case, as stated by the Complainant, are as follows:
3.

It is submitted that the Complainants purchased a flat bearing No. E 04 13 08, 13th

Floor in Tower No. 4, admeasuring 1190 Sft of saleable area in the project “Vasavi Lake
1 of 20


It is stated that as per the agreed terms, the Complainant made 80% of the payment

towards the flat, believing that the project was on track. The builder, Sri Vijay Kumar Yerram,
had personally assured that the handover would take place by August 2023, and that
possession could even be expected before the committed deadline.
5.

It is contended that despite these assurances, the project faced repeated and unjustified

delays and, as of February 2025, remained incomplete. The Respondent allegedly postponed
the handover dates on multiple occasions, provided vague reasons, and failed to communicate
a clear and firm timeline. Having already paid the maximum amount, the Complainant stated
that this delay caused uncertainty and financial distress, significantly impacting plans and
investments.
6.

It is further submitted that as of February 2025, the project was not yet completed,

with no major work carried out thereafter. Key aspects such as interior finishing, common
amenities, and supporting infrastructure remained incomplete. Despite multiple follow-ups,
the Respondent allegedly failed to provide any roadmap or completion schedule, leaving the
Complainant and other homebuyers frustrated and anxious.
7.

The Complainant alleged that the continued delay in possession constitutes a violation

of the provisions of the RE(R&D) Act, 2016, as the Respondent failed to deliver the project
within the stipulated timeline without valid justification. By collecting 80% of the payment,
way long back in March 2024, and failing to fulfil contractual obligations, the Respondent
has allegedly breached the statutory requirements. The Complainant stated that the delay has
caused financial strain, mental stress, and emotional distress, and therefore sought
intervention of this Authority for urgent directions, financial compensation, and strict action
against the Respondent.
B. Relief(s) Sought:
8.

Accordingly, the Complainant sought the following reliefs:

2 of 20


To direct the Respondent to complete the construction and hand over possession of
the flat at the earliest. Seeking immediate action to ensure that the remaining work is
completed within a fixed and enforceable timeframe, failing which strict penalties
should be imposed on the Respondent.

ii.

To direct the Respondent to pay interest on the total amount paid by the Complainant
from the promised possession date of August 2023 until the actual date of handover,
at the rate prescribed under Section 18 of the Act, 2016.

iii.

To direct the Respondent to pay compensation for the undue stress, inconvenience,
and financial losses incurred as a result of the prolonged delay.

C. Counter filed by the Respondent:
9.

It is submitted by the Respondent that the complaint is not maintainable either in law

or on facts and is liable to be dismissed. It is submitted that the complainant has not followed
the remedies available under the Agreement for Sale for resolution of disputes before
approaching this Hon’ble Authority. Further, no prior legal notice was issued before filing
this complaint, which itself renders the application defective and not maintainable.
10.

It is submitted that the project “Lake City-East” was developed lawfully after

obtaining rights from the landowners under registered documents, covering 34,704.37 sq.
yds. While requisite land conversion permissions and building permissions for construction
of multi-storied apartments were obtained on 07.02.2020. The project consists of six towers
(4 cellars + ground + 14 upper floors), Tower No. 4, 5, and 6 (3 Cellars + ground + 14 upper
floors) and a clubhouse (stilt + ground + five upper floors). The project was duly registered
with this Authority vide Registration No. P02500001821 dated 20.03.2020.
11.

It is further submitted that the Complainant was allotted an apartment in the project

vide booking dated 24.04.2022, and was allotted an apartment No. E.041308 on the 13th
Floor of Tower 4, admeasuring 1190 sq. ft., along with car parking, for a total consideration
of Rs.78,32,700/-. The Agreement of Sale sets out the carpet area, balcony/veranda area,
common area, and undivided share of land. The Complainant has paid Rs. 16,44,867/towards the sale consideration, while the balance amount remains payable in accordance with
the agreed payment schedule.

3 of 20


It is submitted that as per Clause 7 of the Agreement, the Respondent was obligated to

hand over possession of the flat and common areas by 31.08.2023, subject to extension in the
event of force majeure. The Agreement itself clearly records that timely delivery is the
essence of the contract but also recognises that the period of completion shall stand extended
to the extent of delay caused by force majeure conditions, during which period the allottee is
not entitled to claim compensation.
12.

It is submitted that the complainants have not come before this Hon’ble Authority

with clean facts but with an ulterior motive to make unlawful gain and that there has been
material suppression of facts of the case with regard to the claim and the relief sought therein.
13.

It is further stated that COVID-19 is a force majeure event duly recognized under law,

and hence the timelines stood extended. The Respondent contended that the COVID-19
pandemic, subsequent lockdowns, and migration of labourers had severely impacted
construction work. The Respondent further relies on the orders of the Hon’ble Supreme Court
in Suo Motu Writ Petition No. 3 of 2020, whereby the period from 15.03.2020 till 28.02.2022
was excluded for the purposes of computation of limitation across various statutes. It is
contended that the extension of time for completion of the project was not only factually
justified but also recognised in law.
14.

In addition to COVID-19, the Respondent submits that unforeseen site conditions

such as rocky terrain requiring manual excavation further delayed the project. Owing to
restrictions on blasting due to the residential nature of the surrounding locality, excavation
could only be done manually, which compounded the delay. These challenges were
communicated to all allottees through regular updates and meetings.
15.

The Respondent also submits that certain third-party disputes adversely impacted the

project timelines. These include cases such as RERA Case No. 190/2020, W.P. Nos.
2694/2021, 13898/2022, 33433/2023, W.A. No. 584/2023, SLP Nos. 9694–9695/2023, and
W.P. No. 26301/2024, some of which are still pending. While most have been resolved, their
pendency at various points of time hindered the smooth progress of the project.
16.

It is contended that the project has been executed strictly in accordance with approved

plans and specifications, and any clerical or typographical errors in the Agreement of Sale
cannot be construed to create liability. It is the case of the Respondent that more than 90% of
4 of 20


With regard to the claims for interest and compensation, the Respondent submits that

in view of the force majeure conditions, no such relief is available to the Complainant under
law. Section 6 of the Act specifically contemplates force majeure events such as natural
calamities and other circumstances beyond the control of the promoter. The Respondent
submits that the COVID-19 pandemic, together with the extraordinary circumstances outlined
above, clearly falls within the scope of force majeure.
D. Rejoinder filed by the Complainant:
18.

It is submitted that the objection regarding maintainability is baseless, vague, and

legally untenable. The present complaint has been filed strictly under the provisions of the
RE(R&D) Act, 2016, seeking redressal for the inordinate delay in handing over possession of
the flat booked under the registered project bearing RERA No. P02500001821. It is further
submitted that the Agreement of Sale dated 08.09.2021 clearly stipulates the committed date
of possession as 31.08.2023. However, as of the date of filing this complaint on 07.03.2025,
possession has not been granted, and the project is only approximately 85% complete.
Therefore, the application is legally maintainable before this Hon’ble Authority, and the
preliminary objection deserves to be rejected outright.
19.

It is further submitted that all relevant evidence, including the Minutes of Meetings

and Form-M, have already been produced in support of the claim. The Complainant has made
repeated attempts through all possible means to contact the builder, and therefore the
objection regarding alternate remedies has no merit.
20.

It is submitted that RERA does not mandate the issuance of a legal notice as a

precondition for filing a complaint. Moreover, the issue of delay was repeatedly raised during
several in-person meetings organized by the Respondent, where the Respondent themselves
assured new timelines. Therefore, the Respondent was fully aware of the grievance and
cannot now claim otherwise.
5 of 20


It is submitted that there is no dispute regarding the lawful rights obtained by the

Respondent from the landowners, the permissions secured for conversion and building, and
the project registration with this Authority. The Complainant does not dispute these facts.
22.

It is stated that as per the RE(R&D) Act, 2016, the Agreement for Sale is the

governing document. The committed date of possession clearly stated in the Agreement of
Sale is 31.08.2023. The booking date only evidences the buyer’s commitment but does not
alter the Respondent’s obligation.
23.

It is further submitted that as per the Agreement of Sale dated 08.09.2021, possession

was committed by 31.08.2023. Even with the 6-month grace period, the Respondent has
exceeded the timeline as of the date of filing this complaint. While construction progress may
have been reported to the authorities, the fact remains that possession has not been delivered
and the project is only about 85% complete. The reference to amenities is irrelevant to the
core issue, namely the delay in handing over possession.
24.

It is further submitted that Clause 5 of the Agreement confirms the promoter’s

obligation to abide by the time schedule and Clause 7.1 explicitly states that timely delivery
is the essence of the contract. If the Respondent seeks to rely on COVID-19 as force majeure,
the Agreement of Sale dated 08.09.2021 was executed towards the end of COVID-19 period,
when the Respondent was fully aware of its impact.
25.

It is submitted that Clause 7.2 requires that possession be formally offered after

obtaining the Occupancy Certificate. As of the complaint date, no Occupancy Certificate has
been secured, nor any written offer made. The Respondent is in continuing breach of Clause
7.1, as the extended timeline even accounting for grace and force majeure has expired. Clause
9 further defines promoter default, which clearly applies in the present case.
26.

It is further submitted that the allegation that the complaint is filed with ulterior

motive is baseless and unfounded. The Complainant has approached this Hon’ble Authority
with clean hands, placing all material documents including the Agreement for Sale, payment
proofs, and Minutes of Meetings. The Respondent has failed to fulfil the fundamental
obligation to deliver possession on time. The vague allegation of suppression is therefore
denied in toto.

6 of 20


It is submitted that while COVID-19 was a public health emergency, the Agreement

of Sale was executed after the pandemic began, with full awareness of its consequences.
Despite this, the Respondent committed to a specific possession date. Therefore, COVID-19
cannot now be used as an excuse for indefinite delay, beyond the six months’ extension
permissible.
28.

It is further submitted that the reliance placed on the Hon’ble Supreme Court’s

extension of limitation periods is misconceived and irrelevant. Those directions related to
computation of limitation for filing proceedings and do not alter contractual obligations under
RERA. The Respondent entered into the Agreement of Sale on 08.09.2021 with full
knowledge of the COVID-19 situation and yet committed to deliver possession by
31.08.2023. The Respondent never cited the pandemic in earlier communications and instead
attributed delay to funding and legal disputes. Hence, the present reliance on limitation orders
is an afterthought and must be rejected.
29.

It is further submitted that the vague reference to “additional factors” affecting

construction is unsupported by any evidence. No documentary proof has been produced
showing specific reasons for delay or revised timelines. Mere verbal assurances in meetings
cannot substitute statutory obligations under RERA. The Respondent themselves cited
funding and legal issues during meetings, not unidentified “other factors.” Accordingly, the
vague plea of additional reasons must be rejected.
30.

It is submitted that the Respondent’s attempt to treat the possession date of

31.08.2023 as a “clerical or typographical error” is wholly untenable. This date appears
consistently in the Agreement of Sale, including in Clause 7.1, and reflects a deliberate
contractual commitment. If there was indeed an error, the Respondent ought to have executed
a rectification deed or amendment, which was never done. The claim of typographical
mistake is therefore an afterthought and cannot defeat the Complainant’s rights.
31.

It is further submitted that the suggestion that the complaint is baseless and intended

to harass the builder is denied. The complaint rests squarely on documentary evidence,
including the Agreement of Sale and payment proofs. The extension of the project’s RERA
registration until 2026 does not override the Respondent’s individual contractual obligations
to deliver possession by 31st August 2023. RERA registration timelines relate to the life of
the project, not specific contractual delivery dates.
7 of 20


It is submitted that the reference to third-party disputes is also not a valid justification.

The Respondent only disclosed such disputes belatedly in January 2025, long after the
committed possession date and the grace period had expired. The Respondent failed to notify
the Complainant in a timely manner or to obtain specific extensions based on these disputes.
Hence, reliance on such proceedings cannot absolve them of liability for delay.
33.

It is further submitted that while the Respondent communicated certain updates

during meetings and general correspondence, such informal updates cannot override the
binding possession date in the Agreement of Sale. As of the date of filing the complaint, no
Occupancy Certificate has been issued and possession has not been offered. Interest for delay
is a statutory entitlement under Section 18 of RERA.
34.

It is submitted that the denial of interest on the ground of force majeure is contrary to

law. The Respondent voluntarily executed the Agreement during the pandemic period,
committing to a timeline with knowledge of prevailing conditions. Having failed to deliver
within that timeframe, the Respondent is liable to pay interest for delay as mandated by law.
35.

It is further submitted that compensation for hardship and inconvenience is also

justified in addition to statutory interest. The delay has caused real disruption in financial
planning, and stability for the Complainant. These are genuine consequences of the
Respondent’s breach and not arbitrary claims.
36.

It is submitted that the Respondent’s assurance that the project will be completed by

February 2026 does not mitigate their liability. The Complainant has already paid 80% of the
flat cost as per the payment schedule in Schedule-C of the Agreement, and the remaining
amount is due only at the time of registration, which has not yet occurred. As of March 2025,
no formal demand or offer of possession has been made. Therefore, statutory interest for
delay remains payable until actual possession is handed over.
37.

It is further submitted that the new explanation regarding rocky terrain and excavation

challenges is also untenable. This was never cited earlier in any communications with
allottees and cannot now be raised as an unforeseen obstacle. Site conditions are the
developer’s responsibility and are expected to be considered before committing delivery
timelines. Hence, this belated justification deserves no consideration.

8 of 20


It is further submitted that the Respondent’s characterization of the complaint as

“preposterous” is strongly objected to. The Complainant has approached this Hon’ble
Authority lawfully, seeking only statutory and contractual relief for delay. The reputation or
claimed efforts of the Respondent cannot override the Complainant’s rights.
39.

In view of the above submissions, it is respectfully prayed that this Hon’ble Authority

may be pleased to direct the Respondent to compensate for the delay as per applicable law,
and ensure timely possession with the Occupancy Certificate going forward.
E. Points for Consideration:
40.

Upon a careful perusal of the record and the submissions advanced by both parties,

oral as well as written, this Authority is of the view that the following issues arise for
determination in the present complaint:
1. Whether the present complaint is maintainable before this Authority?
2. Whether the Complainants are entitled to the reliefs as prayed for?
F. Observations of the Authority:
Point 1:
41.

The Respondent has raised an objection as to the maintainability of the present

complaint on the ground that the Complainants failed to first resort to the contractual dispute
resolution mechanism envisaged in the Agreement of Sale, namely an amicable settlement by
mutual discussion, prior to approaching this Authority.
42.

The Authority finds this objection untenable for the following reasons:

43.

The relevant Dispute Resolution clause in the Agreement of Sale is reproduced below

for ready reference:
33. Dispute Resolution clause in the Agreement of sale executed between the
parties, the said clause stated that all or any disputes arising out ot touching
upon or in relation to the terms and conditions of this Agreement, including
the interpretation and validity of the terms thereof and the respective rights
and obligations of the Parties, shall be settled amicably by mutual discussion,
falling which the same shall be settled through adjudication officer appointed
under the Act.

9 of 20


It is clear from the above that the clause only requires the parties to attempt an

amicable settlement by mutual discussion. Such a clause is at best directory and cannot oust
or restrict the statutory jurisdiction of this Authority.
45

Section 79 of the RE(R&D) Act expressly bars the jurisdiction of Civil Courts in

respect of any matter which this Authority, the Adjudicating Officer, or the Appellate Tribunal
is empowered to determine. Likewise, Section 88 clarifies that the provisions of the
RE(R&D) Act are in addition to, and not in derogation of, other laws. Thus, the intention of
the legislature is that remedies under this beneficial legislation must remain open to allottees,
irrespective of any private clause for amicable settlement.
46.

Even in cases where agreements contained arbitration clauses (which is not the case

here), the Hon’ble Supreme Court and the Hon’ble NCDRC have consistently held that such
clauses cannot circumscribe the jurisdiction of consumer fora or statutory authorities
constituted under special enactments.
47.

In National Seeds Corporation Ltd. v. M. Madhusudhan Reddy (2012) 2 SCC 506, the

Supreme Court held that remedies under special statutes are in addition to, and not in
derogation of, other remedies. For ready reference, the relevant extract is reproduced below:
*“49. Support to the above view is also lent by Section 79 of the recently enacted
Real Estate (Regulation and Development) Act, 2016 (for short "the Real Estate
Act").
Section
79
of
the
said
Act
reads
as
follows:‘79. Bar of jurisdiction - No civil court shall have jurisdiction to entertain any suit or
proceeding in respect of any matter which the Authority or the adjudicating officer or
the Appellate Tribunal is empowered by or under this Act to determine and no
injunction shall be granted by any court or other authority in respect of any action
taken or to be taken in pursuance of any power conferred by or under this Act.’
It can thus, be seen that the said provision expressly ousts the jurisdiction of the Civil
Court in respect of any matter which the Real Estate Regulatory Authority,
established under Subsection (1) of Section 20 or the Adjudicating Officer, appointed
under Sub-section (1) of Section 71, or the Real Estate Appellate Tribunal established
under Section 43 of the Real Estate Act, is empowered to determine. Hence, in view of
the binding dictum of the Hon'ble Supreme Court in A. Ayyaswamy (supra), the
matters/disputes, which the Authorities under the Real Estate Act are empowered to
decide, are non-arbitrable, notwithstanding an Arbitration Agreement between the
parties to such matters, which, to a large extent, are similar to the disputes falling for
resolution under the Consumer Act.
56. Consequently, we unhesitatingly reject the arguments on behalf of the Builder
and hold that an Arbitration Clause in the afore-stated kind of Agreements
between the Complainants and the Builder cannot circumscribe the jurisdiction
of a Consumer Fora, notwithstanding the amendments made to Section 8 of the
Arbitration Act.”*

10 of 20


Similarly, in Aftab Singh &Ors. v. Emaar MGF Land Ltd. &Ors. (Consumer Case No.

701 of 2015, decided on 13.07.2017), it was held that arbitration clauses in builder-buyer
agreements cannot oust the jurisdiction of consumer fora. The said view was later upheld by
the Hon’ble Supreme Court in Civil Appeal Nos. 23512–23513 of 2017. The relevant para
reads:
25. This Court in the series of judgments as noticed above considered the
provisions of Consumer Protection Act, L986 os well as Arbitration Act, 1996 and
laid down that complaint under Consumer Protection Act being a special remedy,
despite there being an arbitration agreement the proceedings before Consumer
Forum have to go on and no ercor committed by Consumer Forum on rejecting
the application. There is reason for not interjecting proceedings under Consumer
Protection Act on the strength an arbitration agreement by Act, 1996. The remedy
under Consumer Protection Act is a remedy provided to a consumer when there is
a defect in any goods or services. The complaint means any allegation in writing
made by a complainant has also been explained in Section 2(c) of the Act. The
remedy under the Consumer Protection Act is confined to complaint by consumer
as defined under the Act for defect or deficiencies caused by a service provider,
the cheap and a quick remedy has been provided to the consumer which is the
object and purpose of the Act as noticed above."

49.

In the present matter, there is only a clause requiring amicable discussion before

invoking remedies. Such a clause is directory at best, and cannot override or defeat the
statutory right of the Complainant to approach this Authority under the RE(R&D) Act.
Accordingly, this Authority has no hesitation in holding that the Complainant is well within
its rights to approach this forum without being first compelled to pursue an amicable
settlement under the Agreement. The objection of the Respondent as to maintainability is
therefore rejected.
Point No. 2:
50.

The Complainants have sought relief on the ground that there has been an inordinate

delay in handing over of possession of the subject flat.
51.

It is the case of the Complainants that the Agreement of Sale dated 08.09.2021,

executed between the parties, clearly stipulated that possession of the subject flat would be
handed over by 31.08.2023, with a grace period of six months, ending on 28.02.2024. The
Respondent has failed to hand over possession even as on date. Further, although the project
was registered with TG RERA up to February 2025 and later extended until February 2026,
the project remains incomplete.
11 of 20


The Complainants submit that the Respondent has repeatedly given false assurances

of completion, while allottees continue to suffer. The Respondent, conversely, attributes the
delay to the Covid-19 pandemic, claiming force majeure, citing the nationwide lockdown
beginning March 2020, the impact on migrant labour, and consequential delays. The
Respondent further cites rocky terrain at the site, third-party disputes, and typographical
errors in the possession date as additional justifications.
i.

Whether the Covid-19 pandemic can be taken as a valid shield by the Respondent in
the present case?

53.

This Authority finds no merit in such contentions. The Agreement of Sale was

admittedly executed on 08.09.2021, much after the onset and near subsiding of the Covid-19
pandemic. The Respondent, being fully aware of the prevailing global circumstances,
nevertheless executed the Agreement by specifically assuring completion of the project by
August 2023 with the grace period of 6 months i.e 28.02.2024. Having consciously
undertaken such commitment, the Respondent cannot now, with retrospective justification,
rely on Covid-19 as a defense to escape its contractual and statutory obligations. Such
conduct clearly amounts to holding out false assurances with mala fide intent.
54.

It is a settled principle that once a promoter has chosen to register a project and enter

into binding contractual commitments with allottees, he does so with full knowledge of the
risks, constraints, and challenges of the market. At the time of entering into the Agreement of
Sale with the present Complainant, the Respondent was already aware of the Covid-related
disruptions, as well as the Government notifications granting moratoriums for project
completion timelines. Despite this knowledge, the Respondent chose to provide a specific
assurance of delivery by August 2023.
55.

This Authority aligns with the observations of the Hon’ble Bombay High Court in

Neelkamal Realtors Suburban Pvt. Ltd. &Anr. vs. Union of India &Ors. [2017 SCC OnLine
Bom 9302], wherein at para 119 it was categorically observed:
"While the proposal is submitted, the Promoter is supposed to be conscious
of the consequences of getting the project registered under RERA. Having
sufficient experience in the open market, the Promoter is expected to have a
fair assessment of the time required for completing the project…".

56.

The above dictum fortifies the principle that the promoter, being structurally at an

advantageous position with respect to project information and market realities, is under a
statutory duty to provide realistic timelines. The framework of the Real Estate (Regulation

12 of 20


Therefore, the plea of Covid-19 as a force majeure defence in the present case is

wholly untenable. The Respondent, having executed the Agreement of Sale in August 2021
with specific possession timelines, cannot now seek to retrospectively attribute delays to the
pandemic. Accordingly, this Authority holds that the reliance on Covid-19 as a shield stands
rejected.
ii.

Extension of Registration

58

The Respondent has further contended that, since extensions have been granted by

this Authority, the project timeline now stands extended up to February 2026, and therefore
possession shall be delivered by then. The Complainants, however, have questioned the
validity and effect of such extensions.
59.

At the outset, it must be clarified that under the scheme of the RE(R&D) Act:
“An Act to establish the Real Estate Regulatory Authority for regulation and
promotion of the real estate sector and to ensure sale of plot, apartment or building,
as the case may be, or sale of real estate project, in an efficient and transparent
manner and to protect the interest of consumers in the real estate sector and to
establish an adjudicating mechanism for speedy dispute redressal and also to
establish the Appellate Tribunal to hear appeals from the decisions, directions or
orders of the Real Estate Regulatory Authority and the adjudicating officer and for
matters connected therewith or incidental thereto.”

60.

The paramount objective is twofold: protection of consumer interest, and ensuring

completion of projects in an efficient manner. Denial of extension during the Covid-19
disruption would have resulted in projects being stalled, to the grave prejudice of allottees. It
was in this context that this Authority, balancing the equities, granted extensions in line with
the moratoriums issued by Telangana RERA:
1. 15.03.2020 to 14.09.2020 (Circular No.14 dated 13.05.2020),
2. 15.09.2020 to 15.03.2021 (Order No.15 dated 29.09.2020),
3. 15.03.2021 to 14.09.2021 (Order No.16 dated 01.06.2021).
61.

Accordingly, an aggregate 18 months’ extension was applied across projects to

safeguard larger consumer interest. However, it is equally well settled that such regulatory
extensions cannot dilute the contractual rights of individual allottees under their respective

13 of 20


In the present matter, it is evident that the Respondent has unilaterally revised

possession timelines first to February 2024, and thereafter to February 2026 due to the
extension taken without consultation or consent of the Complainants. Such unilateral
revisions are impermissible. The Hon’ble Bombay High Court in Neelkamal Realtors
Suburban Pvt. Ltd. vs. Union of India &Ors. [2017 SCC OnLine Bom 9302], while
upholding the constitutional validity of RERA, categorically observed:
Para 119 “The RERA does not contemplate rewriting of contract between the
flat purchaser and the promoter."
Para 256 of this Judgment further clarifies that
“by giving opportunity to the promoter to prescribe fresh timeline under
Section 4(2)(l)(C), he is not absolved of the liability under the agreement for
sale”

63.

The above dicta makes it abundantly clear that any extension granted by the

Authority, or revised timelines uploaded on the TG RERA project registration portal, do not
ipso facto alter or bind the allottees’ contractual rights. The agreed date of possession remains
as stipulated in the Agreement for Sale, and unilateral extensions by the promoter cannot be
foisted upon allottees to their detriment.
64.

Accordingly, this Authority holds that the revised possession dates mentioned by the

Respondent, whether while seeking extensions before the Authority or as updated on the
registration portal, cannot be treated as binding on the Complainants.

iii.

Relief under Section 18 of the RE(R&D) Act:

65.

It is not in dispute that the Complainants have paid approximately 80% of the total

sale consideration substantiated with the payment receipts, diligently and without default.
The Agreement clearly stipulated possession by 31.08.2023, with grace period of 6 months to
28.02.2024. Admittedly, possession has not been delivered.
66.

The Respondent’s contention that 90% work is complete and that the complainants

have paid only partial consideration is wholly unsustainable. The complainants have already
paid substantial amount of the agreed consideration. Despite receiving such substantial sums,
the Respondent has failed to honour its contractual obligations. It is manifest that the
Respondent gave false assurances, being fully conscious of the market situation, yet assuring

14 of 20


The Respondent further seeks to shift the burden on the complainant by contending

that the balance amount is unpaid. This plea is untenable. The law does not permit a defaulter
to take advantage of its own breach. As held by the Hon’ble Supreme Court in Kusheshwar
Prasad Singh v. State of Bihar [Civil Appeal No. 7357 of 2000]:
It is settled principle of law that a man cannot be permitted to take undue and
unfair advantage of his own wrong to gain favourable interpretation of law. It is
sound principle that he, who prevents a thing from being done shall not avail
himself of the non-performance he has occasioned. To put it differently, "a
wrongdoer ought not to be permitted to make a profit out of his own wrong.

68.

In this context, it is pertinent to note that the Agreement of Sale linked the payment

schedule to the progress of construction. While the allottees are indeed bound to adhere to the
agreed payment plan, such obligation arises only when the promoter simultaneously fulfils its
reciprocal obligation of executing construction in line with the assured progress. In the
absence of such progress, the Respondent cannot insist upon further payments as a condition
to claim relief.
69.

Section 18 of the RE(R&D) Act is categorical and unconditional. It does not make the

grant of interest contingent upon the quantum of sale consideration paid, nor does it provide
any defence to a defaulting promoter. Once delay in handing over possession is established,
an allottee who elects to remain in the project is entitled to interest for every month of delay,
irrespective of whether part or whole of the consideration has been paid, provided that the
payments already made are in accordance with the Agreement of sale. The Respondent’s plea
that only “partial sale consideration” has been paid and hence interest cannot be granted is
therefore vague, misconceived, and contrary to the express mandate of the statute.
70.

Now, Section 18 of the RE(R&D) Act is categorical:
(1) If the promoter fails to complete or is unable to give possession of an
apartment, plot or building,—
(a) in accordance with the terms of the agreement for sale or, as the case may
be, duly completed by the date specified therein; or
(b) due to discontinuance of his business as a developer on account of
suspension or revocation of the registration under this Act or for any other
reason,

15 of 20


71.

This statutory right of allottee is unqualified and absolute. Attention is drawn to the

decision of the Hon'ble Supreme Court of India in Civil Appeal Nos. 3581-359 of 2022, Civil
Appeal Diary No. 9796/2019, M/s Imperia Structures Limited vs. Anil Patni & Others,
wherein it was held:
"In terms of Section 18 of the RERA Act, if a promoter fails to complete or is
unable to give possession of an apartment by the date specified in the agreement,
the promoter would be liable, on demand, to return the amount received in
respect of that apartment if the allottee wishes to withdraw from the project.
Such a right of the allottee is 'without prejudice to any other remedy available to
him'. This right is unqualified, and if availed, the deposited money must be
refunded with interest as prescribed. The proviso to Section 18(1) contemplates
that if the allottee does not intend to withdraw from the project, they are entitled
to interest for every month of delay until possession is handed over. The allottee
may proceed under Section 18(1) or the proviso thereto."

72.
Similarly, in Civil Appeal Nos. 6745-6749 of 2021, M/s Newtech Promoters and
Developers Private Limited vs. State of UP & Others, the Hon’ble Supreme Court observed:
"Section 18(1) of the Act spells out the consequences if the promoter fails to
complete or is unable to give possession of an 9 of 10 apartment, plot, or
building in terms of the agreement for sale. The allottee/home buyer holds an
unqualified right to seek a refund of the amount with interest as prescribed."

73.

Further, as earlier observed, the Hon’ble Bombay High Court in Neelkamal Realtors

Suburban Pvt. Ltd. v. Union of India [(2017) SCC Online Bom 9302] clarified that RERA
registration or its extension cannot rewrite the contract between parties. The date assured
under the Agreement of Sale, executed with the allottee’s consent, shall prevail. Thus, the

16 of 20


At the same time, if the Complainant has indeed defaulted in adhering to the payment

schedule, the Respondent is not without remedy. Sections 19(6) and 19(7) of the Act confer
upon the promoter a right to claim interest for delayed payments, as per Rule 15 of the
Telangana RE(R&D) Rules, 2017. Nevertheless, such entitlement shall be subject to the
Respondent producing cogent and substantive documents demonstrating both the stage-wise
progress of construction and the corresponding default, and not merely based on unilateral
assertions.
75.

In the present case, this Authority finds the Respondent in clear breach of both

statutory and contractual obligations. The Complainant is therefore entitled to interest at the
prescribed rate for the entire period of delay, i.e., from 01.03.2024 until the actual date of
handing over possession. As regards claims of compensation, this Authority notes that
jurisdiction for adjudicating compensation lies with the Adjudicating Officer under Section
71 of RE(R&D) Act with Form ‘N’. The Complainant is at liberty to pursue such remedy
separately..
76.

Accordingly, while the Complainant is entitled to relief under Section 18 of the

RE(R&D) Act, this entitlement is subject to the reciprocal statutory duty of the Complainant
to discharge any outstanding amounts under the payment plan, if not already paid.
Compliance on both sides is essential to ensure balance of obligations and timely delivery.
77.

This Authority cannot remain oblivious to the larger pattern of violations. It is noted

with grave concern that more than fifty complaints have already been received against this
very Respondent in respect of the subject project. Such repeated defaults and false assurances
strike at the very root of the confidence that homebuyers are entitled to repose under the
protective framework of the RE(R&D) Act.
78.

The Statement of Objects and Reasons of the RE(R&D) Act explicitly emphasizes

“greater accountability towards consumers and to inject transparency, efficiency, and
discipline in the real estate sector”. The conduct of the Respondent herein is in gross
derogation of that legislative mandate. If such violations are permitted to persist, the very
soul of the Act would stand diluted and the protection promised to allottees rendered illusory.

17 of 20


Accordingly, this Authority hereby sternly warns the Respondent promoter that any

further default, non-compliance, or failure to deliver possession within the assured statutory
timelines or any fresh grievances brought to notice by allottees shall invite invocation of
Section 63 of the RE(R&D) Act.
80.

This Authority shall not hesitate to take the strictest view in future, for the Act was

enacted not as a mere regulatory framework but as a beneficial legislation to protect innocent
homebuyers from the very malaise exemplified by the conduct of this Respondent.
81.

The Respondent is hereby directed to complete the project and hand over possession

to the Complainants within the stipulated period. It is further clarified that if the
Complainants have defaulted in making payments as per the agreed schedule, the Respondent
shall be entitled under Section 19(6) of the Act to claim interest on such delayed payments,
provided that it substantiates such claim with credible documentary evidence of both
construction progress and corresponding default.
82.

In the event the Complainants have defaulted in making payments as per the agreed

schedule, the Respondent shall be entitled, under Section 19(6) of the Real Estate (Regulation
and Development) Act, 2016, to claim interest on such delayed payments in accordance with
Rule 15 of the Telangana Real Estate (Regulation and Development) Rules, 2017.
Nevertheless, such entitlement shall be subject to the Respondent producing cogent and
substantive documents demonstrating both the stage-wise progress of construction and the
corresponding default, and not merely based on unilateral assertions.
83.

The Complainants are, in turn, directed to discharge any balance amounts due under

the agreed payment schedule, if not already paid. Mutual compliance is essential to ensure
timely completion and delivery of the project.
G. Directions of the Authority:
85.

In view of the findings and observations recorded hereinabove, this Authority

proceeds to issue the following directions:
a. The preliminary objection raised by the Respondent regarding the maintainability of
the complaint on account of the Dispute Resolution Clause in the Agreement of Sale
stands rejected. The complaint is maintainable before this Authority.

18 of 20


Having regard to the repeated defaults and the large number of complaints

already pending against this Respondent in the same project, this Authority sternly warns
the Respondent that any further delay, non-compliance, or grievance brought to notice by
allottees shall invite section 63 of the RE(R&D) Act.
87.

The complaint is accordingly allowed in part, in terms of the above directions.
19 of 20


Failure to comply with above said directions by the Respondent shall attract

penalty in accordance with Section 63 of the RE(R&D) Act, 2016
89.

As a result, the complaint is disposed of accordingly. No order as to costs.

Sd/Sri. K. Srinivas Rao,
Hon’ble Member
TG RERA

Sd/Sri. Laxmi NaryanaJannu,
Hon’ble Member
TG RERA

Sd/Dr. N. Satyanarayana, IAS (Retd.),
Hon’ble Chairperson
TG RERA

20 of 20


Related Orders

Interim Order Complaint No.228 of 2025
Rangareddy, Telangana, 500077)
15 Apr 2026
Order Complaint No. 386 of 2025
Koti, Hyderabad-500027.
09 Apr 2026
Order Complaint No. 153 of 2024
Telangana – 500011.
08 Apr 2026
Order Complaint No. 152 of 2024
Telangana – 500011.
08 Apr 2026
Order Complaint No. 151 of 2024
Telangana – 500011.
08 Apr 2026

Need Complete Property Verification?

Get ownership details, EC records, survey sketch, zone checks, geo-insights & AI analysis - all in one place

Ownership Details
EC Records
Survey Sketch
Zone Checks
Geo-Insights
AI Analysis
Try VerifyMyLand Now ✨ Get comprehensive property verification in minutes

Verify Your Property Before You Buy

AI-powered legal due diligence — title verification, encumbrance checks, zoning compliance, and risk assessment in minutes. Catch issues before they cost you crores.