BEFORE TELANGANA REAL ESTATE REGULATORY AUTHORITY
[Under the Real Estate (Regulation and Development) Act, 2016]
Complaint No. 194 of 2024
25th of April, 2025
Corum:
Dr. N. Satyanarayana, IAS (Retd.), Hon’ble Chairperson
Sri K. Srinivasa Rao, Hon’ble Member
Sri Laxmi Narayana Jannu, Hon’ble Member
Devi Linga Reddy
(Flat No.7, Second floor, Amar Apartments East Maredpally, Hyderabad, Telangana 500026)
…Complainant
Versus
M/s. Aditya Construction Company India(P) Ltd,
(Represented through its Authorized Representative)
Aditya Mansion, Plot No. 29/A, Road No.5, Jubilee Hills, Hyderabad, Telangana – 500081
…Respondent
The Complainant has filed complaint on hand under Section 31 of the Real Estate
(Regulation and Development) Act, 2016 (hereinafter referred to as the "RE(R&D) Act"), read
with Rule 34(1) of the Telangana Real Estate (Regulation and Development) Rules, 2017
(hereinafter referred to as the "Rules"), alleging commission of violation and contravening of
the provisions of the said Act and Rules and sought for the appropriate reliefs against the
Respondent.
2.
The matter was listed before this Authority on 22.04.2025. The Complainant appeared
in person and the Respondent was represented through learned Counsel, Sri Srinivas Achanta
and Smt. Aruna Kumari.
3.
During the course of proceedings, it was brought to the notice of the Authority that both
parties had mutually executed a Settlement Memo dated 26.03.2025, in terms of which certain
works were to be completed by the Respondent.
4.
Upon perusal of the records and hearing the submissions of the parties, it was noted that
although the Settlement Memo was filed earlier, the Complainant had submitted that
compliance with respect to certain works was still pending. Consequently, the Authority, vide
its interim direction, had granted time to the Respondent to ensure full compliance with the
terms of the Settlement Memo.
5.
On the next date of hearing, i.e., 22.04.2025, both the Complainant and the Respondent
appeared, submitted that the agreed works had been duly completed and that the Complainant
had no further grievance.
6.
In view of the Settlement Memo dated 26.03.2025 and the submissions made by the
Complainant, the Authority is satisfied that the dispute between the parties has been amicably
resolved.
7.
Accordingly, the present Complaint stands disposed of as withdrawn.
8.
No order as to costs.
Sd/Sri. K. Srinivasa Rao,
Hon’ble Member
TG RERA
Sd/Sri. Laxmi Naryana Jannu,
Hon’ble Member
TG RERA
Sd/Dr. N. Satyanarayana, IAS (Retd.),
Hon’ble Chairperson
TG RERA
Related Orders
Interim Order Complaint No.228 of 2025
Rangareddy, Telangana, 500077)Order Complaint No. 386 of 2025
Koti, Hyderabad-500027.Order Complaint No. 153 of 2024
Telangana – 500011.Order Complaint No. 152 of 2024
Telangana – 500011.Order Complaint No. 151 of 2024
Telangana – 500011.Need Complete Property Verification?
Get ownership details, EC records, survey sketch, zone checks, geo-insights & AI analysis - all in one place