Order Complaint No. 161 of 2025
Order Details
| Order Type | TG-RERA Authority |
|---|---|
| Complaint/Case Number | Complaint No. 161 of 2025 |
| Year | 2025 |
| Order Category | Regular Order |
| Order Date | 30 Dec 2025 |
| Complainant | Hyderabad - 500050. |
| Respondent | Road No. 12, Banjara Hills, Hyderabad, Telangana - 500034 |
| PDF Document | Download PDF BU_311225170327276.pdf |
Full Order Text
BEFORE TELANGANA REAL ESTATE REGULATORY AUTHORITY
[Under the Real Estate (Regulation and Development) Act, 2016]
Complaint No. 161 of 2025
Dated: 30th December 2025
Quorum:
Dr. N. Satyanarayana, IAS (Retd.), Hon’ble Chairperson
Sri K. Srinivasa Rao, Hon’ble Member
Sri Laxmi Narayana Jannu, Hon’ble Member
Mr. Bramhaji Kande,
R/o # 402, Block-C, West Metro Apartments,
Friends Colony, Chandanagar,
Hyderabad - 500050.
…Complainant
Versus
M/s. Vasavi Realtor LLP,
Rep by its Designated Partner, Vijay Kumar Yerram & Kandey Ramesh,
Vasavi Corporate,
H.No.8-2-703/7/1 and 8-2-703/7/1/A,
4th Floor, Vasavi Corporate Building, Amrutha Valley Apartments,
Road No. 12, Banjara Hills, Hyderabad, Telangana - 500034
…Respondent
The present matter filed by the Complainant herein came up for hearing before this
Authority in presence of Complainant and the Respondent; upon pursuing the material on
record and on hearing arguments of both the parties and having stood over for consideration
till this day, the following order is passed:
ORDER
2.
The present Complaint has been filed by the Complainant under Section 31 of the Real
Estate (Regulation & Development) Act, 2016 (hereinafter referred to as the “Act”) read with
Rule 34(1) of the Telangana Real Estate (Regulation and Development) Rules, 2017
(hereinafter referred to as the “Rules”) seeking appropriate relief(s) against the Respondents.
A. The brief facts of the case, as stated by the Complainant, are as follows:
3.
It was submitted that the Complainant had visited the “Vasavi Lake City West” project
in 2021 and subsequently booked a flat in January 2021. It was stated that pursuant to the terms
of the sale agreement, the Respondent was obligated to hand over possession of the flat by
August 2023, with a permissible extension until February 2024.
4.
It was contended that as of the time of filing the complaint, the flat was not ready for
possession and the project remained under construction, in breach of the agreed-upon timeline.
Page 1 of 20
It was further submitted that the Complainant had paid 90% of the total cost of the flat
by May 2023, thereby fulfilling all payment obligations in accordance with the schedule
stipulated by the Respondent.
6.
It was alleged that the Respondent had repeatedly postponed the handover dates and
had demonstrated a lack of concern for its customers. The Complainant submitted that despite
having paid their hard-earned money in a timely manner, they had not received possession of
their flat.
B. Reliefs Sought
7.
Accordingly, the Complainant sought the following reliefs:
i.
To direct the Respondent to forthwith complete all pending construction and hand over
possession of the subject flat to the Complainant at the earliest, within a fixed and
enforceable timeframe to be determined by this Honourable Authority.
ii.
To direct the Respondent to pay interest on the total amounts paid by the Complainant,
calculated from the promised date of possession as per the Agreement for Sale until the
actual date of handover, at the rate prescribed under the Act.
iii.
To direct the Respondent to pay adequate compensation for the severe mental anguish,
financial strain, health issues, and loss of professional time suffered by the Complainant
as a direct result of the inordinate delay in the project's completion and the ongoing
burden of loan EMIs.
C. Counter filed by the Respondents.
8.
It was submitted by the Respondent that the complaint was not maintainable either in
law or on facts and was liable to be dismissed. The Respondent contended that the Complainant
had failed to follow the remedies available under the Agreement for Sale for the resolution of
disputes before approaching this Hon’ble Authority. It was further submitted that no prior legal
notice was issued before the filing of the complaint, which rendered the application defective.
9.
It was submitted that the project, “Lake City-West,” was developed lawfully after the
Respondent obtained rights from the landowners under registered documents, covering a total
land area of 34,704.37 sq. yds. The requisite permissions for land conversion and for the
construction of multi-storied residential apartments were obtained on 07.02.2020. The project,
consisting of multiple towers and a clubhouse, was duly registered with this Authority vide
Registration No. P02500001821 dated 20.03.2020.
Page 2 of 20
It was further submitted that the Complainant was allotted apartment No. W. 30309 on
the 3rd Floor of Tower 3, admeasuring 1650 sq. ft., and an undivided share of 44 sq. yds. of
land under the Agreement of Sale. The agreement detailed the carpet area, balcony area,
common area, and the undivided share of land. The total sale consideration was Rs.
1,00,35,000/- out of which the Complainant paid Rs. 21,07,350/-.
11.
It was submitted that as per Clause 7 of the Agreement, the Respondent was obligated
to hand over possession of the apartment on or before 31.08.2024, with a grace period of six
months. The said clause explicitly stated that the period of completion would stand extended
in the event of force majeure conditions, during which the allottee was not entitled to claim any
compensation for the delay.
12.
It was contended that the Complainant had not approached this Hon’ble Authority with
clean hands but with an ulterior motive for unlawful gain, and that there had been a material
suppression of facts. While the existence of the Agreement of Sale was not in dispute, the
Respondent averred that the Complainant made false claims despite being aware of the
contractual terms and circumstances.
13.
The Respondent stated that the project timelines were severely impacted by the
COVID-19 pandemic, which was a force majeure event recognized under law. It was submitted
that following the declaration of a public health emergency in January 2020, a nationwide
lockdown was imposed in India from March 2020. This event led to a mass migration of the
labour force, which was critical to the construction industry in Hyderabad, thereby causing a
significant and unavoidable delay in the project work. All allottees were kept informed of these
developments.
14.
The Respondent further relied on the orders of the Hon’ble Supreme Court in Suo Motu
Writ Petition (C) No. 3 of 2020, whereby the period from 15.03.2020 to 28.02.2022 was
excluded for the purposes of computing limitation across all statutes. It was contended that this
legally recognized the extraordinary circumstances and justified the extension of timelines for
project completion.
15.
In addition to the pandemic, the Respondent submitted that the project was delayed by
other unforeseen factors. It was stated that the project site contained rocky terrain which, due
to its location in a residential vicinity, could not be excavated using explosives. The consequent
need for manual rock-breaking compounded the construction delays. Furthermore, the project
was adversely impacted by third-party disputes, including several legal proceedings filed
Page 3 of 20
It was contended that any clerical or typographical errors in the Agreement of Sale,
such as an incorrect possession date mentioned in one instance, could not be exploited to create
liability, especially when the magnitude of the project made such a timeline practically
impossible. The Respondent asserted that the project was over 90% complete and in the final
finishing stages. An extension for the project registration had been granted by this Authority
up to 07.02.2026, and the Respondent gave an undertaking to deliver the apartments within this
extended period.
17.
With regard to the claims for interest and compensation, the Respondent submitted that
such reliefs were not maintainable in view of the force majeure conditions. It was argued that
the circumstances clearly fell within the definition provided under Section 6 of the Act. The
Respondent maintained that the delay was not due to any deliberate act or default on its part,
and therefore, the Complainant had not established any legal basis for claiming compensation
for mental agony or financial loss.
18.
The Respondent concluded that the complaint was preposterous and without
foundation. It was prayed that the complaint be dismissed and the Respondent be allowed to
complete the project and deliver possession to all allottees as per the extended timeline.
D. Rejoinder filed by the Complainant
19.
It was submitted in response to the preliminary objection on maintainability, that the
said objection was vague, unsupported, and legally untenable. The complaint had been filed
under Section 31 of the Real Estate (Regulation and Development) Act, 2016, which explicitly
granted an aggrieved allottee the right to seek redressal. It was stated that the Agreement of
Sale dated 16th November 2021 clearly committed to handing over possession by 31st August
2023, and as the flat had not been delivered, the complaint was fully maintainable.
20.
The contention that the Complainant had not availed methods as provided in the
agreement was described as legally unfounded and entirely unsustainable. It was submitted that
under Section 31 of the Act, an aggrieved allottee had a statutory and independent right to
approach the Hon'ble Authority, and the existence of any private dispute mechanism did not
oust the jurisdiction of the Authority. It was further stated that the Complainant had attempted
Page 4 of 20
The objection regarding the non-issuance of a legal notice was described as legally
misconceived and procedurally irrelevant, as there was no such requirement under Section 31
of the Act.
22.
It was stated that the Respondent's development rights and the permissions obtained for
construction were not in dispute; the issue lay in the Respondent's failure to deliver possession
on time as per contractual obligations.
23.
It was submitted that while the project was registered with RERA, the Respondent had
grossly failed to comply with the obligations that accompanied such registration, particularly
those relating to timely possession and transparency. The Respondent's conduct postregistration showed a clear disregard for the regulations.
24.
It was submitted that the Respondent's reference to the booking date was legally
immaterial, and the apartment number was incorrectly mentioned, the correct number being
W30309. The rights and obligations were governed solely by the Agreement of Sale dated 12th
March 2021, which committed to possession by 31st August 2023. The Complainant had duly
paid a sum of ₹93,20,006/- towards the sale consideration.
25.
The Respondent's reliance on a RERA extension was described as legally flawed and
misleading. It was submitted that the possession date as agreed between the parties, 31st August
2023, must prevail for assessing delay, irrespective of any regulatory extensions. The
Respondent's conduct, in now citing a delivery date of February 2026, rendered the contract
meaningless.
26.
The Complainant fully acknowledged the payment of the booking amount of
₹39,60,000/-. However, it was submitted that the Respondent's attempt to divert the discussion
toward specifications was unrelated to the core issue of delay in possession.
27.
It was submitted that the Respondent had selectively cited clauses while ignoring their
binding obligation to deliver possession on or before 31st August 2023. The Respondent had
far exceeded even the six-month grace period. The repeated reference to force majeure was
described as legally untenable and factually inapplicable, as the Agreement was executed in
March 2021, after the major COVID-19 lockdowns. It was noted that sales representatives had
actively promised even earlier possession. It was argued that a force-majeure clause could not
override the statutory right granted to allottees under Section 18(1) of the RERA Act.
Page 5 of 20
The Respondent's selective quoting of Clause 7.2 was stated to be misleading and
premature, as the condition precedent of obtaining an occupancy certificate (OC) had not been
met. It was submitted that Clause 9, which dealt with promoter defaults, was fully applicable
and must be enforced.
29.
The Complainant categorically denied the baseless, vague, and defamatory allegations
of acting with an "ulterior motive." It was submitted that the Complainant had made full and
honest disclosure of all relevant facts, including proof of payments totalling ₹93,20,006/-,
whereas the Respondent had failed to meet their contractual obligations.
30.
While the impact of the COVID-19 pandemic was acknowledged, it was submitted that
the Respondent's reliance on it was misleading, as the Agreement for Sale was executed on 12th
March 2021, with full knowledge of the circumstances. The delay from 2023 to 2025 could not
be blamed on the pandemic and was instead a result of mismanagement and inefficiency.
31.
It was submitted that the legal extensions cited by the Respondent pertained only to
statutory limitation periods for initiating legal proceedings and had no bearing whatsoever on
a real estate developer's contractual obligations under the RERA Act.
32.
The attempt to attribute the delay to labour migration was stated as not being applicable
to the facts, as the Complainant's unit in Tower 3 had been structurally completed more than
24 months prior, and the subsequent delay reflected a lack of intent and mismanagement on the
part of the builder.
33.
The Respondent's statement regarding "various additional factors" was described as
vague, evasive, and devoid of any factual backing. It was submitted that the claim that
"customers were intimated from time to time" was factually incorrect in the Complainant's
case.
34.
The response by the Respondent, terming the committed possession date in a formally
executed Agreement of Sale as a product of "clerical and typographical mistakes," was
described as both self-incriminating and legally indefensible. It was submitted that this was a
dishonest afterthought and reflected a complete abdication of responsibility, or worse, a
misrepresentation from the outset.
35.
The accusation that the Complainant's allegations were factually baseless was described
as an unfounded, derogatory, and blatant diversionary tactic. It was submitted that the
Complainant had provided extensive documentary evidence, while the Respondent's citation
of a RERA registration extension had no bearing on their contractual liability.
Page 6 of 20
It was submitted that while certain legal disputes may have arisen, their mere existence
could not be used as a blanket justification for delay. It was the legal responsibility of the
promoter under Section 11(3)(a) of the RERA Act to ensure the project was free of
encumbrances, and these risks had not been proactively disclosed.
37.
The Complainant challenged the Respondent to produce any formal written
communication that proactively disclosed delays. It was submitted that the pattern of repeatedly
outlining and then dishonouring revised timelines reflected a calculated approach to deflect
pressure.
38.
The Complainant submitted that the claim for interest was a non-negotiable and
unconditional statutory right under Section 18(1) of the Act. The reliance on force majeure due
to COVID-19 was wholly misplaced as the Agreement was signed after the lockdown period.
The Complainant, who had already paid over ₹93,20,006/- was not seeking cancellation but
merely the rightful interest.
39.
The Respondent's statement regarding compensation was stated to reflect complete
insensitivity to the real and severe consequences faced by the Complainant, which had been
clearly laid out in Form M. Specific hardships were detailed, including the displacement of
aged parents, increased commute times, and mental agony.
40.
The Complainant strongly objected to the Respondent's claim that delivery was now
scheduled for February 2026 and that the Complainant was in arrears. It was asserted that the
Complainant had never agreed to any extension and was not in default, having paid over 90%
of the consideration and was awaiting clarifications to release further payments. The
Respondent's "unconditional undertaking" was stated as not waiving their legal liability for
interest.
41.
The response regarding the Complainant agreeing to the delay was described as another
attempt to deflect responsibility using afterthought excuses. It was stated that the Complainant
never agreed to excuse the delay. The new claim about rocky terrain reflected a lack of due
diligence and was a foreseeable project risk, not force majeure.
42.
The Respondent's statement that the Complainant was not entitled to any relief was
described as a sweeping and baseless denial of liability. It was submitted that the Respondent's
generic claim that the delay was "beyond their control" had been repeatedly refuted.
43.
Finally, it was submitted that the Respondent's characterization of the complaint as
"preposterous" and "false" was unfounded. The Respondent's claimed reputation could not
Page 7 of 20
Upon a careful perusal of the record and the submissions advanced by both parties, oral
as well as written, this Authority is of the view that the following issues arise for determination
in the present complaint:
1. Whether the present complaint is maintainable before this Authority?
2. Whether the Complainants are entitled to the reliefs as prayed for?
F. Observations of the Authority:
Point 1:
45.
The Respondent has raised an objection as to the maintainability of the present
complaint on the ground that the Complainants failed to first resort to the contractual dispute
resolution mechanism envisaged in the Agreement of Sale, namely an amicable settlement by
mutual discussion, prior to approaching this Authority. The Authority finds this objection
untenable for the following reasons:
46.
The relevant Dispute Resolution clause in the Agreement of Sale is reproduced below
for ready reference:
“33. Dispute Resolution clause in the Agreement of sale executed between the parties, the said
clause stated that all or any disputes arising out ot touching upon or in relation to the terms
and conditions of this Agreement, including the interpretation and validity of the terms thereof
and the respective rights and obligations of the Parties, shall be settled amicably by mutual
discussion, falling which the same shall be settled through adjudication officer appointed under
the Act.”
47.
It is clear from the above that the clause only requires the parties to attempt an amicable
settlement by mutual discussion. Such a clause is at best directory and cannot oust or restrict
the statutory jurisdiction of this Authority. Section 79 of the RE(R&D) Act expressly bars the
jurisdiction of Civil Courts in respect of any matter which this Authority, the Adjudicating
Page 8 of 20
Even in cases where agreements contained arbitration clauses (which is not the case
here), the Hon’ble Supreme Court and the Hon’ble NCDRC have consistently held that such
clauses cannot circumscribe the jurisdiction of consumer fora or statutory authorities
constituted under special enactments.
49.
In National Seeds Corporation Ltd. v. M. Madhusudhan Reddy (2012) 2 SCC 506, the
Supreme Court held that remedies under special statutes are in addition to, and not in derogation
of, other remedies. For ready reference, the relevant extract is reproduced below:
*“49. Support to the above view is also lent by Section 79 of the recently enacted Real
Estate (Regulation and Development) Act, 2016 (for short "the Real Estate Act").
Section 79 of the said Act reads as follows:‘79. Bar of jurisdiction - No civil court shall have jurisdiction to entertain any suit or
proceeding in respect of any matter which the Authority or the adjudicating officer or
the Appellate Tribunal is empowered by or under this Act to determine and no
injunction shall be granted by any court or other authority in respect of any action
taken or to be taken in pursuance of any power conferred by or under this Act.’ It can
thus, be seen that the said provision expressly ousts the jurisdiction of the Civil Court
in respect of any matter which the Real Estate Regulatory Authority, established under
Subsection (1) of Section 20 or the Adjudicating Officer, appointed under Subsection
(1) of Section 71, or the Real Estate Appellate Tribunal established under Section 43 of
the Real Estate Act, is empowered to determine. Hence, in view of the binding dictum
of the Hon'ble Supreme Court in A. Ayyaswamy (supra), the matters/disputes, which
the Authorities under the Real Estate Act are empowered to decide, are non-arbitrable,
notwithstanding an Arbitration Agreement between the parties to such matters, which,
to a large extent, are similar to the disputes falling for resolution under the Consumer
Act.
Page 9 of 20
Similarly, in Aftab Singh &Ors. v. Emaar MGF Land Ltd. &Ors. (Consumer Case No.
701 of 2015, decided on 13.07.2017), it was held that arbitration clauses in builder-buyer
agreements cannot oust the jurisdiction of consumer fora. The said view was later upheld by
the Hon’ble Supreme Court in Civil Appeal Nos. 23512–23513 of 2017. The relevant para
reads:
“25. This Court in the series of judgments as noticed above considered the provisions
of Consumer Protection Act, L986 os well as Arbitration Act, 1996 and laid down that
complaint under Consumer Protection Act being a special remedy, despite there being
an arbitration agreement the proceedings before Consumer Forum have to go on and
no error committed by Consumer Forum on rejecting the application. There is reason
for not interjecting proceedings under Consumer Protection Act on the strength an
arbitration agreement by Act, 1996. The remedy under Consumer Protection Act is a
remedy provided to a consumer when there is a defect in any goods or services. The
complaint means any allegation in writing made by a complainant has also been
explained in Section 2(c) of the Act. The remedy under the Consumer Protection Act is
confined to complaint by consumer as defined under the Act for defect or deficiencies
caused by a service provider, the cheap and a quick remedy has been provided to the
consumer which is the object and purpose of the Act as noticed above."
51.
In the present matter, there is only a clause requiring amicable discussion before
invoking remedies. Such a clause is directory at best, and cannot override or defeat the statutory
right of the Complainant to approach this Authority under the RE(R&D) Act, 2016.
Accordingly, this Authority has no hesitation in holding that the Complainant is well within its
rights to approach this forum without being first compelled to pursue an amicable settlement
under the Agreement. The objection of the Respondent as to maintainability is therefore
rejected.
Point No. 2:
Page 10 of 20
The Complainants have sought relief on the ground that there has been an inordinate
delay in handing over possession of the subject flat.
53.
It is the case of the Complainants where Agreement of Sale was executed on 12.03.2021
between the parties, clearly stipulated that possession of the subject flat would be handed over
by 31.08.2023, with a grace period of six months, ending on 28.02.2024. The Respondent has
failed to hand over possession even as on date. Further, although the project was registered
with TG RERA up to February 2025 and later extended until 07.02.2026, the project remains
incomplete.
54.
The Complainants submit that the Respondent has repeatedly given false assurances of
completion, while allottees continue to suffer. The Respondent, conversely, attributes the delay
to the Covid-19 pandemic, claiming force majeure, citing the nationwide lockdown beginning
March 2020, the impact on migrant labour, and consequential delays. The Respondent further
cites rocky terrain at the site, third-party disputes, and typographical errors in the possession
date as additional justifications.
(i)
Whether the Covid-19 pandemic can be taken as a valid shield by the Respondent
in the present case?
55.
This Authority finds no merit in such a contention. The Agreement of Sale was executed
on 12.03.2021, well after the onset and subsiding of the Covid-19 pandemic. Having
consciously undertaken such commitment, the Respondent cannot now, with retrospective
justification, rely on Covid-19 as a defence to escape its contractual and statutory obligations.
Such conduct clearly amounts to holding out false assurances with mala fide intent.
56.
It is a settled principle that once a promoter has chosen to register a project and enter
into binding contractual commitments with allottees, he does so with full knowledge of the
risks, constraints, and challenges of the market. At the time of entering into the Agreement of
Sale with the present Complainant, the Respondent was already aware of the Covid-related
disruptions, as well as the Government notifications granting moratoriums for project
completion timelines. Despite this knowledge, the Respondent chose to provide a specific
assurance of delivery by 31.08.2023 and six months of grace period.
Page 11 of 20
57.
Neelkamal Realtors Suburban Pvt. Ltd. &Anr. vs. Union of India &Ors. [2017 SCC OnLine
Bom 9302], wherein at para 119 it was categorically observed:
"While the proposal is submitted, the Promoter is supposed to be conscious of the
consequences of getting the project registered under RERA. Having sufficient
experience in the open market, the Promoter is expected to have a fair assessment of
the time required for completing the project…".
58.
The above dictum fortifies the principle that the promoter, being structurally at an
advantageous position with respect to project information and market realities, is under a
statutory duty to provide realistic timelines. The framework of the Real Estate (Regulation and
Development) Act, 2016 reinforces this obligation by mandating timely completion and
possession within the period stipulated in the Agreement of Sale.
59.
Therefore, the plea of Covid-19 as a force majeure defence in the present case is wholly
untenable. The Respondent, having executed the Agreement of Sale in March 2021 with
specific possession timelines, cannot now seek to retrospectively attribute delays to the
pandemic. Accordingly, this Authority holds that the reliance on Covid-19 as a shield stands
rejected.
ii)
60.
Extension of Registration
The Respondent has further contended that, since extensions have been granted by this
Authority, the project timeline now stands extended up to February 2026, and therefore
possession shall be delivered by then. The Complainants, however, have questioned the validity
and effect of such extensions.
61.
At the outset, it must be clarified that under the scheme of the RE(R&D) Act, 2016.
“An Act to establish the Real Estate Regulatory Authority for regulation and
promotion of the real estate sector and to ensure sale of plot, apartment or
building, as the case may be, or sale of real estate project, in an efficient and
transparent manner and to protect the interest of consumers in the real estate
sector and to establish an adjudicating mechanism for speedy dispute redressal
and also to establish the Appellate Tribunal to hear appeals from the decisions,
Page 12 of 20
The paramount objective is twofold: protection of consumer interest, and ensuring
completion of projects in an efficient manner. Denial of extension during the Covid-19
disruption would have resulted in projects being stalled, to the grave prejudice of allottees. It
was in this context that this Authority, balancing the equities, granted extensions in line with
the moratoriums issued by Telangana RERA:
1. 15.03.2020 to 14.09.2020 (Circular No.14 dated 13.05.2020),
2. 15.09.2020 to 15.03.2021 (Order No.15 dated 29.09.2020),
3. 15.03.2021 to 14.09.2021 (Order No.16 dated 01.06.2021).
63.
Accordingly, an aggregate 18 months’ extension was applied across projects to
safeguard larger consumer interest. However, it is equally well settled that such regulatory
extensions cannot dilute the contractual rights of individual allottees under their respective
Agreements of Sale, nor can they displace the statutory rights flowing from Section 18 of the
RE(R&D) Act, 2016.
64.
In the present matter, it is evident that the Respondent has unilaterally revised
possession timelines first to February 2024, and thereafter to February 2026 due to the
extension taken without consultation or consent of the Complainants. Such unilateral revisions
are impermissible. The Hon’ble Bombay High Court in Neelkamal Realtors Suburban Pvt.
Ltd. vs. Union of India &Ors. [2017 SCC OnLine Bom 9302], while upholding the
constitutional validity of RERA, categorically observed:
Para 119 “The RERA does not contemplate rewriting of contract between the flat
purchaser and the promoter."
Para 256 of this Judgment further clarifies that “by giving opportunity to the promoter
to prescribe fresh timeline under Section 4(2)(l)(C), he is not absolved of the liability
under the agreement for sale”
65.
The above dicta makes it abundantly clear that any extension granted by the Authority,
or revised timelines uploaded on the TG RERA project registration portal, do not ipso facto
Page 13 of 20
Accordingly, this Authority holds that the revised possession dates mentioned by the
Respondent, whether while seeking extensions before the Authority or as updated on the
registration portal, cannot be treated as binding on the Complainants.
(iii)Relief under Section 18 of the RE(R&D) Act:
67.
It is observed as per the records furnished before this Authority that the entire sale
consideration is for an amount of Rs. 1,00,35,000/- (Rupees One Crore and Thirty Five
Thousand Only). It is observed as per the said Agreement of Sale only an amount of Rs.
21,07,350/- (Rupees Twenty One lakh Seven Thousand Three Hundred and Fifty Only) has
been paid by the Complainant towards the sale consideration.
It is the Complainants
submission that a sum of Rs. 93,20,006/- (Rupees Ninety Three Lakh Twenty Thousand And
Six Only) has been paid towards the sale consideration amount. However, it is duly noted as
per the payment receipts produced before this Authority by the Complainant, has only paid a
sum of Rs.82,66,331/- (Rupees Eighty Two Lakh Sixty Six Thousand Three Hundred And
Thirty One Only) which amounts to over 80% of the total sale consideration amount. It is also
observed that the Agreement of Sale unequivocally stipulates that possession was to be
delivered by 31.08.2023, with a grace period of six months, i.e., up to 28.02.2024. Admittedly,
possession has not been delivered within the stipulated period.
68.
The Respondent’s contention that 90% work is complete and that the Complainants
have paid only a portion of the consideration is wholly unsustainable. The Complainants have
already paid over 90% of the agreed consideration as per their averments. Despite receiving
such substantial sums, the Respondent has failed to honour its contractual obligations. It is
manifest that the Respondent gave false assurances, being fully conscious of the market
situation, yet assuring dates of completion that it had no capacity to honour. More than months
has elapsed beyond the stipulated date, yet the project is neither complete nor possession
handed over.
69.
The Respondent further seeks to shift the burden on the complainant by contending that
the balance amount is unpaid. This plea is untenable. The law does not permit a defaulter to
Page 14 of 20
In this context, it is pertinent to note that the Agreement of Sale linked the payment
schedule to the progress of construction. While the allottees are indeed bound to adhere to the
agreed payment plan, such obligation arises only when the promoter simultaneously fulfils its
reciprocal obligation of executing construction in line with the assured progress. In the absence
of such progress, the Respondent cannot insist upon further payments as a condition to claim
relief.
71.
Section 18 of the RE(R&D) Act is categorical and unconditional. It does not make the
grant of interest contingent upon the quantum of sale consideration paid, nor does it provide
any defence to a defaulting promoter. Once delay in handing over possession is established, an
allottee who elects to remain in the project is entitled to interest for every month of delay,
irrespective of whether part or whole of the consideration has been paid, provided that the
payments already made are in accordance with the Agreement of sale. The Respondent’s plea
that only “partial sale consideration” has been paid and hence interest cannot be granted is
therefore vague, misconceived, and contrary to the express mandate of the statute. Now,
Section 18 of the RE(R&D) Act is categorical:
“(1) If the promoter fails to complete or is unable to give possession of an apartment,
plot or building,—
(a) in accordance with the terms of the agreement for sale or, as the case may be, duly
completed by the date specified therein; or
(b) due to discontinuance of his business as a developer on account of suspension or
revocation of the registration under this Act or for any other reason, he shall be liable
on demand to the allottees, in case the allottee wishes to withdraw from the project,
without prejudice to any other remedy available, to return the amount received by him
in respect of that apartment, plot, building, as the case may be, with interest at such
Page 15 of 20
This statutory right of allottee is unqualified and absolute. Attention is drawn to the
decision of the Hon'ble Supreme Court of India in Civil Appeal Nos. 3581-359 of 2022, Civil
Appeal Diary No. 9796/2019, M/s Imperia Structures Limited vs. Anil Patni & Others,
wherein it was held:
"In terms of Section 18 of the RERA Act, if a promoter fails to complete or is unable to
give possession of an apartment by the date specified in the agreement, the promoter
would be liable, on demand, to return the amount received in respect of that apartment
if the allottee wishes to withdraw from the project. Such a right of the allottee is 'without
prejudice to any other remedy available to him'. This right is unqualified, and if availed,
the deposited money must be refunded with interest as prescribed. The proviso to
Section 18(1) contemplates that if the allottee does not intend to withdraw from the
project, they are entitled to interest for every month of delay until possession is handed
over. The allottee may proceed under Section 18(1) or the proviso thereto."
73.
Similarly, in Civil Appeal Nos. 6745-6749 of 2021, M/s Newtech Promoters and
Developers Private Limited vs. State of UP & Others, the Hon’ble Supreme Court
observed:
Page 16 of 20
Further, as earlier observed, the Hon’ble Bombay High Court in Neelkamal Realtors
Suburban Pvt. Ltd. v. Union of India [(2017) SCC Online Bom 9302] clarified that RERA
registration or its extension cannot rewrite the contract between parties. The date assured under
the Agreement of Sale, executed with the allottee’s consent, shall prevail. Thus, the Respondent
is bound by Section 11(4)(a) of the RE(R&D) Act, which mandates adherence to the terms of
the Agreement of Sale.
75.
At the same time, if the Complainant has indeed defaulted in adhering to the payment
schedule, the Respondent is not without remedy. Sections 19(6) and 19(7) of the Act confer
upon the promoter a right to claim interest for delayed payments, as per Rule 15 of the
Telangana RE(R&D) Rules, 2017. Nevertheless, such entitlement shall be subject to the
Respondent producing cogent and substantive documents demonstrating both the stage-wise
progress of construction and the corresponding default, and not merely based on unilateral
assertions.
76.
In the present case, this Authority finds the Respondent in clear breach of both statutory
and contractual obligations. The Complainant is therefore entitled to interest at the prescribed
rate for the entire period of delay, i.e., from 01.03.2024 until the actual date of handing over
possession. As regards claims of compensation, this Authority notes that jurisdiction for
adjudicating compensation lies with the Adjudicating Officer under Section 71 of RE(R&D)
Act with Form ‘N’. The Complainant is at liberty to pursue such remedy separately.
77.
Accordingly, while the Complainant is entitled to relief under Section 18 of the
RE(R&D) Act, this entitlement is subject to the reciprocal statutory duty of the Complainant
to discharge any outstanding amounts under the payment plan, if not already paid. Compliance
on both sides is essential to ensure balance of obligations and timely delivery.
78.
This Authority cannot remain oblivious to the larger pattern of violations. It is noted
with grave concern that more than fifty complaints have already been received against this very
Respondent in respect of the subject project. Such repeated defaults and false assurances strike
Page 17 of 20
The Statement of Objects and Reasons of the RE(R&D) Act explicitly emphasizes
“greater accountability towards consumers and to inject transparency, efficiency, and
discipline in the real estate sector”. The conduct of the Respondent herein is in gross
derogation of that legislative mandate. If such violations are permitted to persist, the very soul
of the Act would stand diluted and the protection promised to allottees rendered illusory.
80.
Accordingly, this Authority hereby sternly warns the Respondent promoter that any
further default, non-compliance, or failure to deliver possession within the assured statutory
timelines or any fresh grievances brought to notice by allottees shall invite invocation of
Section 63 of the RE(R&D) Act, 2016.
81.
This Authority shall not hesitate to take the strictest view in future, for the RE(R&D)
Act, 2016 was enacted not as a mere regulatory framework but as a beneficial legislation to
protect innocent homebuyers from the very malaise exemplified by the conduct of this
Respondent.
82.
The Respondent is hereby directed to complete the project and hand over possession to
the Complainants within the stipulated period. It is further clarified that if the Complainants
have defaulted in making payments as per the agreed schedule, the Respondent shall be entitled
under Section 19(6) of the RE(R&D) Act, 2016 to claim interest on such delayed payments,
provided that it substantiates such claim with credible documentary evidence of both
construction progress and corresponding default.
83.
In the event the Complainants have defaulted in making payments as per the agreed
schedule, the Respondent shall be entitled, under Section 19(6) of the Real Estate (Regulation
and Development) Act, 2016, to claim interest on such delayed payments in accordance with
Rule 15 of the Telangana Real Estate (Regulation and Development) Rules, 2017.
Nevertheless, such entitlement shall be subject to the Respondent producing cogent and
substantive documents demonstrating both the stage-wise progress of construction and the
corresponding default, and not merely based on unilateral assertions.
Page 18 of 20
The Complainants are, in turn, directed to discharge any balance amounts due under
the agreed payment schedule, if not already paid. Mutual compliance is essential to ensure
timely completion and delivery of the project.
G. Directions of the Authority:
85.
In view of the findings and observations recorded hereinabove, this Authority
proceeds to issue the following directions:
a) The preliminary objection raised by the Respondent regarding the maintainability of
the complaint on account of the Dispute Resolution Clause in the Agreement of Sale
stands rejected. The complaint is maintainable before this Authority.
b) The Respondent’s reliance on the Covid-19 pandemic as a ground of force majeure is
held untenable, since the Agreement of Sale was executed after the subsiding of the
pandemic and with full knowledge of the prevailing circumstances.
c) The extension of registration taken by this Respondent cannot dilute the contractual
rights of the Complainant under the Agreement of Sale. The date of possession as
stipulated in the Agreement shall prevail.
d) The Respondent is held liable for failure to hand over possession of the subject flat by
the agreed date i.e., 28.02.2024 (inclusive of grace period).
e) The Complainants are entitled to interest at the rate of 10.7% per annum (being SBI
MCLR + 2% as per Rule 15 of the TG RE(R&D) Rules, 2017), computed on the
amounts actually paid by the Complainants, with effect from 01.03.2024 until actual
handing over of lawful possession. The exact computation shall be subject to
verification of such payments by the Respondent at the stage of effecting payment The
Respondent shall pay the arrears accrued up to the date of this Order within sixty (60)
days, and shall thereafter continue to pay the accruing interest on a monthly basis, on
or before the 10th day of each succeeding month, until possession is delivered.
f) Insofar as compensation is concerned, the Complainant is at liberty to pursue
appropriate proceedings before the Learned Adjudicating Officer under “Form N”.
g) The Respondent is hereby directed to complete the project forthwith and hand over
possession to the Complainants within the statutory timelines.
h) The Complainants are directed to pay the balance consideration strictly in accordance
with the agreed payment schedule. In the event of any default in adhering to such
schedule, the Respondent shall be at liberty to claim interest on the delayed amounts,
as provided under Rule 15 of the Telangana Real Estate (Regulation and Development)
Page 19 of 20
Having regard to the repeated defaults and the large number of complaints already
pending against this Respondent in the same project, this Authority sternly warns the
Respondent that any further delay, non-compliance, or grievance brought to notice by allottees
shall invite section 63 of the RE(R&D) Act.
87.
The complaint is accordingly allowed in part, in terms of the above directions.
88.
Failure to comply with above said directions by the Respondent shall attract penalty in
accordance with Section 63 of the RE(R&D) Act, 2016.
89.
As a result, the Complaint is disposed of accordingly. No order as to costs.
Sd/-
Sd/-
Sd/-
Sri K. Srinivasa Rao,
Sri Laxmi Narayana Jannu,
Dr. N. Satyanarayana, IAS (Retd.),
Hon’ble Member,
Hon’ble Member,
Hon’ble Chairperson,
TG RERA
TG RERA
TG RERA
Page 20 of 20
Related Orders
Interim Order Complaint No.228 of 2025
Rangareddy, Telangana, 500077)Order Complaint No. 386 of 2025
Koti, Hyderabad-500027.Order Complaint No. 153 of 2024
Telangana – 500011.Order Complaint No. 152 of 2024
Telangana – 500011.Order Complaint No. 151 of 2024
Telangana – 500011.Need Complete Property Verification?
Get ownership details, EC records, survey sketch, zone checks, geo-insights & AI analysis - all in one place